New York’s Highest Court Weighs in on N.Y. Labor Law
September 23, 2024 —
Bill Wilson - Construction Law ZoneN.Y. Labor Law § 241(6) requires owners and contractors to provide reasonable and adequate protection and safety to persons employed at or lawfully frequenting a construction site. If a worker is injured on a construction site and establishes a violation of a specific and applicable Industrial Code regulation, both the owner and contractor will be held vicariously liable for the worker’s injury, without regard to their fault and even in the absence of control or supervision of the worksite. The Court of Appeals of New York recently addressed the broad scope of the Labor Law in the context of slipping hazards.
In Bazdaric v. Almah Partners, LLC, 41 N.Y.3d 310 (2024), the plaintiff, an injured painter, slipped and fell on a plastic covering placed over an escalator in an area he was assigned to paint. The plaintiff claimed that the plastic covering was a foreign substance for purposes of Industrial Code 12 NYCRR 23-1.7(d) because it was not part of the escalator. Industrial Code 12 NYCRR 23-1.7(d) states:
Slipping hazards. Employers shall not suffer or permit any employee to use a floor, passageway, walkway, scaffold, platform or other elevated working surface which is in a slippery condition. Ice, snow, water, grease and any other foreign substance which may cause slippery footing shall be removed, sanded or covered to provide safe footing.
Read the court decisionRead the full story...Reprinted courtesy of
Bill Wilson, Robinson & Cole LLPMr. Wilson may be contacted at
wwilson@rc.com
Burlingame Construction Defect Case Heading to Trial
December 30, 2013 —
CDJ STAFFA condominium association in the Aspen, Colorado area will likely go to trial over its claims of construction defects, reports Aspen Daily News Online. According to the suit, siding and trim were improperly manufactured and installed. The homeowners engaged experts to determine the appropriate remedy, and then sought bids from contractors. Shaw Construction, which built the condos, responded with a counteroffer. Chris Rhody, the lawyer for the homeowners, said there was “a big difference” between the association’s request and the builder’s counteroffer.
According to Mr. Rhody, settlement is still possible, but seems unlikely. A date for the trial is yet to be set.
Read the court decisionRead the full story...Reprinted courtesy of
Policy's Operation Classification Found Ambiguous
May 21, 2014 —
Tred R. Eyerly – Insurance Law HawaiiProperty damage caused by a subcontractor's sheet piling was found to be within the policy's operation classification, which included "grading of land." Canal Indemn. Co. v. Margaretville of NSM, Inc., No. 13-13541 (11th Cir. April 15, 2014).
Canal issued a CGL policy to the insured. The policy had a classification limitation provision: “This insurance applies to bodily injury, property damage, personal injury, advertising injury or medical expense arising out of only those operations that are classified and shown on the Commercial General Liability Coverage Declarations . . .”
The policy's Declarations, in turn, referred to the operation classification as "Grading of Land - INCL. Borrowing, Filling or Back Filling." The policy did not define these terms.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Communications between Counsel and PR Firm Hired by Counsel Held Discoverable
March 22, 2017 —
Kevin R. Crisp, David W. Evans, & Sarah A. Marsey – Haight Brown & Bonesteel LLPCounsel handling cases involving newsworthy facts and litigation often hire public relations (“PR”) consultants. In Nicholas Behunin v. The Superior Court of Los Angeles County, 2017 DJDAR 2405 (No. B272225 March 14, 2017) the California Court of Appeal, Second District, denied a petition for writ of mandate concerning a trial court discovery order holding that communications between a plaintiff’s attorney and a public relations firm counsel hired for the purpose of creating a website for the Plaintiff were discoverable, despite claims that such communications were protected from disclosure by attorney-client privilege.
Plaintiff sued Defendants -- (the) Charles Schwab and his son Michael Schwab -- over an unsuccessful real estate investment. Plaintiff’s attorneys hired a public relations consultant to create a website (www.chuck-you.com) that sought to link the Schwabs with the late Indonesian dictator Suharto’s family. The court succinctly described the web site as “a social media campaign to induce the Schwabs to settle the case.”
Reprinted courtesy of Haight Brown & Bonesteel LLP attorneys
Kevin R. Crisp,
David W. Evans and
Sarah A. Marsey
Mr. Crisp may be contacted at kcrisp@hbblaw.com
Mr. Evans may be contacted at devans@hbblaw.com
Ms. Marsey may be contacted at smarsey@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
“Incidental” Versus “Direct” Third Party Beneficiaries Under Insurance Policies in Which a Party is Not an Additional Insured
April 18, 2023 —
Garret Murai - California Construction Law BlogAs they say, when it rains, it pours. Indemnity and insurance are the “Big Two” when it comes to risk avoidance on construction projects. The next case,
LaBarbera v. Security National Security Company, 86 Cal.App.5th 1329 (2022), involves both. It’s an interesting case, which I think could have gone either way, involving claims by a higher-tiered party that they were a third party beneficiary under an insurance policy in which they were not named as an additional insured.
The LaBarbera Case
The Indemnity Provision and Insurance Policy
In June 1016, Chris LaBarbera hired Richard Knight doing business as Knight Construction to remodel his house in Carmichael, California. The construction contract included an indemnity provision which provided that Knight would defend and indemnify LaBarbera from all claims arising out the remodeling work except for claims arising from LaBarbera’s sole negligence and willful misconduct.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
No Coverage For Construction Defects When Complaint Alleges Contractual Damages
September 01, 2011 —
Tred R. Eyerly - Insurance Law HawaiiThe underlying plaintiff’s allegations contended the contractor was in breach of contract for construction defects caused in building her home. Accordingly, the court found no coverage.See Nat’l Builders and Contractors Ins. Co. v. Slocum, 2011 U.S. Dist. LEXIS 81694 (S.D. Miss. July 26, 2011).
Slocum Construction LLC sold a home it built to Laura Peterson. Subsequently, Peterson filed suit, alleging a breach of the contract and seeking rescission and cancellation of the contract. Peterson further alleged at least thirty-three specific defects in the construction of the house.
Slocum tendered to its insurer, National Builders and Contractors Insurance Company (NBCI). NBCI filed suit for a declaratory judgment.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
Bertha – The Tunnel is Finished, but Her Legacy Continues
September 28, 2017 —
John P. Ahlers - Ahlers & Cressman PLLCThe Tunnel Boring Machine (“TBM”) known as “Bertha,” built by Hitachi Zosen Corp in Osaka, Japan, was the world’s largest TBM at 57.5 ft. in diameter. The TBM was built to drill the Seattle SR 99 Viaduct replacement tunnel. Seattle Tunnel Partners (“STP”) has a contract with the Washington State Department of Transportation (WSDOT) to dig the two-mile tunnel which is now complete.
In December of 2013, tunneling was stopped ostensibly because a 119 ft.-long, eight-inch diameter steel well casing halted the TBM. See 2/15 Blog “Bertha is Stuck and She Remains Mired in Controversy.” Reports are that WSDOT installed the pipe in 2002 to measure groundwater levels and the pipe was allegedly mentioned in the reference material provided to bidders. STP had assumed that the pipe had been removed until the steel casing got stuck in Bertha’s cutting teeth, halting progress. See 1/30/14 Blog “Big Bertha Stuck: Differing Site Condition Principles Revisited.” STP had a design-build contract with WSDOT. The contract contains a Differing Site Conditions (“DSC”) clause pursuant to which if the contractor can prove that the eight-inch pipe was an unforeseen condition (not disclosed in the contract documents), and that the unforeseen condition caused the TBM’s failure, STP is entitled to an equitable adjustment of its contract.
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers & Cressman PLLCMr. Ahlers may be contacted at
jahlers@ac-lawyers.com
Builder’s Risk Coverage—Construction Defects
August 20, 2019 —
Brian Hearst - Construction ExecutiveThis is the second of three articles bringing clarity to the complex and challenging course of construction exposures and providing solutions for mitigating risk through builder’s risk insurance coverage. Part I, Builder’s Risk Coverage – Language Matters, addressed a select few critical exposures to projects under the course of construction. Part II addresses how a standard builder’s risk policy may respond to a loss arising from defective construction and alternative insurance market offerings that can help with specific costs associated with construction defect loss.
Coverage for Loss Ensuing from Faulty Workmanship
Part I tackled the standard builder’s risk exclusion that applies to losses arising from faulty materials or workmanship. Traditionally, carriers do not have an appetite for covering a contractor’s failure to perform their work properly. There is one exception, which is coverage is available for ensuing loss – or the resulting damage to other property from faulty workmanship.
If the excluded cause of loss (i.e., faulty workmanship) causes resultant damage, the builder’s risk policy will cover the damages to the extent the peril of fire is covered. The ensuing loss exception limits the faulty work exclusion to costs directly related to repairing or replacing the faulty work.
For example, suppose faulty wiring work leads to a fire which damages part of a structure under construction. The faulty workmanship exclusion would apply to the actual faulty wiring work, but if fire is a covered peril under the policy (this is nearly always the case), the policy would respond to the structure’s fire damage.
Reprinted courtesy of
Brian Hearst, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Hearst may be contacted at