Investigators Explain Focus on Pre-Collapse Cracking in Florida Bridge
June 06, 2018 —
Scott Judy & Richard Korman - Engineering News-RecordThe National Transportation Safety Board's preliminary report on the fatal collapse in March of a pedestrian bridge at Florida International University in Sweetwater focuses attention on the widely discussed pre-collapse cracking in the main span. The report also confirms accounts about what the construction crew working on the bridge was doing before the structure fell.
Reprinted courtesy of
Scott Judy, ENR and
Richard Korman, ENR
Mr. Judy may be contacted at judys@enr.com
Mr. Korman may be contacted at kormanr@enr.com
Read the court decisionRead the full story...Reprinted courtesy of
Las Vegas Sphere Lawsuits Roll On in Nevada Courtrooms
October 02, 2023 —
Richard Korman - Engineering News-RecordBig concerts have yet to start at Las Vegas’ distinctive new ball-shaped entertainment venue, but the legal noise over its construction has been heard in Clark County courtrooms for more than two years.
Reprinted courtesy of
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Apartment Construction Increasing in Colorado while Condo Construction Remains Slow
March 12, 2014 —
Beverley BevenFlorez-CDJ STAFFDennis Huspeni writing for the Denver Business Journal reported that Colorado is having a surge of new apartment construction, but very little condominium building. According to Huspeni, “some business leaders and government officials worry that Colorado’s construction defect laws” are the reason for the lack of condominium construction.
Huspeni in the Denver Business Journal alleged that there is a large “liability risk for builders, developers and subcontractors” because current state laws “make it easier for homeowners’ associations to file large, class-action lawsuits against builders for construction problems associated with new condominiums.”
Huspeni spoke with John Batug, senior vice president and regional manager of Wells Fargo’s community banking real estate group, who stated that condo development usually occurs at the same rate as apartment development. Batug alleged that construction defect litigation “seems to have pushed that component of the market out.”
A bill that is supposed to “jump-start” the “condominium construction sector will be introduced this session, but its sponsor said he remains unsure what types of legal reform will be a part of it,” reported Ed Sealover in the Denver Business Journal.
Lakewood Mayor Bob Murphy told Sealover that “city and business leaders would like to see two particular changes in the law: 1.They want to require a super-majority of condo owners to have to agree to legal action before any lawsuit is filed — instead of just needing two of them to move forward. 2.They want a requirement to attempt some sort of alternative dispute resolution before a suit can be filed.”
However, not everyone is in favor of the proposed suggestions. Jonathan Harris, vice president of The Point Homeowners Association, told Sealover that the “bill that the Metro Mayors Caucus wants ignores the fact that arbitration can be an expensive process for property owners.”
Read the full story, Huspeni Article...
Read the full story, Sealover Article... Read the court decisionRead the full story...Reprinted courtesy of
Couple Claims Poor Installation of Home Caused Defects
December 30, 2013 —
CDJ STAFFRobert and Tracy Samosky of Spanishburg, West Virginia have filed a lawsuit claiming that the improper delivery of their modular home caused defects and damages, preventing them from actually using their home. The couple purchased a modular home from J&M Quality Construction for a home designed and built by Mod-U-Kraf Homes. They are suing the two firms for $50,000 in damages, reports the West Virginia Record.
Read the court decisionRead the full story...Reprinted courtesy of
An Architect Uses AI to Explore Surreal Black Worlds
October 24, 2023 —
Kriston Capps - BloombergFor architect Curry Hackett, the appeal of using artificial intelligence to design projects isn’t to build the world of the impossibly distant future. Instead he wants to mine the near present, using machine learning to generate postcards from a world that is recognizably our own, but refracted through a lens of Black history and material design.
Hackett is the designer behind a series of provocations made using AI to remix Black vernacular architecture in kaleidoscopic Afrofuturist landscapes. Specifically, he’s assembling images with Midjourney, an AI tool favored by architects to imagine what buildings might look like. Hackett’s prompts result in straightforward yet surreal sets, including roadside Popeyes kiosks in rural North Carolina, homes with inflatable porches in the Florida panhandle and park benches made out of the couch from grandma’s living room. Quilts, basket weaving and other cultural modes associated with American South are the building materials for Hackett’s speculative futures.
Read the court decisionRead the full story...Reprinted courtesy of
Kriston Capps, Bloomberg
Chimney Collapses at South African Utility’s Unfinished $13 Billion Power Plant
November 21, 2022 —
Paul Burkhardt - BloombergSouth Africa’s newest coal-fired power plant, which has been under construction since 2008 and will cost an estimated 232 billion rand ($12.7 billion), shut one of its six generating units after a duct collapsed.
The unit at the Kusile plant could remain offline “for a few months” although a clearer estimate will be known over coming weeks, state-owned utility Eskom Holdings SOC Ltd. said in a statement late Wednesday. The outage comes as the country endures record blackouts -- locally known as loadshedding.
The duct appeared to have sheared off from the unit’s main structure, a photo posted on Twitter by Anton Eberhard, a professor at the University of Cape Town’s Graduate School of Business, showed.
Read the court decisionRead the full story...Reprinted courtesy of
Paul Burkhardt, Bloomberg
Florida Appellate Courts Holds Underwriting Manuals are Discoverable in Breach of Contract Case
February 14, 2022 —
Andrea DeField & Adriana A. Perez - Hunton Insurance Recovery BlogRecently, Florida’s First District Court of Appeals handed down a victory for policyholders when it affirmed a Circuit Court’s order compelling an insurer to produce its underwriting manual in a breach of contract action. In People’s Trust Insurance Co. v. Foster, No. 1D21-845 (Fla. 1st DCA Jan. 26, 2022), the policyholder, Mr. Foster, filed a breach of contract claim against his insurer, People’s Trust, after People’s Trust failed to pay his insurance claim for damage caused to Mr. Foster’s home due to a leaking water pipe. People’s Trust denied Foster’s claim because “Foster’s pipe damage predated the policy’s inception.”
During discovery Foster requested People’s Trusts’ underwriting manual(s) in effect at the time his policy was issued or renewed. People’s Trust objected to the request. In response, Foster filed a motion to compel production of the underwriting manual(s). After a hearing, the Circuit Court granted Foster’s motion and People’s Trust sought a writ of Certiorari from the First District Court of Appeal to quash the order compelling production.
Reprinted courtesy of
Andrea DeField, Hunton Andrews Kurth and
Adriana A. Perez, Hunton Andrews Kurth
Ms. DeField may be contacted at adefield@HuntonAK.com
Ms. Perez may be contacted at pereza@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Delays in Filing Lead to Dismissal in Moisture Intrusion Lawsuit
September 09, 2011 —
CDJ STAFFThe Alabama Court of Civil Appeals has upheld a summary judgment in the case of Franklin v. Mitchell. Walter Mitchell, doing business as Southern Classic Construction built a new home for the Franklins. The Franklins moved into the home in October 2001. In April 2006 they discovered sagging floors in both the bathroom and kitchen. They contacted Mitchell who suggested the flooring might be defective. The Franklins spent eight months attempting to contact the flooring manufacturer.
In March 2007, the Franklins had the home inspected. The sagging was determined to be due to a loss of strength in the decking because of condensation from the air conditioning system. Air returns were not properly sealed and drawing moisture into the structure. There was mold on the decking and floor joints.
When Mitchell was contacted by the Franklins, he told them his one-year warranty had expired but had the HVAC subcontractor, Southern Mechanical Heating & Air (owned by Mitchell’s father, Jim Mitchell), look at the situation. SMHA replaced and braced subfloors. Later, they entered the crawl space to tape ducts, seal the air return, and insulate the air vent housing. The Franklins were not satisfied with the repairs, as not all the ducts were taped, nor were the air vent housings insulated.
Franklin complained to Walter Mitchell who again cited his one-year warranty. Jim Mitchell said he would not report complaints to his insurer, stating that the repairs were unnecessary, that the work had been done correctly in the first place, and it was only done at the request of Walter Mitchell.
In February 2009, the Franklins sued Walker Mitchell. Mitchell denied the claims, citing in part the statute of limitations. Mitchell also filed complaints against three subcontractors, including his father’s firm. Mitchell received a summary judgment as the case started after Alabama’s six-year statute of limitations.
The appeals court rejected the Franklin’s argument that the claim of damage did not start until they were aware it was due to a construction defect. The court noted that as Walter Mitchell was licensed as a “residential home builder, the statute the Franklins cite did not apply, as it concerns architects, engineers, and licensed general contactors.”
Nor did they feel that Mitchells’ claim that his warranty had expired were sufficient to override the statute of limitations, quoting an earlier case, “Vague assurances do not amount to an affirmative inducement to delay filing suit.” Their claim of subsequent negligent repairs was rejected because Mitchell did not direct the specific actions taken by his father’s firm.
Read the court’s decision…