The Word “Estimate” in a Contract Matters as to a Completion Date
February 12, 2024 —
David Adelstein - Florida Construction Legal UpdatesLanguage in a contract matters. The word “estimates” or “estimated” matters particularly when it comes to a date certain such as a substantial completion or completion date. Remember this.
Here is an example.
In Parque Towers Developers, LLC v. Pilac Management, Ltd., 49 Fla.L.Weekly D190a (Fla. 3d DCA 2024), a trial court held that the developer did not complete the construction of five condominium units by the date in the purchase agreements. The developer appealed because “[t]he agreements contain no date certain for the completion of the units, but rather include a clause that ‘Seller estimates it will substantially complete construction of the Unit, in the manner specified in this Agreement, by December 31, 2017, subject to extensions resulting from ‘Force Majeure (the ‘Outside Date’).’” Parque Towers, supra. Another provision in the purchase agreements stated, “[w]henver this Agreement requires Seller to complete or substantially complete any item of construction, that item will be understood to be complete or substantially complete when so completed or substantially completed in Seller’s opinion. Id.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Building 47 Bridges in Two Years
December 23, 2023 —
Dan Sopczak - Construction ExecutiveEvery construction project has its challenges, but some truly push the boundaries of what is achievable in the heavy civil industry. When the Indiana Department of Transportation sought to modernize its I-65/I-70 North Split Interchange in Indianapolis, Indiana, its request for proposals included building 47 new bridges and rehabilitating six additional bridges on an ambitious two-year timeline—905 days to substantial completion.
“Three design-build teams responded to the RFQ, and the same three teams responded to the RFP,” according to INDOT Strategic Communications Director Natalie Garrett. “Proposals were scored and evaluated using the best-value evaluation process defined by INDOT. The score was a combination of a technical proposal score and a price score.”
Reprinted courtesy of
Dan Sopczak, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Industrialized Construction News 7/2022
August 15, 2022 —
Aarni Heiskanen - AEC BusinessThe
AEC Business newsletter’s Industrialized Construction edition in July featured the following news stories:
The Pros and Cons of Offsite Construction – A French Research Study
The study is titled The current use of industrialized construction techniques in France: Benefits, limits and future expectations. The authors are Emna Attouri, Zoubeir Lafhaj, Laure Ducoulombierb and Bruno Linéatte.
Read more
Rise of the machines? For Construction, Not Yet
Matthew Thibault’s article examines the opportunities and challenges of construction robotics. Robots can improve safety and productivity, but the ROI is still unclear to many contractors.
Read more Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Can an Owner Preemptively Avoid a Mechanics Lien?
May 25, 2020 —
William L. Porter - Porter Law GroupVarious sections of the California Civil Code, beginning with section 8000, protect the right of contractors, subcontractors and suppliers in the construction industry to obtain payment for work performed and materials supplied to construction projects. Under these statutes, unpaid claimants are entitled to use mechanics liens, stop payment notices and other methods to protect their right to payment. Mechanics liens allow unpaid claimants to sell the property where the work was performed in order to obtain payment. Stop payment notices force the owner or the bank to set money aside to pay unpaid claimants. Article XIV of our California Constitution even elevates the mechanics lien remedy to a “constitutional right”. The system generally works well, and claimants are paid.
As someone who practices and teaches construction law, I have noticed a seldom used statutory tool that seems to provide a mechanism for property owners under certain circumstances to prevent subcontractors and suppliers from imposing enforceable mechanics lien on property where work was performed. Under California Civil Code section 8520, it appears that all that an owner of property need do to avoid a mechanics lien on its property is to give a proper notice (per Civil Code section 8100 et seq.) to a person who has a mechanics lien right (a subcontractor or supplier) that the owner is invoking Civil Code section 8520 and that if the claimant is unpaid for work performed or materials supplied to the owner’s property that the claimant must either provide the owner with a stop payment notice or forfeit the right to a mechanics lien on the owner’s property. This would allow an owner to avoid a mechanics lien on its property if the claimant failed to send a stop payment notice to the owner.
Providing the “notice” under Civil Code section 8100 appears to be easy. It can be sent by “registered or certified mail or by express mail or by overnight delivery by an express service carrier”. It can even be by “hand delivery”. As far as the notice itself, it would seem that it can be very simple and easily performed under the process described below, which can be implemented within the office of any owner or developer.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Communications between Counsel and PR Firm Hired by Counsel Held Discoverable
March 22, 2017 —
Kevin R. Crisp, David W. Evans, & Sarah A. Marsey – Haight Brown & Bonesteel LLPCounsel handling cases involving newsworthy facts and litigation often hire public relations (“PR”) consultants. In Nicholas Behunin v. The Superior Court of Los Angeles County, 2017 DJDAR 2405 (No. B272225 March 14, 2017) the California Court of Appeal, Second District, denied a petition for writ of mandate concerning a trial court discovery order holding that communications between a plaintiff’s attorney and a public relations firm counsel hired for the purpose of creating a website for the Plaintiff were discoverable, despite claims that such communications were protected from disclosure by attorney-client privilege.
Plaintiff sued Defendants -- (the) Charles Schwab and his son Michael Schwab -- over an unsuccessful real estate investment. Plaintiff’s attorneys hired a public relations consultant to create a website (www.chuck-you.com) that sought to link the Schwabs with the late Indonesian dictator Suharto’s family. The court succinctly described the web site as “a social media campaign to induce the Schwabs to settle the case.”
Reprinted courtesy of Haight Brown & Bonesteel LLP attorneys
Kevin R. Crisp,
David W. Evans and
Sarah A. Marsey
Mr. Crisp may be contacted at kcrisp@hbblaw.com
Mr. Evans may be contacted at devans@hbblaw.com
Ms. Marsey may be contacted at smarsey@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Contractor Changes Contract After Signed, Then Sues Older Woman for Breaking It
September 03, 2015 —
Beverley BevenFlorez-CDJ STAFFChannel 13 Who TV reported, in Winterset, Iowa, Mary Gregory allegedly signed an estimate for hail damage repair to her home, and was later told by the contractor that it was a contract. When a crew showed up to her home to perform the work, she turned them away. Then, Gregory received a letter from an attorney demanding eight thousand dollars for breach of contract.
It turns out that the contractor altered the estimate Gregory signed and submitted it to the insurance company. According to Who TV, the altered estimate “contained work that Gregory says she didn’t authorize and a price tag of $32,134.” Jim Nelle, the contractor, admitted that he added to the contract after it was signed. He claims he was only trying to help her.
Read the court decisionRead the full story...Reprinted courtesy of
Indemnification Against Release/“Disposal” of Hazardous Materials
May 18, 2020 —
Brian S. Wood & Miranda R. Millerick - ConsensusDocsIt is very common, if not nearly an industry standard, for construction contracts and subcontracts to contain provisions addressing the discovery of unanticipated hazardous materials. Many of these provisions require a contractor or subcontractor to discontinue work where hazardous materials are discovered. An example of such a clause can be found in the American Institute of Architects (AIA) Document A201 (2017), Section 10.3.1, which states in part:
If the Contractor encounters a hazardous material or substance not addressed in the Contract Documents and if reasonable precautions will be inadequate to prevent foreseeable bodily injury or death to persons resulting from a material or substance, including but not limited to asbestos or polychlorinated biphenyl (PCB), encountered on the site by the Contractor, the Contractor shall, upon recognizing the condition, immediately stop Work in the affected area and notify the Owner and Architect of the condition.
A similar clause in ConsensusDocs does not require the contractor to stop work, but provides that the “Contractor shall not be obligated to commence or continue work until any Hazardous Material discovered at the Work site has been removed, rendered or determined to be harmless by the Owner as certified by an independent testing laboratory and approved by the appropriate government agency.”
Reprinted courtesy of
Brian S. Wood, Smith, Currie & Hancock LLP and
Miranda R. Millerick, Smith, Currie & Hancock LLP
Mr. Wood may be contacted at bswood@smithcurrie.com
Ms. Millerick may be contacted at mrmillerick@smithcurrie.com
Read the court decisionRead the full story...Reprinted courtesy of
Compliance with Contractual and Jurisdictional Pre-Suit Requirements is Essential to Maximizing Recovery
November 27, 2023 —
Michael S. Levine, Geoffrey B. Fehling & Charlotte Leszinske - Hunton Insurance Recovery BlogTimely notice is an important first step in a successful insurance recovery. But insurance policies are not always straightforward in identifying how, when, and to whom notice must be provided. Some states may also impose additional procedural hurdles, including requiring policyholders to contact their insurers before filing suit (the idea behind this requirement is that it may avoid litigation). Failing to comply with pre-suit requirements can hurt the policyholder’s recovery, as illustrated in a recent decision from the Northern District of Texas.
In NewcrestImage Holdings, LLC v. The Travelers Lloyds Insurance Company, No. 2:23-cv-039-BR (N.D. Tex. Oct. 17, 2023), the court considered whether NewcrestImage had forfeited its right to recover attorneys’ fees by failing to give Travelers pre-suit notice. NewcrestImage had filed suit against Travelers to obtain coverage for damage to its hotel property arising out of Winter Storm Uri. In its answer, Travelers asserted that NewcrestImage failed to provide the insurer with pre-suit notice as required under the Texas Insurance Code, and that if NewcrestImage successfully proved it was entitled to coverage, NewcrestImage’s failure to provide pre-suit notice precluded it from recovering attorneys’ fees. Travelers later moved to strike the claim for attorneys’ fees on that basis.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth,
Geoffrey B. Fehling, Hunton Andrews Kurth and
Charlotte Leszinske, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Fehling may be contacted at gfehling@HuntonAK.com
Ms. Leszinske may be contacted at cleszinske@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of