Colorado Senate Bill 13-052: The “Transit-Oriented Development Claims Act of 2013.”
January 25, 2013 —
CDJ STAFFLast fall the Denver Regional Council of Governments approached the Colorado Association of Home Builders to inquire as to why there are no builders developing or constructing for-sale, multi-family projects along the newly constructed light rail lines. By surveying its membership, the CAHB quickly learned that the biggest impediment to such construction is Colorado’s litigation environment, i.e., “if you build it, they will sue.” This started a dialogue within the industry in order to determine what changes developers and general contractors would like to see made in order to consider again building for-sale, multi-family construction. The result of this dialogue is Senate Bill 13-052, introduced on January 16, 2013, and known as the Transit-Oriented Development Claims Act of 2013, sponsored by Senators Scheffel and Cadman and Representative DelGrosso. You can find the current iteration of SB 13-052 here.
Read the court decisionRead the full story...Reprinted courtesy of
David McLainMr. McLain can be contacted at
mclain@hhmrlaw.com
Seventh Circuit Remands “Waters of the United States” Case to Corps of Engineers to Determine Whether there is a “Significant Nexus”
July 10, 2018 —
Anthony B. Cavender - Gravel2Gavel Construction & Real Estate Law Blog On June 27, the U.S. Court of Appeals for the Seventh Circuit decided the case of Orchard Hill Building Co. v. U.S. Army Corps of Engineers. The Court of Appeals vacated the decision of the District Court granting the U.S. Army Corps of Engineers’ (Corps) motion for summary judgment dismissing the Orchard Hill Building Company’s (Orchard) complaint that the Corps’ jurisdictional determination erroneously found that the waters at issue were “jurisdictional waters” under the Clean Water Act (CWA) subject to the Corps’ jurisdiction. Acknowledging that the Corps and EPA had promulgated a new rule re-defining “waters of the United States” in 2015—which is now being challenged in the courts—the Court of Appeals noted that this case is controlled by the pre-2015 definition of “waters of the United States.” The Court of Appeals remanded the case to the Corps, directing it to determine if there was a significant nexus, as required.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, Pillsbury Winthrop Shaw Pittman LLPMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Pandemic Magnifies Financial Risk in Construction: What Executives Can Do to Speed up Customer Payments
August 23, 2021 —
Lori J. Drake - Construction ExecutiveConstruction businesses are waiting longer for payment in 2021, according to the newly released 2021 Construction Cash Flow and Payment Report conducted by Levelset.
According to respondents, only 10% of construction businesses get paid in full, which is a 75% drop from 2020, and only 9% get paid on time, which is a drop of 60% over last year.
The report, based on a survey of 764 construction professionals, illustrates that financial risk in the industry flowed down the payment chain. General contractors were four times more likely to get paid in 30 days, and 50% more likely to get paid in full. However, 20% of subcontractors, suppliers and other second-tier companies were kept waiting more than 60 days to collect payment.
Reprinted courtesy of
Lori J. Drake, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Illinois Earns C- on its 2022 Infrastructure Report Card while Making Strides on Roads and Transit
May 02, 2022 —
American Society of Civil EngineersChicago, Ill. – The Illinois Section of the American Society of Civil Engineers (ASCE) today revealed its 2022 Infrastructure Report Card, giving the state an overall grade of C-. Illinois' civil engineers studied eleven infrastructure categories. Of those eleven, six categories are in mediocre condition, and five categories are in poor condition.
The committee representing more than 2,700 civil engineers across Illinois collected and analyzed data and based its grades on eight criteria, including condition, funding, public safety and resilience. As a major hub for our nation's infrastructure, Illinois has taken considerable steps to improving its transportation and infrastructure networks and several major categories showed improvements – notably transit and roads.
To view the report card and all eleven categories evaluated, visit https://infrastructurereportcard.org/state-item/Illinois/.
ABOUT THE ILLINOIS SECTION OF THE AMERICAN SOCIETY OF CIVIL ENGINEERS
Civil engineering experts in their respective fields from the Illinois Section of ASCE, with assistance from the Central Illinois Section, Quad Cities Section, and the St. Louis Section, prepared The Report Card for Illinois' Infrastructure. The Report Card is created to educate and advise our elected officials and citizens on the condition of our State's infrastructure using sound engineering evaluation criteria and to provide recommendations on how to raise the grade. Since 1915, the Illinois Section has represented Civil Engineers in America's engineering hub and the organization recently celebrated its Centennial Anniversary. ASCE provides a platform for our members to mentor, learn and teach, which enables us to serve as stewards of infrastructure in our state, nation and throughout the world.
Read the court decisionRead the full story...Reprinted courtesy of
Parol Evidence can be Used to Defeat Fraudulent Lien
March 27, 2019 —
David Adelstein - Florida Construction Legal UpdatesParol or extrinsic evidence can be used to defeat an argument that a lien is a fraudulent lien. And, just because a lien amount exceeds the total contract amount does not presumptively mean the lien is willfully exaggerated or recorded in bad faith. Finally, a ruling invalidating a construction lien can create the irreparable harm required to support a petition for writ of certiorari. All of these issues are important when dealing with and defending against a fraudulent lien and are explained in a recent case involving a dispute between an electrical subcontractor and its supplier.
In Farrey’s Wholesale Hardware Co., Inc. v. Coltin Electrical Services, LLC, 44 Fla.L.Weekly D130a (Fla. 2d DCA 2019), there were various revisions to the supplier’s initial purchase order, both from a qualitative and quantitative perspective, and a ninth-revised purchaser order was issued and accepted. The electrical subcontractor claimed that deliveries were late, unassembled, and did not include the required marking (likely the UL marking), to pass building inspections. As a result, the subcontractor withheld money from the supplier and the supplier recorded a lien in the amount of $853,773.16 and filed a foreclosure lawsuit.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Hartford Stadium Controversy Still Unresolved
September 22, 2016 —
Scott Van Voorhis - Engineering News-RecordThe Hartford Yard Goats and the city of Hartford, Conn., say Arch Insurance—the surety for the dual developer/prime contractor of the minor-league baseball team’s new, unfinished stadium—has committed to helping complete the project now that the team and its developer have acrimoniously split.
Read the court decisionRead the full story...Reprinted courtesy of
Scott Van Voorhis, Engineering News-RecordENR may be contacted at
enr.com@bnpmedia.com
The Air in There: Offices, and Issues, That Seem to Make Us Stupid
October 28, 2015 —
Eric Roston – BloombergIt's tempting to conclude from the climate change debate that all that carbon dioxide in the air is making everybody dumber.
In fact, all that carbon dioxide in the air is making everybody dumber.
Workers showed diminished cognitive functioning after spending several hours in office air that had normal levels of CO2 and chemical pollutants and ordinary ventilation, in a study published this week in Environmental Health Perspectives. Researchers tinkered with the levels of carbon dioxide and volatile organic compounds (airborne chemicals) and the amount of outside air pumped in, while the subjects did their regular work, though at a Syracuse University lab. The levels were chosen to simulate the indoor environment of conventional offices, LEED Platinum "green" buildings, and green buildings with an elevated outdoor ventilation rate ("Green+"). The 24 participants, including architects, engineers, and marketing professionals, were exposed to different conditions on different days during the six-day study, not knowing of the changes.
At 3 pm every day, the researchers administered computer-based cognitive tests of strategy-setting and focus, for example, and recorded the results and the kind of air the participants had been breathing. A day spent in the air of an extra-ventilated green building correlated with the best performance on the tests. Participants performed 61 percent better in green-building air than in conventional air, and 101 percent higher in the Green+ scenario. The research was supported in part by a United Technologies gift to Harvard's T.H. Chan School of Public Health. United Technologies, which makes building systems, wasn't involved in the experiment itself.
Read the court decisionRead the full story...Reprinted courtesy of
Eric Roston, Bloomberg
Is a Text a Writing?
June 10, 2024 —
Michael Yelle - Ahlers Cressman & Sleight PLLCIs a text message a writing? Project communication is constantly evolving, and text messages are an increasingly common way teams share pictures, video, and provide project updates. When texting is part of the communication flow on a project, contractors and owners might text approvals for extra work, notices of changed conditions, or other information that could be a basis for a change order.
In a text exchange about a compensable event, the notice, reply, and approval are all saved on the phone. But contracts often contain specific requirements for a contractor or subcontractor to request changes and authorization to proceed may be specifically required in writing.
For example, the Associated General Contractors of Washington – 2018 Standard Subcontract says the “Subcontractor shall make no claims for extras unless the same shall be agreed upon
in writing by Contractor prior to performance of any such extra work.” (emphasis added).
The AGC subcontract doesn’t define “writing,” so the subcontractor and contractor might wonder if a text message exchange about a potentially compensable event was an “agreement in writing.”
Read the court decisionRead the full story...Reprinted courtesy of
Michael Yelle, Ahlers Cressman & Sleight PLLCMr. Yelle may be contacted at
michael.yelle@acslawyers.com