Coverage for Construction Defect Barred by Contractual-Liability Exclusion
July 30, 2014 —
Tred R. Eyerly – Insurance Law HawaiiRelying upon precedent from the Texas Supreme Court, the Fifth Circuit upheld the District Court's denial of coverage based upon the policy's contractual-liability exclusion. Crownover v. Mid-Continent Cas. Co., 2014 U.S. App. LEXIS 12158 (5th Cir. June. 27, 2014).
The Crownovers entered a construction contract with Arrow Development, Inc. to construct a home. Paragraph 23.1 of the contract contained a warranty-to-repair clause, which provided Arrow "would correct work . . . failing to conform to the requirements of the Contract Documents." After the work was completed, cracks began to appear in the walls and foundation of the Crownovers' home. Additional problems with the heating, ventilation, and air conditioning system caused leaking in exterior lines and air ducts inside the home.
When Arrow refused to correct the problems, the Crownovers initiated arbitration. The arbitrator found that the Crownovers had a meritorious claim for breach of the express warranty to repair contained in paragraph 23.1 of the construction contract. Damages were awarded.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Making the Construction Industry a Safer place for Women
February 22, 2018 —
Laura Parsons - CDJ STAFFWomen make up 47 percent of the total U.S. workforce yet they only hold approximately 9 percent of construction jobs nationwide. Because of this minority, women endure health and safety issues that men usually don’t, according to Safety.BLR.com’s article “OSHA renews alliance to protect women in construction.”
The main areas that women face problems in the construction industry are healthy, safety and workplace culture. Women are potentially exposed to sexual harassment, demeaning remarks, and bodily assaults. Most of personal protective equipment (PPE) and tools are made for the typical male body to use and operate and are too heavy or oversized for many women.
The National Association of Women in Construction (NAWIC) partnered with OSHA in 2013 and just renewed their alliance aiming to improve upon workplace intimidation and violence as well as sanitation and PPE. The partnership is committed “to providing NAWIC members and others with information, guidance, and access to training resources that will help them protect the health and safety of workers, and understand the rights of workers and the responsibilities of employers under the Occupational Safety and Health Act (OSH Act).” This will be achieved by the implementation of national rules, laws, and standards as well as the circulation of preventative information.
Read the court decisionRead the full story...Reprinted courtesy of
2017 Legislative Changes Affecting the Construction Industry
July 13, 2017 —
Melinda S. Gentile – Peckar & Abramson, P.C.The 2017 Florida Legislative Session recently concluded, and a number of important construction-related House Bills (HB) and Senate Bills (SB) were presented during the Session, most notably SB 204/HB 377. These Bills may impact General Contractors and Construction Managers in a number of ways, not the least of which is the period of time that a cause of action may be initiated for the design, planning or construction of an improvement.
The following construction-related Bills passed in both the House and Senate and will become law if approved by the Governor.
Senate Bill (SB) 204/House Bill (HB) 377: Relating to the Statute of Repose for causes of action based on design, planning or construction of an improvement to real property. This bill passed both the House and the Senate and was approved by the Governor on June 14, 2017. This bill becomes effective on July 1, 2017.
Read the court decisionRead the full story...Reprinted courtesy of
Melinda S. Gentile, Peckar & Abramson, P.C.Ms. Gentile may be contacted at
mgentile@pecklaw.com
Express Warranty Trumping Spearin’s Implied Warranty
March 06, 2022 —
David Adelstein - Florida Construction Legal UpdatesBe mindful of that express warranty provision in your contract. It could result in an outcome that you did not consider or factor when submitting your proposal or agreeing to your contract amount.
An express warranty could have the effect of eviscerating the argument that you performed your scope of work pursuant to the plans and specifications. In other words, the applicability of the Spearin doctrine could be rendered moot based on express warranty language in your contract that is fully within your control because you do not have to agree to that language.
Under the Spearin doctrine:
[W]hen a ‘contractor is bound to build according to plans and specifications prepared by the owner, the contractor will not be responsible for the consequences of defects in the plans and specification.’ Spearin and its progeny set forth a default rule of fundamental fairness that when a general contractor requires a subcontractor to follow certain plans and specifications, the general contractor impliedly warrants that those plans and specifications are ‘free from design defects.’ Put simply, Spearin protects subcontractors from liability for simply following the general contractor’s direction and requirements.
However, the implied warranty set forth in Spearin and its progeny may be overcome by express agreement. Where a general contractor and subcontractor expressly agree to allocate the risk of a defective product to the subcontractor, that express agreement must prevail over Spearin’s implied warranty.
Lighting Retrofit International, LLC v. Consellation NewEnergy, Inc., 2022 WL 541156 (D. Md. 2022) (internal citations omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Insurer’s Attempt to Shift Cost of Defense to Another Insurer Found Void as to Public Policy
June 09, 2016 —
Garret Murai – California Construction Law BlogWhile construction can sometimes be risky, construction litigation is almost always expensive. This volatile mix of risk and expense has made risk shifting, through indemnity and insurance, a primary goal and concern of project owners, contractors and suppliers alike. Construction insurers know this all too well and insurers, even between themselves, seek to shift risk.
As one primary insurer found, however, risk shifting provisions in their policies – specifically, one which sought to shift the cost of defense to another insurer – is not without its limitations.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
“Over? Did you say ‘over’?”
December 31, 2024 —
Daniel Lund III - LexologyThe United States Seventh Circuit Court of Appeals recently held that under the Federal Arbitration Act, an arbitrator – and not a court – is to determine the preclusive effect of an arbitrator’s earlier ruling.
In the case, insurers engaged in three reinsurance agreements had previously arbitrated concerning one of the insurer’s billing methodologies. When a similar dispute occurred years later, the victors in the first arbitration – rather than pursuing arbitration – filed in federal court in Chicago seeking to have the court declare that the prior arbitration award precluded re-arbitration of the latest dispute. The insurer on the other side of the dispute moved to compel arbitration, a motion granted by the district court. The plaintiff insurers appealed.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Failing to Release A Mechanics Lien Can Destroy Your Construction Business
May 01, 2023 —
William L. Porter - Porter Law GroupIs the title to this article possibly true? Yes, absolutely! I have seen it happen. Let me tell you how it happens so you can avoid such a result.
When contractors, subcontractors or suppliers in California construction projects are not paid they often record a mechanics lien on the property on which they worked. This is a customary accepted legal process for the claimant to secure its right to payment. The mechanics lien enables the claimant to eventually sell the property and obtain payment from the proceeds to the extent they remain unpaid. California Civil Code Section 8460 generally requires that a lawsuit to foreclose on a mechanics’ lien must be filed in court within ninety (90) days after the mechanics’ lien is recorded. If no lawsuit has been filed in court within this 90-day period, then the lien generally becomes unenforceable. Because the mechanics lien remains a cloud on the title to the property if not released, the lien claimant usually releases the mechanics lien if they have failed to meet the lawsuit deadline. Lien claimants will also release a lien and/or dismiss the foreclosure lawsuit in exchange for payment. It is rare that the property is actually sold to obtain payment. This is a brief description of the pathway to payment through the use of a mechanics lien.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Arizona Supreme Court Leaves Limits on Construction Defects Unclear
August 27, 2013 —
CDJ STAFFThe Arizona Supreme Court has determined that “non-contracting parties may bring negligence claims for construction defects because such claims are not barred by the economic loss doctrine,” as Richard Erikson writes in a Snell & Wilmer Legal Alert.
In the case of Sullivan v. Pulte Home, Pulte had built the home in 2000. The original buyer sold it to the Sullivans in 2003. The Sullivans discovered construction defects in a retaining wall in 2009. The lost their original lawsuit, but the appeals court found that if the Sullivans filed within two years of finding the damage, they could sue. The case then progressed to the Arizona Supreme Court.
Erikson points out that in an amicus brief, a number of parties in the Arizona homebuilding industry argued that “the appellate court’s ruling was commercially irreconcilable with expectations of builders, homeowners, homebuyers, engineers and architects in the construction industry.” Nevertheless, the Sullivans prevailed at court.
Erikson asks what the actual limit on construction defects must be, given that the court found for plaintiffs who discovered construction defects nine years after the home was built. “How many years after the builder finishes a home does it have to plan on defending defect claims—10, 20, 30 years?” He proposes that the Arizona legislature needs to clarify the specific limits.
Read the court decisionRead the full story...Reprinted courtesy of