Practical Pointers for Change Orders on Commercial Construction Contracts
December 31, 2014 —
John E. Bowerbank - Newmeyer & DillionConstruction projects pose unique challenges, including keeping costs within budget, meeting project deadlines, and coordinating the work of numerous contractors and subcontractors in the wake of inevitable design revisions and changes to the plans. Anticipating potential project challenges and negotiating contract provisions before commencing work on a project is critical for all parties. Careful planning should reduce the number of contract disputes. This, in turn, can facilitate the completion of a project within budget and on schedule.
“Changes” Clauses in Construction Contracts
Most commercial construction contracts have a clause addressing changes to the contract. A “changes” clause typically requires the mutual agreement of the parties on the scope of any modifications to the contract, as well as the effect on the contract price and timeframe for the work to be performed. This results in what is generally referred to as a “change order.” Many projects have a large number of change orders, which can result in significant cost overruns and delays to the project if the contract contains a complicated change order process. Therefore, in order to minimize cost overruns and project delays, it is crucial to keep the change order process as simplified and streamlined as possible.
In the most basic terms, change orders memorialize modifications to the original contract, and typically alter the contract's price, scope of work, and/or completion dates. A typical change order is a written document prepared by the owner or its design professional, and signed by the owner, design professional, and affected contractors and subcontractors. An executed change order indicates the parties’ agreement as to what changes are taking place, including approval for additional costs and schedule impacts.
While the reasons for change orders and the parties initiating them may vary, all change orders have one feature in common. Effective change orders alter the original contract and become part of the contract. Therefore, from a legal standpoint, change orders must be approached with the same caution and forethought as the original contract.
Practice Pointers for Change Orders
In light of the foregoing, some practice pointers for change orders in commercial construction contracts are as follows:
- Carefully Negotiate and Draft Change Order Provisions in the Original Contract.
A carefully negotiated and drafted “changes” clause that accounts for “unexpected circumstances” or “hidden conditions” can protect the parties from downstream costly disputes.
- Immediately Address Changes by Following the Change Order Process, Including Obtaining Necessary Signatures.
Regardless if you are an owner, general contractor or subcontractor, you should address any proposed change order immediately. Even if a decision maker gives “verbal” approval to go ahead with changed work, the work should not proceed without following the change order process in the original contract. This includes making sure to obtain any necessary signatures for the change order, if at all possible.
- Analyze the Plans and Specifications to Determine Whether “Changes” are Within the Scope of the Original Contract, or Whether They are Extra Work.
Prior to entering an original contract, it is imperative that the parties review the plans and specifications for ambiguities regarding work included in the original contract, versus potential extra work that would require a change order. This is important because a careful review of the plans and specifications sometimes reveals that work believed to be a change order is, in fact, original work, or vice versa.
- Make Sure Requests and Approvals for Change Orders are Done by an Authorized Representative.
When a party requests or gives its approval to a change order, it is important to confirm the request or approval came from an authorized representative.
- Avoid Vague and Open-Ended Change Orders.
Indeed, the vaguer a change order, the more likely it can lead to a dispute. Vague and open-ended change orders, including change orders that provide for payment on a time and materials basis, can be difficult for an owner to budget and schedule. This can lead to disputes as to cost and/or time extensions.
- Oral Assurances for Payment Without a Signed Change Order May Not Be Recoverable.
When a party provides verbal assurances to another party for extra work without following the change order process, there is a much higher likelihood that disputes will occur. Although there is case law that may allow a contractor to recover for extra work in private contracts based on oral promises, the parties should avoid placing themselves in such a legal position. Notably, in public contracts, a contractor may not be able to recover for any extra work without a signed changed order, even with verbal assurances of payment from the owner.
About the Author:
John E. Bowerbank, Newmeyer & Dillion
Mr. Bowerbank is a partner in the Newport Beach office and practices in the areas of business, insurance, real estate, and construction litigation. You can reach John at john.bowerbank@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
Steel-Fiber Concrete Link Beams Perform Well in Tests
December 21, 2016 —
Nadine M. Post – Engineering News-RecordA recent series of dynamic tests demonstrates that there are several types and doses of steel-fiber reinforcement that can be used in performance-based seismic design of coupling beams—headers that link openings in concrete shear walls—to reduce rebar congestion. The tests, performed at the University of Wisconsin, are called “a step in the right direction” by the structural engineer who pioneered the use of SFR concrete.
Read the court decisionRead the full story...Reprinted courtesy of
Nadine M. Post, Engineering News-RecordMs. Post may be contacted at
postn@enr.com
Japan Quake Triggers Landslides, Knocks Power Plant Offline
September 10, 2018 —
Jeff Rubenstone - Engineering News-RecordA magnitude 6.7 earthquake occurred on the northern Japanese island of Hokkaido on Sept. 6, leaving at least seven dead and damaging buildings and structures in the region, including a 1,650MW coal-fired thermal power plant that was taken offline.
Read the court decisionRead the full story...Reprinted courtesy of
Jeff Rubenstone, ENRMr. Rubenstone may be contacted at
rubenstonej@enr.com
Attorney Writing Series on Misconceptions over Construction Defects
June 28, 2013 —
CDJ STAFFMark Wiechnik, a litigation partner at Herrick, Feinstein LLP, has started a seven-part series in which he looks at the misconceptions homeowner board members have when they’re facing construction defect lawsuits. He opens by setting the scene of unit owners “complaining of leaks, roof problems, mold and myriad of other issues”, but conflicting views on what to do about them. In his series, he looks at some of the most common mistaken assumptions and discusses how board members should respond.
Wiechnik’s first misconception examined is the claim that “we should file a homeowners warranty claim right away!” He notes that this is “rarely a good idea,” since if the building is more than two years old, the warranty will only be worthwhile if the building is near collapse. He also notes that once you file a warranty claim, “the association is precluded from ever filing a lawsuit on that issue.”
Additionally, Wiechnik points out that filing a warranty claim puts everything into the hands of an arbitrator, who gets control of the whole process and whose decision is final, whether the association is happy with the results. Further, he notes, “the program favors builders and contractors over the homeowners.”
In his second section, he looks at the fears that if the developer is bankrupt, there is no point is suing. Here he notes that the money for repairs does not come from the developer, but “from the developer’s and subcontractor’s insurance carriers.”
Read the court decisionRead the full story...Reprinted courtesy of
Rikus Locati Selected to 2024 Northern California Rising Stars!
August 05, 2024 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPCongratulations to BWB&O’s 2024 Northern California Super Lawyers Rising Stars!
BWB&O is proud to announce that Walnut Creek Associate
Rikus Locati has been selected to the 2024 Northern California Super Lawyers list as Rising Stars for his work in Personal Injury.
Super Lawyers is a rating service of outstanding lawyers from more than 70 practice areas who have attained a high degree of peer recognition and professional achievement. The objective of Super Lawyers’ patented multiphase selection process is to create a credible, comprehensive, and diverse listing of outstanding attorneys that can be used as a resource for attorneys and consumers searching for legal counsel.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
New York Construction Practice Team Obtains Summary Judgment and Dismissal of Labor Law Claims
October 01, 2024 —
Lewis Brisbois NewsroomNew York, N.Y. (August 23, 2024) – In Trujillo-Cruz v. City of New York, et al., New York Partner Inderjit Dhami, a member of New York Partner Meghan A. Cavalieri’s Construction Practice Team, recently obtained summary judgment and dismissal of the plaintiff's Labor Law §240(1), §241(6) and §200 claims dismissing the entire case against national developer and construction company clients.
The plaintiff alleged to have sustained injuries as the result of a construction site accident occurring on July 11, 2018, while in the scope of his employment as a laborer in connection with the construction/renovation of a residential apartment building in Brooklyn, New York. Specifically, the plaintiff alleged that he was injured when he was coming down from a ladder and fell on a 2”x 4”, causing him disabling injuries. The plaintiffs’ counsel articulated a $3 million settlement demand.
Labor Law §240(1) imposes absolute liability on a defendant where an injured worker engaged in the performance of covered construction work establishes that a safety device proved inadequate to shield him from elevation-related harm, and that the defendant’s failure to provide an adequate safety device proximately caused the injuries alleged. The plaintiff first testified that he stepped on the 2” x 4” after he came down off of the ladder, but his counsel then prompted him to recalibrate his testimony by asking whether the accident arose when he was coming down the ladder or after he had come down off of the ladder. The plaintiff changed his testimony, alleging that the accident arose as he was coming down the ladder and that he remained partially on the ladder when he stepped on the piece of formwork and fell. Inderjit argued that the plaintiff’s reframing of his deposition testimony was immaterial for purposes of the Labor Law § 240 (1) analysis. Irrespective of whether the plaintiff was on solid ground or had one foot on the ladder at the time of the occurrence, his Labor Law § 240 (1) claim was unavailing in that the accident did not arise as a result of the type of extraordinary elevation-related peril protected by Labor Law § 240 (1). Justice Maslow agreed and dismissed the plaintiff’s Labor Law § 240 (1) claims.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
Drafting a Contractual Arbitration Provision
February 11, 2019 —
David Adelstein - Florida Construction Legal UpdatesA recent Florida case discussing a contractual arbitration provision in a homebuilder’s contract discussed the difference between a narrow arbitration provision and a broad arbitration provision. See Vancore Construction, Inc. v. Osborn, 43 Fla.L.Weekly D2769b (Fla. 5th DCA 2018). Understanding the distinction between the two types of arbitration provisions is important, particularly if you are drafting and/or negotiating a contractual arbitration provision.
A narrow contractual arbitration provision includes the verbiage “arises out of” the contract such that disputes arising out of the contract are subject to arbitration. Arbitration is required for those claims the have a direct relationship with the contract.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
No Signature? Potentially No Problem for Sureties Enforcing a Bond’s Forum Selection Clause
March 21, 2022 —
Brian C. Padove - ConsensusDocsOne of the foundational tenets of contract law is that a party may only be bound by terms they agree to, or in other words, if the party did not sign a contract, that party cannot be bound by the terms thereof. While this principle is generally unwavering, there are certain situations in which a non-signatory to a contract may still be bound by the terms of a contract.
In particular, this non-signatory issue may arise when a payment bond claimant makes a bond claim, subsequently files a lawsuit, but the bond contains a forum selection clause different than the venue of the lawsuit and the surety seeks to enforce the bond’s forum selection clause. For example, the claimant may have filed its lawsuit against the surety in federal court, even though the bond provides language specifically mandating that no lawsuit shall be commenced by any claimant other than in a state court where the project is located. Thus, the question then becomes, can the surety enforce the forum selection clause against the claimant when the claimant did not sign the bond and/or never agreed to the terms thereof? The short answer, it depends (yes, that is a very lawyer-like answer). Given recent case law over the past decade, however, the surety has a strong argument in favor of enforcement of the forum selection clause.
Read the court decisionRead the full story...Reprinted courtesy of
Brian C. Padove, Watt, Tieder, Hoffar & Fitzgerald, LLP (ConsensusDocs)Mr. Padove may be contacted at
bpadove@watttieder.com