Charles Carter v. Pulte Home Corporation
October 12, 2020 —
Michael Velladao - Lewis BrisboisIn Carter v. Pulte Home Corp., __Cal.App.5th__(July 23, 2020), the California Court of Appeal affirmed the entry of judgment in favor of subcontractors in connection with a Complaint for Intervention based on equitable subrogation filed by Travelers Property Casualty Company of America (“Travelers”) seeking to recover defense costs incurred in defending Pulte Home Corporation (“Pulte”) in an underlying construction defect lawsuit. The parties’ dispute arose out of Travelers’ defense of Pulte as an additional insured under policies issued to four subcontractors involved in the underlying construction defect lawsuit. Several subcontractors involved in the underlying construction defect lawsuit refused to defend Pulte based on the indemnity clauses in their subcontracts. Such clauses promised to indemnify Pulte as follows:
“all liability, claims, judgments, suits, or demands for damages to persons or property arising out of, resulting from, or relating to Contractor’s performance of work under the Agreement (“Claims”) unless such Claims have been specifically determined by the trier of fact to be the sole negligence of Pulte. . . .”
Pulte eventually settled the construction defect lawsuit and its claims against all of the subcontractors. Travelers ultimately paid $320,491.82 for Pulte’s defense and recovered $164,400 from some of the subcontractors. Travelers’ intervention in the underlying lawsuit was intended to recover the remaining $156,091.82 from the subcontractors that refused to indemnify Pulte for the defense of the construction defect lawsuit. In the underlying trial, Travelers argued that the subcontractors were obligated to pay defense costs on a joint and several basis (minus what Travelers had already recovered). The trial court did not agree and held that Travelers was not entitled to equitable subrogation for the remaining defense costs.
Read the court decisionRead the full story...Reprinted courtesy of
Michael Velladao, Lewis BrisboisMr. Velladao may be contacted at
Michael.Velladao@lewisbrisbois.com
Five Construction Payment Issues—and Solutions
October 03, 2022 —
Michael Bignold - Construction ExecutiveSales are important for construction companies that want to succeed. However, while companies certainly need to spend time on sales and marketing, having a full order book is only part of the equation. They still need to do the work and, even more importantly, they need to be able to collect payment from customers.
Here are common payment issues in the construction industry and what leaders can do to prevent or mitigate them.
1. Change Order Disputes
If a project goes exactly as planned and quoted, billing the customer is a fairly simple matter. However, it’s very rare that any job goes exactly according to the quote in the construction business. Change orders, omissions and additions are typical on jobs of any size across the industry. If contractors are not handling those changes properly by getting everything in writing, they could be in trouble when the time comes to send invoices.
Reprinted courtesy of
Michael Bignold, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Anti-Concurrent Causation Clause Eliminates Loss from Hurricane
September 06, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe court found the insured was not covered for losses caused by Hurricane Laura due to the implementation of the policy's anti-concurrent causation clause. Aegis Sec. Ins. Co. v. Lejeune, 2021 U.S. Dist. LEXIS 106804 (W. D. La. June 7, 2021).
At the time of the hurricane, the insureds' home was covered by a manufactured home insurance policy issued by Aegis. The policy excluded coverage for damage "caused by, contributed to or aggravated by" flooding. The policy's anti-concurrent causation clause read, "We do not pay for loss to the types of property covered under this policy caused by any of the following. Such loss is excluded regardless of any other cause or event contributing concurrently or in any sequence to the loss." The policy's exceptions followed.
After the storm, the insureds submitted their claim. Aegis filed suit for declaratory judgment. Aegis relied upon reports that the manufactured home and barn owned by the insureds were damaged by winds, then displaced and destroyed by storm surge associated with the hurricane. The home first sustained damage from the storm's high winds before it was displaced from its concrete piers by a 12 to 16 foot storm surge.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Will They Blow It Up?
March 28, 2012 —
CDJ STAFFThe issues concerning the Harmon Towers building in Las Vegas continue to make their way through the courts. As we noted in a previous piece, Cook County building officials stated that the building could be a hazard if Las Vegas were struck by an earthquake. The question of whether the building will continue to stand is just one of the issues in front of a judge.
MGM Resorts International argued at a March 13 hearing for permission to implode the Harmon hotel building. They claim that more than 1,700 defects have been discovered in the building and that the building is a public safety hazard. Arguing against demolition, Perini Building Company, the general contractor for the hotel, and its subcontractors are claiming that imploding the building would destroy evidence and prejudice juries in the ongoing construction defect claims. They claim that MGM Resorts wishes to abandon the building due to the economic slowdown. Perini Corp, the contractor for the project, claims that the building can be fixed. Perini claims that MGM’s position in the construction trial would be improved if the building is demolished.
After Judge Elizabeth Gonzalez heard the four days of testimony on the Harmon Towers building and whether it should be demolished, she scheduled more testimony, with two days in April and an entire week in July. Judge Gonzalez will be deciding whether the building will be torn down, imploded, or left in place.
Read the full story…
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Infrastructure Money Comes With Labor Law Strings Attached
July 25, 2022 —
Cheryl Behymer, Patrick M. Dalin & Collin Cook - Construction ExecutiveThe federal government has committed to spending $1 trillion under the Infrastructure Investment and Jobs Act on nationwide construction, alteration and repair projects. Billions of dollars have already been deployed on projects to improve highways, bridges, airports, electrical infrastructure and drinking water distribution, and the government is poised to spend the remaining funds on a massive infrastructure build-out over the next five years. While federal government contracts may provide a lucrative and reliable stream of revenue for construction companies, contractors must be prepared to comply with special requirements, particularly under the labor and employment laws enforced by the U.S. Department of Labor (USDOL).
1. The Davis Bacon Act Requires Payment of Prevailing Wages and Fringe Benefits
The Davis Bacon Act (DBA) applies to most federally funded and federally assisted projects for construction, alteration or repair work. This law requires all contractors and subcontractors on a covered project to pay all “laborers or mechanics” the wages and fringe benefits that “prevail” in the locality where the work is being performed. The USDOL determines what the prevailing wages and fringe benefits are for each trade and publishes them in wage determinations that should be issued to all contractors on the project.
Reprinted courtesy of
Cheryl Behymer, Patrick M. Dalin & Collin Cook, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Competition to Design Washington D.C.’s 11th Street Bridge Park
May 07, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to Architect Magazine, eighty landscape architecture and architecture firms (forty teams) submitted proposals to design the $25-million Washington D.C. 11th Street Bridge Park project. A jury has shortlisted six design teams: “Wallace Roberts & Todd (WRT)/Next Architects, Piet Oudolf with Glenn LaRue Smith/PUSH Studio/WXY Architecture + Urban Design, OLIN/OMA, Workshop: Ken Smith Landscape/Davis Brody Bond, Stoss Landscape Urbanism/Höweler + Yoon Architecture, and Balmori Associates/Cooper, Robertson & Partners.”
The “nonprofit Building Bridges Across the River at THEARC (Town Hall Education Arts Recreation Campus) and the District's Office of Planning” launched the competition in March of this year. Architect Magazine stated that “the goal of” the project is to unify “what some call a ‘long-divided city,’ by connecting Capitol Hill and Anacostia, the neighborhoods on either side of the river.”
Read the court decisionRead the full story...Reprinted courtesy of
OPINION: Stop Requiring Exhibit Lists!
September 18, 2023 —
Todd Heffner - The Dispute ResolverYou are conducting the final hearing of a high-dollar construction arbitration. Opposing counsel hands you the next document that counsel plans to use in questioning the witness on the stand. You notice that the document is bates stamped but has no exhibit number. So, you quickly consult opposing counsel’s exhibit list and – gasp – you find that the document is not on the list. What do you do? Do you object?
Assuming this is not your first construction arbitration hearing, you do not object. Why? Because your objection would be futile. Construction arbitrators simply do not exclude evidence on the basis that it does not appear on an exhibit list. (Evidence not produced in discovery or otherwise previously provided might be a different case.) In an informal poll of a dozen construction lawyers conducted by this author, not one reported evidence being excluded solely because it did not appear on an exhibit list. This remained true even when the applicable case management order purported to prohibit the introduction of evidence not on an exhibit list. Thus, to be used in an arbitration hearing, documents must appear on an exhibit list, unless they don’t, in which case you can use them anyway. So far, so pointless.
Read the court decisionRead the full story...Reprinted courtesy of
Todd Heffner, Troutman PepperMr. Heffner may be contacted at
todd.heffner@troutman.com
Pennsylvania Supreme Court Denies Review of Pro-Policy Decision
October 22, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to McCarter & English, LLP, “product manufacturers relied on commercial general liability policies to defend and indemnify them for product liability claims,” however, in result of the Pennsylvania Supreme Court’s decision in Kvaerner Metals Division of Kvaerner U.S., Inc. v. Commercial Union Ins. Co., 908 A.2d 888 (Pa. 2006), “[i]nsurers began denying coverage to Pennsylvania companies – and companies around the country – arguing that a design or manufacturing defect was not an ‘accident.’” McCarter & English, LLP reported that “the tide has begun to turn, and product manufacturers may once again be reliably protected by from product liability claims.”