Supreme Court Holds Arbitrator can Fully Decide Threshold Arbitrability Issue
March 18, 2019 —
David Adelstein - Florida Construction Legal UpdatesThe United States Supreme Court recently decided parties to a contract can agree, under the Federal Arbitration Act, an arbitrator, rather than a court, can fully resolve the initial arbitrability question. Henry Schein, Inc. v. Archer and White Sales, Inc., 2019 WL 122164 (2019). The arbitrability question is whether the dispute itself is subject to arbitration under an arbitration provision. Parties that do not want to arbitrate try to circumvent this process by filing a lawsuit and asking the court to determine the threshold arbitrability question.
In Henry Schein, Inc., the contract at-issue provided:
This Agreement shall be governed by the laws of the State of North Carolina. Any dispute arising under or related to this Agreement (except for actions seeking injunctive relief and disputes related to trademarks, trade secrets, or other intellectual property) shall be resolved by binding arbitration in accordance with the arbitration rules of the American Arbitration Association. The place of arbitration shall be in Charlotte, North Carolina.
The plaintiff in this case asserted a claim for injunctive relief (among other claims) and argued that, therefore, the dispute is not subject to arbitration based on the exception in the provision. The initial, threshold issue became whether the dispute was subject to arbitration and, importantly, who decides this issue. The Court further looked at whether a trial court can resolve this issue under the “wholly groundless” exception, i.e.,the court can decide the issue if the argument for arbitration is wholly groundless.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Subcontractors Have Remedies, Even if “Pay-if-Paid” Provisions are Enforced
February 19, 2019 —
John P. Ahlers - Ahlers Cressman & Sleight PLLCIn a recent case in Kentucky[1], a sub-tier subcontractor sued the general contractor and owner for failure to pay for extra work. At the trial, the court held the subcontractor was entitled to recover under the theories of implied contracts and unjust enrichment, even though the subcontract contained a “pay-if-paid” clause. All parties appealed. In particular, the general contractor asserted that the pay-if-paid provision in the subcontract precluded recovery by the subcontractor. The issue was petitioned to the Supreme Court of Kentucky.
The question to be resolved by the Supreme Court of Kentucky was whether a pay-if-paid provision was enforceable as between a general contractor and subcontractor, and if so, whether the subcontractor could nevertheless pursue the owner directly for payment notwithstanding a lack of privity between the owner and subcontractor.
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers Cressman & Sleight PLLCMr. Ahlers may be contacted at
john.ahlers@acslawyers.com
Indiana Court of Appeals Holds That Lease Terms Bar Landlord’s Carrier From Subrogating Against Commercial Tenant
April 03, 2019 —
Gus Sara - The Subrogation StrategistIn Youell v. Cincinnati Ins. Co., 2018 Ind. App. LEXIS 497 (2018), the Court of Appeals of Indiana considered whether a landlord’s carrier could bring a subrogation claim against a commercial tenant for fire-related damages when the lease, which did not reference subrogation, explicitly required the landlord to maintain fire insurance coverage for the leased premises. The court held that subrogation was barred because the provision requiring the landlord to maintain fire insurance established an agreement to provide both parties with the benefits of insurance. The Youell case establishes that, in Indiana, if the lease explicitly states that the landlord will maintain fire casualty insurance for the building, the lease evidences an agreement by the parties to shift the risk of loss to the insurer. This agreement bars a landlord’s insurance carrier from subrogating against a commercial tenant in the event of a casualty.
In 2013, the building owner, Greg Dotson, began leasing a commercial building to Robert Youell for his tire business, Best One Giant Tire, Inc. (collectively, Youell). The lease agreement required that the landlord maintain fire and extended coverage insurance on the building and the leased premises. The lease also required the tenant to purchase fire and extended coverage insurance for its personal property. The lease did not mention subrogation. Dotson obtained a property insurance policy through Cincinnati Insurance.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and Williams LLPMr. Sara may be contacted at
sarag@whiteandwilliams.com
Don’t Forget to Mediate the Small Stuff
August 02, 2017 —
Christopher G. Hill - Construction Law MusingsIt’s been a while since I talked mediation here at Construction Law Musings. Those that read regularly (thanks) have likely missed my musings on the topic. Those who read this construction blog regularly also know that I am both a Virginia Supreme Court certified general district court mediator and a huge advocate of mediation as a method to resolve construction disputes. While many of us think of mediation as a method to resolve the major disputes or litigation that occasionally rear their heads in the course of running a construction law practice or construction business, my experience as both a construction attorney and a mediator has taught me something: mediation works for all sizes of cases.
As an advocate for my construction clients, I know that proper trial preparation requires the same diligence and attention to detail for a smaller case as it does for a larger case. While a smaller case in the Virginia general district court may not have the depositions, written discovery and motions practice that a Virginia circuit court case may have, it still requires witness preparation, document processing and review and many of the other aspects of a larger case. While construction litigation is never a money maker in the best of circumstances, in the smaller cases the attorney fees often total a larger percentage of the total potential recovery. For this reason, the small cases are almost better suited for a quick mediated resolution than the larger ones. The larger cases may cost more to prosecute or defend, but the fees are less likely to eat up such a large percentage of any recovery.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Granting of Lodestar Multiplier in Coverage Case Affirmed
November 14, 2018 —
Tred R. Eyerly - Insurance Law HawaiiThe trial court's use of a multiplier in awarding fees to the insured was affirmed by the Florida Court of Appeal. Citizens Prop. Ins. Corp. v. Laguerre, 2018 Fla. App. LEXIS 11794 (Fla. Ct. App. Aug. 22, 2018).
Following Hurricane Wilma, the insured made a claim for wind damage to her insurer, Citizens. Citizens investigated the claim and paid $8,400.77. The insured then demanded an appraisal and submitted an appraisal estimate in the amount of $60,256.79. There was no response to the appraisal demand.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Building Amid the COVID Challenge
November 29, 2021 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogAt longtime client Clark Construction, Dave Beck took charge of risk management just weeks before the COVID-19 pandemic struck.
David Beck made a big career move last year—just how big, he soon learned. In January 2020, Beck became division president for risk management at Clark Construction Group, a major national builder based in Bethesda, Md., with more than 4,000 employees across the U.S. In business since 1906, Clark has grown from a small, local excavator into one of the country’s best-known providers of construction services.
Beck took up his position at Clark shortly before COVID-19 changed life for everyone. We recently reached out to him to learn how his role has evolved since then.
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Helsinki is Building a Digital Twin of the City
May 20, 2019 —
Aarni Heiskanen - AEC BusinessThe capital of Finland first tested city modeling as long back as 1987. But the most recent model of the Kalasatama district demonstrates the new state-of-the-art possibilities of this technology: creation of a highly accurate digital twin of the city.
My hosts, Helsinki’s city modeling specialists Jarmo Suomisto and Enni Airaksinen, showed me their latest projects. One of them offered a glimpse of history through a lens of the future.
With 3D glasses on, I was able to experience the unrealized city plan made by Eliel Saarinen, the father of the world-renowned architect Eero Saarinen. The virtual model in question was a digitized version of a huge physical model from 1915. Being able to stroll the streets and fly over the roofs of the imagined city really made me understand how awesome the original design was. I had seen a scale model of this same plan while it was laid in the foyer of the Museum of Finnish Architecture many years ago, but this experience was quite different.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Lessons Learned from Implementing Infrastructure BIM in Helsinki
February 07, 2018 —
Aarni Heiskanen – AEC Business BlogFinland’s capital is currently experiencing a construction boom. Old industrial citadels are turning into residential areas with new commercial centers. Consequently, Helsinki needs to build new infrastructure. To improve the efficiency and quality of infrastructure construction, the city has started using BIM, and is now learning how to get the most value from it.
Ville Alajoki, Team Leader in Helsinki’s Urban Development Division, is a keen proponent of BIM. “Infrastructure construction is still in its early stages when it comes to using BIM. For the most part, BIM implementation has not been systematic in our city yet. We tend to use it in our own structural design and often in building construction. However, in infrastructure project management, its active individuals who have set the pace,” Ville admits. He believes that the city’s strategy for 2017–2021 will spur the use of new technologies, including BIM. “Helsinki aims to be the city in the world that makes the best use of digitalization,” Mayor
Jan Vapaavuori has declared.
A good start, but there’s room for improvement.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC Business Blog Mr. Heiskanen may be contacted at
info@aepartners.fi