Tenth Circuit Finds Insurer Must Defend Unintentional Faulty Workmanship
December 09, 2011 —
Tred R. Eyerly - Insurance Law HawaiiApplying Colorado law, the Tenth Circuit found a duty to defend construction defect claims where the faulty workmanship was unintentional. Greystone Const. Inc. v. National Fire & Marine Ins. Co., 2011 U.S. App. LEXIS 22053 (10th Cir. Nov. 1, 2011). A prior post [here] discussed the Tenth Circuit’s certified question to the Colorado Supreme Court in this matter, a request that was rejected by the Colorado court.
In two underlying cases, Greystone was sued by the homeowner for damage caused to the foundation by soil expansion. In both cases, the actual construction was performed by subcontractors. Further, in neither case was the damage intended or anticipated. Nevertheless, National Union refused to defend, contending property damage resulting from faulty construction was not an occurrence.
Relying on a Colorado Court of Appeals case, General Security Indemn. Co. of Arizona v. Mountain States Mut. Cas. Co., 205 P.3d 529 (Colo. App. 2009), the district court granted summary judgment to National Union.
On appeal, the Tenth Circuit first considered whether Colorado legislation enacted to overturn General Security could be applied retroactively. The statute, section 13-20-808, provided courts "shall presume that the work of a construction professional that results in property damage, including damage to the work itself or other work, is an accident unless the property damage is intended and expected by the insured."
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
Force Majeure, Construction Delays, Labor Shortages and COVID-19
April 06, 2020 —
Elizabeth J. Dye - Gravel2Gavel Construction & Real Estate Law BlogThe global effect of the Coronavirus disease (COVID-19) is still unknown, and the progress of many large-scale construction projects has been affected by “Shelter in Place” orders, although some states and localities have classified construction projects as “essential.” Just last Friday, New York shut down all construction, with few exceptions.
Several states have enacted gathering bans of all sizes (including Michigan, Oregon, New Mexico, Washington, New York, New Jersey, Wisconsin, Illinois, Indiana, Ohio, West Virginia, California) and more people are likely to be quarantined as widespread testing becomes available. These decisions will undoubtedly affect the supply of materials and labor necessary for construction projects.
Officials have turned to increasingly disruptive and measures to control the spread of the virus in addition to event prohibitions and school closures, including restricting people to their homes, and closing businesses that are not “essential.” While many companies have adopted mandatory telecommuting, this is an impossibility on the construction sites. Eventually, supply and labor shortages due to governmental restrictions or quarantines will affect the critical path of construction projects.
Read the court decisionRead the full story...Reprinted courtesy of
Elizabeth J. Dye, PillsburyMs. Dye may be contacted at
elizabeth.dye@pillsburylaw.com
Delaware Supreme Court Allows Shareholders Access to Corporation’s Attorney-Client Privileged Documents
August 13, 2014 —
Marc S. Casarino and Lori S. Smith – White and Williams LLPDelaware corporations may be required to turn over internal documents of directors and officers, including those of in-house counsel, where the factors enumerated in Garner v. Walfinbarger, 430 F.2d 1093 (5th Cir. 1970) weigh in favor of disclosure. In a July 23, 2014 decision of first-impression, the Delaware Supreme Court ruled in Wal-Mart Stores, Inc. v. Indiana Electrical Workers Pension Trust Fund IBEW, that the Garner doctrine applies to plenary shareholder/corporation disputes, as well as to books and records inspection actions under Section 220 of the Delaware General Corporation Law. The Garner doctrine provides that a shareholder may invade the corporation’s attorney-client privilege in order to prove fiduciary breaches by those in control of the corporation upon a showing of good cause. The non-exhaustive list of factors by which a finding of good cause should be tested are:
“(i) the number of shareholders and the percentage of stock they represent; (ii) the bona fides of the shareholders; (iii) the nature of the shareholders’ claim and whether it is obviously colorable; (iv) the apparent necessity or desirability of the shareholders having the information and the availability of it from other sources; (v) whether, if the shareholders’ claim is of wrongful action by the corporation, it is of action criminal, or illegal but not criminal, or of doubtful legality; (vi) whether the communication is of advice concerning the litigation itself; (vii) the extent to which the communication is identified versus the extent to which the shareholders are blindly fishing; and (viii) the risk of revelation of trade secrets or other information in whose confidentiality the corporation has an interest for independent reasons.”
Reprinted courtesy of
Marc S. Casarino, White and Williams LLP and
Lori S. Smith, White and Williams LLP
Mr. Casarino may be contacted at casarinom@whiteandwilliams.com; Ms. Smith may be contacted at smithl@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Court Throws Wet Blanket On Prime Contractor's Attorneys' Fees Request In Prompt Payment Case
September 03, 2015 —
Steven M. Cvitanovic & Abigail E. Lighthart – Haight Brown & Bonesteel LLPPrompt payment penalty cases do not come around very often, but when they do, there is bound to be fireworks.
In James L. Harris Painting & Decorating, Inc. v. West Bay Builders, Inc., et al. (No. C072169, filed 8/27/15), the California Court of Appeal for the Third Appellate District upheld the trial court's discretion to not award prevailing party attorneys' fees to the party who won a prompt payment dispute. California Business and Professions Code §7108.5 and Public Contract Code §§7107 and 10262 are the mechanisms for obtaining prompt payment relief in California. As shown by the outcome, it is possible to win and lose at the same time.
West Bay Builders, Inc. (“West Bay”) was the prime contractor on a school construction project for Stockton Unified School District. West Bay entered into a subcontract agreement with James L. Harris Painting & Decorating, Inc. (“Harris”) on the project. During construction there were disagreements between West Bay and Harris regarding the contractual scope of work, and Harris performed work it believed was outside the contract, believing it would be paid for the additional work. After West Bay refused to pay for the additional work, Harris left the project, and West Bay hired another subcontractor to complete the work.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP and
Abigail E. Lighthart, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com
Ms. Lighthart may be contacted at alighthart@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Performance Bond Surety Takeover – Using Terminated Contractor To Complete The Work
January 06, 2020 —
David Adelstein - Florida Construction Legal UpdatesWhen a contractor is defaulted under a performance bond, can its surety hire the same defaulted contractor to complete the work? Stated differently, can the performance bond surety engage its defaulted bond-principal in taking over and completing the same work the contractor was defaulted under? The answer is “yes” if you are dealing with a standard form AIA A312 performance bond (and other bond forms that contain analogous language), as demonstrated by the recent decision in Seawatch at Marathon Condominium Association, Inc. v. The Guarantee Company of North America, 2019 WL 4850194 (Fla. 3d DCA 2019).
In this case, a condominium association hired a contractor in a multi-million dollar contract to renovate condominium buildings. The contractor provided the association, as the obligee, a performance bond written on an AIA A312 performance bond form. During construction, the association declared the contractor in default and terminated the contractor. In doing so, the association demanded that the performance bond surety make an election under paragraph 4 of the AIA A312 bond form that gave the surety the following options:
4.1 Arrange for the CONTRACTOR, with consent of the OWNER, to perform and complete the Contract; or
4.2 Undertake to perform and complete the Contract itself, through its agents or through independent contractors; or
4.3 Obtain bids or negotiated proposals from qualified contractors acceptable to the OWNER for a contract for performance and completion of the Contract, arrange for a contract to be prepared for execution by the OWNER and the contractor selected with the OWNER’S concurrence, to be secured with performance and payment bonds executed by a qualified surety equivalent to the Bonds Issued on the Contract, and pay to the OWNER the amount of damages as described in paragraph 6 in excess of the Balance of the Contract Price incurred by the OWNER resulting from the CONTRACTOR Default; or
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Connecticut Federal District Court Again Finds "Collapse" Provisions Ambiguous
March 22, 2017 —
Tred R. Eyerly – Insurance Law HawaiiThe Federal District Court for the District of Connecticut has issued several decisions of late finding coverage for collapse despite the building not being reduced to rubble. The latest decision in this series is Metsack v. Liberty Mutual Fire Ins. Co., 2017 U.S. App. LEXIS 24062 (D. Conn. Feb. 21, 2017).
The Metsack's property was insured by Allstate under policies issued from June 27, 1991 to September 9, 2009. From September 2009 to present, Liberty Mutual issued property policies to the insureds. Mr. Metsack built the insureds' home in 1992. The concrete basement walls used concrete supplied by JJ Mottes Company.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
University of Tennessee’s New Humanities Building Construction Set to Begin
January 14, 2015 —
Beverley BevenFlorez-CDJ STAFFConstruction preparation of the Tennessee Volunteer’s $30.5 million new humanities building has begun, according to The Tennessean. The 80,000 square-foot facility will become the largest building on the university’s campus, and will feature 23 classrooms, 18 labs, 11 collaborative study areas, 56 offices, 20 adjunct faculty workrooms as well as an outdoor theater and courtyard.
“This is a significant milestone in the history of the college,” President Jerry Faulkner told The Tennessean. “This building has been on our wish list for about 12 years in terms of wanting to have this facility available, so for the first time our humanities division is going to have a home of its own.”
Read the court decisionRead the full story...Reprinted courtesy of
No Interlocutory Appeals of "Garden-Variety" Contract Disputes
March 12, 2015 —
Jesse Howard Witt – Acerbic WittColorado’s new procedure for interlocutory appeals has its limits. In the recent decision of Rich v. Ball Ranch Partnership, ___ P.3d ___, 2014 COA 6 (2015), the Colorado Court of Appeals held that Appellate Rule 4.2 does not permit interlocutory review of questions of law in “garden-variety” or “run-of-the-mill” contract disputes. This resolves a subtle question that has been lingering since Colorado first created the interlocutory appeal process four years ago.
Prior to 2011, Colorado did not permit civil litigants to seek appellate review prior to final judgment, except in a small handful of situations. As I discussed in an article at the time, this changed with the passage of C.R.S. § 13-4-102.1 and the adoption of Rule 4.2, which granted the court of appeals discretion to permit the immediate appeal of certain district court orders. These provisions allowed parties to seek interlocutory review of orders before the conclusion of a case if a district court could certify that (1) immediate review might promote a more orderly disposition or establish a final disposition of the litigation, and (2) the order involved a controlling and unresolved question of law. The rule was patterned after 28 U.S.C. § 1292(b), which provides similar relief in the federal courts.
Read the court decisionRead the full story...Reprinted courtesy of
Jesse Howard Witt, The Witt Law FirmMr. Witt welcomes comments at www.acerbicwitt.com