Contracts and Fraud Don’t Mix (Even for Lawyers!)
August 24, 2020 —
Christopher G. Hill - Construction Law MusingsIn prior posts here at Construction Law Musings, I have discussed how fraud and contracts are often like oil and water. While there are exceptions, these exceptions are few and far between here in Virginia. The reason for the lack of a mix between these two types of claims is the so-called “source of duty” rule. The gist of this rule is that where the reason money is owed from one party to another (the source of the “duty to pay”) is based in the contract, Virginia courts will not allow a fraud claim. The rule was created so that all breaches of contract, claims that are at base a failure to fulfill a prior promise and could, therefore, be considered to be based on a prior “lie,” would not be expanded to turn into tort claims. This rule has been extended to claims that most average people (read, non-lawyers) would consider fraud because there was no intent to fulfill the contract at the time it was signed.
Just so you don’t think that lawyers are exempt from this legal analysis, I point you to a recent case where a law firm sued a construction client of theirs for failure to pay legal fees. In EvansStarrett PLC v. Goode & Preferred General Contracting, the Fairfax County Circuit Court considered a motion by the Plaintiff law firm seeking to add a count of fraud to its breach of contract lawsuit. The Court considered the following facts.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
The Unthinkable Has Happened. How Should Contractors Respond?
May 11, 2020 —
Bruce Orr - AEC BusinessAny construction veteran expects the economy to contract and expand. However, the global pandemic presents contractors with a challenge unlike any in recent memory.
How should they respond in an environment of such uncertainty? For some perspective, I chatted with Dr. John Killingsworth, a construction management professor at Colorado State University who has conducted extensive research on how contractors can weather economic downturns.
BRUCE ORR: John, let’s say you’re in IT or are a c-suite executive at a contracting firm. This event has occurred. What are some of the questions you should be asking right now?
JOHN KILLINGSWORTH: For starters, we have to acknowledge that the uncertainties are so tremendous that many contractors have no choice but to be reactive in the short term. They’re literally not sure whether particular job sites will be open or closed tomorrow or whether they’ll go to work next week. They’re also looking at predictions—from highly qualified statisticians, public health officials and others—that are just all over the map due to the limited nature of the data we have at hand.
Read the court decisionRead the full story...Reprinted courtesy of
Bruce Orr, AEC BusinessMr. Orr may be contacted at
bruce@pronovos.com
Water Damage: Construction’s Often Unnoticed Threat
November 02, 2020 —
Yaron Dycian - Construction ExecutiveFire damage to commercial buildings might get headlines, but water damage, whether to projects under construction or completed buildings, delivers massive financial blows to owners, developers and contractors. The impact is massive, reaching many billions of dollars per year. One water leak on the 19th floor at a construction site of a high-end apartment building in New York City resulted in $30 million in property damage and millions in delayed delivery penalties.
Imagine this all-too-typical scenario: A 20-story building has thousands of pipe connections and many tens of thousands throughout the entire building. It only takes one of those joints failing, perhaps due to human oversight. Early on a Saturday morning when no one is onsite, one of the connections inside a wall begins to leak, slowly at first. In a couple hours the connection fails completely, sending a cascade of water into the building. The site is located next to a highway, so the security guards don’t hear the water flowing.
The leak goes undetected until crews come back onsite on Monday morning. By that point, lower levels of the building have been inundated with thousands of gallons of water that has destroyed construction material, carpeting and electrical switchgear. It’s flowed into the elevator pits and mechanical room.
Reprinted courtesy of
Yaron Dycian, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Dycian may be contacted at
yaron@wint.ai
Angelo Mozilo Speaks: No Regrets at Countrywide
September 03, 2014 —
Max Abelson – BloombergSix years after he lost control of the largest mortgage lender in the U.S., and days after news that the U.S. Attorney’s Office in Los Angeles plans to sue him, the Countrywide Financial Corp. founder is baffled by a new effort to punish him, proud of past triumphs and incensed by criticism.
“You’ll have to ask those people, ‘What do you have against Mozilo, what did he do?’” he said in a 30-minute call with Bloomberg News before Labor Day, one of his few interviews since the firm’s downfall. “Countrywide didn’t change. I didn’t change. The world changed.”
Interviews with Mozilo, 75, and three friends show what retirement looks like for a chief executive officer linked to the worst financial crisis since the Great Depression. Remaining out of public view like Lehman Brothers Holdings Inc.’s Richard Fuld or Jimmy Cayne of Bear Stearns Cos., Mozilo has submitted plans for Old West-style offices in California, taught students in Italy about finance, invested in a building in the Arizona desert that houses a Taco Bell and written about his life so that his grandchildren will “know the truth.”
Read the court decisionRead the full story...Reprinted courtesy of
Max Abelson, BloombergMr. Abelson may be contacted at
mabelson@bloomberg.net
Suzanne Pollack Elected to Lawyers Club of San Diego 2021 Board of Directors
May 03, 2021 —
Suzanne Pollack - Lewis BrisboisSan Diego Associate Suzanne Pollack was recently elected to the 2021 Lawyers Club of San Diego Board of Directors for a three-year term that will begin on July 1, 2021. Founded in 1972, the mission of Lawyers Club - San Diego’s largest specialty bar association - is to advance the status of women in the law and society.
“I am honored to be joining Lawyers Club’s Board of Directors, particularly after this last year, during which we saw the dramatic impact that the pandemic had upon women in the workforce," said Ms. Pollack. "Promoting equality, diversity, and advocacy has never been more important, and I look forward to working with the Board to further these goals.”
Read the court decisionRead the full story...Reprinted courtesy of
Suzanne Pollack, Lewis BrisboisMs. Pollack may be contacted at
Suzanne.Pollack@lewisbrisbois.com
Equitable Subrogation Part Deux: Mechanic’s Lien vs. Later Bank Deed of Trust
September 15, 2016 —
Kevin J. Parker – Snell & Wilmer Real Estate Litigation BlogThis post follows, almost two years to the day, Rick Erickson’s post of August 29, 2014. As noted by Rick Erickson in his August 29, 2014 post, the Arizona Supreme Court in the Weitz case (2014) had determined that equitable subrogation principles were applicable to enable an earlier-recorded mechanic’s lien to be trumped by a later-recorded bank deed of trust, if the loan secured by the later deed of trust paid off a lien that had been ahead of the mechanic’s lien. In a decision filed August 9, 2016, the Arizona Court of Appeals further clarified the scope of such equitable subrogation.
In Markham Contracting Co., Inc. v. FDIC, No. 1 CA-CV 14-0752 (August 9, 2016), the Arizona Court of Appeals addressed a situation where a first-recorded deed of trust was followed by a second-recorded mechanic’s lien; and then, after the mechanic’s lien was recorded, a new lender made a secured construction loan that was used, in part, to pay off the loan that was secured by the first-position deed of trust. The key being “in part.” The subsequent lender loaned $4.8 million, but only $2.9 million went to pay off the balance owing on the first-position deed of trust.
Read the court decisionRead the full story...Reprinted courtesy of
Kevin J. Parker – Snell & WilmerMr. Parker may be contacted at
kparker@swlaw.com
Gordon & Rees Ranked #4 of Top 50 Construction Law Firms in the Nation by Construction Executive Magazine
July 11, 2022 —
GRSM Construction Team - Gordon & Rees Construction Law BlogGordon Rees Scully Mansukhani has been ranked as the No. 4 construction law firm in the nation by Construction Executive in the magazine’s 2022 ranking of The Top 50 Construction Law Firms™. As the only law firm with offices and attorneys in all 50 states, Gordon & Rees’ construction group (with over 150 construction lawyers) delivers maximum value to our clients by understanding their business and combining the resources of a full-service national firm with the local knowledge of a regional firm.
Led by Allen Estes and Angela Richie, the construction lawyers at Gordon & Rees are uniquely situated to serve our construction clients. We have attorneys with professional training and practical experience in related fields such as engineering and construction management, as well as lawyers with leadership experience in various construction industry related trade associations, legal advisory committees and government agencies. “If a client is looking for a legal partner in multiple states who understands their business, Gordon & Rees is that partner,” said Angela Richie.
Read the court decisionRead the full story...Reprinted courtesy of
GRSM Construction Team, Gordon Rees Scully Mansukhani
Beware: Hyper-Technical Labor Code Violations May Expose Employers to Significant Claims for Penalties under the Labor Code California Private Attorneys General Act of 2004 (PAGA)
May 10, 2017 —
Angela Reston-Nunez – Newmeyer & Dillion LLPMost employers know that companywide policies or practices that do not strictly comply with applicable state or federal employment laws can expose employers to class action lawsuits by large numbers of employees seeking recovery of massive sums in damages, attorneys’ fees and costs. Unfortunately, traditional class action lawsuits are not the only representative actions employers should be concerned with. Recent litigation trends have shown that California’s lesser known Labor Code Private Attorneys General Act of 2004 (“PAGA”) can be equally, if not more harmful to employers than class actions due to steep penalties for minor violations.
WHAT IS PAGA?
Under PAGA, “aggrieved employees” can sue employers for alleged Labor Code violations. Like class actions, a PAGA plaintiff sues on a representative basis on behalf of themselves and other workers. However, unlike class action plaintiffs, PAGA plaintiffs do not seek damages; rather, they seek civil and statutory penalties formerly recoverable solely by state agencies in enforcement actions.
The distinction between recovery of damages in class actions and recovery of penalties in PAGA actions reflects the often-insidious nature of PAGA claims. While workers have long alleged “derivative” PAGA claims for penalties in connection with more substantive underlying Labor Code violations (meal or rest break violations, for example), we have seen a recent spike in PAGA suits alleging hyper-technical Labor Code violations with no underlying substantive violation, and where the “aggrieved employees” have suffered no actual harm.
WHAT'S AT STAKE?
Equally troubling for employers is the method by which significant penalties are aggregated. With a few significant exceptions, penalties generally range from $50 to $250 per violation. At first blush, this may not seem like much, however total penalties rise rapidly when considering that calculations are made on a per-employee and a per-pay period basis.
AN EXAMPLE ON HOW PAGA WORKS
Consider the following example based on one recent case:
Issue: An employee brought a PAGA-only lawsuit on behalf of himself and 400 other “aggrieved employees” against his employer for alleged Labor Code violations.
Claim: The employee claimed the employer’s 30-year practice of paying employees 9 days after the close of the applicable payroll period violated Labor Code Section 204(d), which requires payment to be made within 7 days of the close of the payroll period. The employee claimed that, under PAGA, the employer was liable for a minimum penalty of $100 per employee, per pay period, going back at least one year (the statutory limitations period for PAGA claims).
Exposure: With 400 employees, 24 pay periods per year, and $100 per violation, the plaintiff sought a minimum of $960,000 in penalties (not including substantial attorneys’ fees, costs and interest also available under PAGA), despite offering no evidence of harm suffered by the employees or prior notice of the issue.
OTHER IMPORTANT CONSIDERATIONS
In addition to a draconian penalties scheme, there are a myriad of additional aggravating factors for employers involved in PAGA litigation, such as:
- PAGA plaintiffs are not required to meet the rigorous class certification standards required of class action plaintiffs, meaning plaintiffs’ attorneys may be more likely to bring meritless “strike suits” aimed at obtaining quick settlements based on significant alleged penalties exposure.
- 75% of PAGA penalties recovered by way of settlement or judgment are directed to the state of California, while the "aggrieved employees” only keep 25%, reinforcing the notion that PAGA claims are frequently attorneys’-fee-driven, rather than for protecting employees.
STEPS FOR EMPLOYERS TO PROTECT THEMSELVES
Fortunately, there are a number of measures employers can take prior to and during wage and hour litigation which can dramatically reduce, or even eliminate, exposure to substantial penalties and damages. This includes:
- Regular reviews. Prior to litigation, we recommend regular detailed reviews of company policies and practices in order to identify areas of possible concern and ensure compliance with California’s ever-changing labor laws.
- Take action. On receipt of a new PAGA claim, taking immediate action to remedy an alleged violation within the Labor Code’s 33-day “safe harbor” time-period may help limit an employer’s exposure, and could bar a plaintiff from filing suit at all.
- Be aggressive. Once a PAGA or class action claim is in litigation, a proactive, aggressive approach to claim evaluation, investigation and litigation is critical.
For these reasons and more, it’s in an employers’ best interest to monitor these issues closely and seek input when appropriate.
Angela Reston-Nunez is a labor and employment attorney in Newmeyer & Dillion’s Walnut Creek office. For questions regarding PAGA, class action or individual wage and hour issues, or other employment law matters, please feel free to contact Angela Reston-Nunez at (925) 988-3249 or angela.reston-nunez@ndlf.com.
About Newmeyer & Dillion
For more than 30 years, Newmeyer & Dillion has delivered creative and outstanding legal solutions and trial results for a wide array of clients. With over 70 attorneys practicing in all aspects of business, employment, real estate, construction and insurance law, Newmeyer & Dillion delivers legal services tailored to meet each client’s needs. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer & Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949-854-7000 or visit www.ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of