Once Again: Contract Terms Matter
May 11, 2020 —
Christopher G. Hill - Construction Law MusingsI know, you’ve heard this over and over again here at Construction Law Musings: courts in Virginia will interpret a contract strictly and in a manner that gives meaning to its unambiguous terms.
A recent case out of the Eastern District of Virginia federal court, White Oak Power Constructors v. Mitsubishi Hitachi Power Systems, reinforces this point. The basic facts of the case relevant to this discussion and the Court’s opinion are these. Old Dominion Electric Cooperative (ODEC) hired White Oak Power Constructors (White Oak) to build a natural gas power plant. The contract between ODEC and White Oak provided for liquidated damages for delay and also contained a risk of loss provision making ODEC responsible for certain losses or damages due to property damage at the plant. I highly recommend that you read the facts of the case in full to get the details of the terms of these clauses.
Needless to say (or this case wouldn’t be the subject of a construction law blog), the project ran past completion date and liquidated damages were assessed to the tune of more than $50,000,000.00. The delay was alleged to have been caused in substantial part by property damage due to weather, fire, and ice among other causes.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
California to Build ‘Total Disaster City’ for Training
July 30, 2014 —
Beverley BevenFlorez-CDJ STAFFCalifornia is building a “world-class $56 million training facility in eastern Sacramento County that would pit fire crews against a variety of realistic, pressure-packed simulated disasters,” according to the Sacramento Bee. Construction has begun on the Emergency Response Training Center in Mather Field in Rancho Cordova.
“The project is a joint effort between Henke’s fire department, the Governor’s Office of Emergency Services and the Sacramento Fire Department,” reported the Sacramento Bee.
Read the court decisionRead the full story...Reprinted courtesy of
Shifting Fees and Costs in Nevada Construction Defect Cases
November 26, 2014 —
Casey J. Quinn - Newmeyer & Dillion LLPIn Nevada, homeowners who sue a builder for residential constructional defects may recover attorneys’ fees and costs caused by the defect. Many times, the request for attorneys’ fees can outpace the size of the actual claim for defects. However, Nevada provides builders with two ways to potentially shift the right to recover attorneys’ fees and costs away from the homeowner and to the builder.
The first arises during the Nevada Revised Statutes (NRS) Chapter 40 process (Nevada’s Right to Repair law). After a builder receives notice of construction defects, it is required to provide the claimant with a written response to each defect, which may include a proposal for monetary compensation (including contribution from a subcontractor, supplier, or design professional). See NRS 40.6472. If a claimant unreasonably rejects a reasonable written offer of settlement included in the response and decides to commence litigation, the court may deny the claimant’s attorneys’ fees and costs and award attorneys’ fees and costs to the builder. See NRS 40.650. Thus, by including a reasonable offer of monetary compensation in a Chapter 40 response, a builder could possibly avoid paying any fees and costs and even recover its own fees in defending against the claim.
A second method for shifting fees and costs is through a written offer of judgment (OOJ). See NRS 17.115 and NRCP 68. Not limited solely to construction defect matters, an OOJ is a useful tool in all kinds of litigation. OOJs are designed to facilitate and encourage pre-trial settlement by incentivizing parties to make reasonable settlement offers that—when unreasonably rejected—have the consequence of shifting the right to recover attorneys’ fees. Basically, when a party rejects an OOJ and fails to obtain a more favorable judgment, the court cannot award any attorneys’ fees and costs to the rejecting party and may award attorneys’ fees incurred from the date of the offer to the entry of judgment, as well as all reasonable costs, to the party who made the offer. In a recent decision, the Nevada Supreme Court affirmed that when a homeowner rejects an OOJ and fails to obtain a more favorable judgment, it can wipe out that homeowner’s right to Chapter 40 fees and costs. See Gunderson, et al. v. D.R. Horton, 130 Nev. Adv. Op. 9 (Feb. 27, 2014). In other words, “While NRS Chapter 40 permits an award of reasonable attorney fees proximately caused by a construction defect, it does not guarantee it.” Id.
Because of the potentially harsh consequences of rejecting an OOJ, there are specific requirements that must be met to trigger them. An offer of judgment must be made in writing, can be made at any time at least 10 days before trial, and is irrevocable for 10 days with no provision for withdrawal before the 10 days expire. See Nava v. Second Judicial Dist. Court, 118 Nev. 396, 46 P.3d 60 (2002). A party may make successive offers of judgment, but the most recent offer extinguishes previous offers and is controlling for determining the date from which attorneys’ fees may be awarded. See Albios v. Horizon Communities, Inc. 132 P.3d 1022 (2006).
In Beattie v. Thomas, 99 Nev. 579, 668 P.2d 268, 274 (1983), the Nevada Supreme Court explained that the purpose of OOJs are not to cause plaintiffs to unfairly forego legitimate claims. However, when a valid offer of judgment is made, the offer is rejected, and the party rejecting the offer fails to obtain a more favorable judgment, a court must evaluate whether the plaintiff's claim was brought in good faith; whether the offer of judgment was reasonable and in good faith in both its timing and amount; whether the plaintiff's decision to reject the offer and proceed to trial was grossly unreasonable or in bad faith; and whether the fees sought by the offer are reasonable and justified. “After weighing the foregoing factors, the district judge may, where warranted, award up to the full amount of fees requested.” Id.
It is worth noting that in Albios v. Horizon Communities, Inc. 132 P.3d 1022 (2006), the Nevada Supreme Court held that when a party rejects a reasonable OOJ and is foreclosed from recovering fees and costs, the party is likewise foreclosed from an award of fees and costs under Chapter 40. This means that even if a builder fails to include a monetary settlement offer as part of a Chapter 40 response, it may still avoid paying the claimant’s fees and costs with a reasonable and timely OOJ.
Finally, it is important to remember that OOJs are a powerful tool that can cut both ways. If an OOJ is not reasonable and timely, or if it fails to contemplate all the potential recovery of an offeree, the OOJ may have no effect on the outcome of a case. Moreover, if a party rejects an OOJ and fails to obtain a more favorable judgment, that party could end up paying the offeror’s costs and attorney’s fees incurred from the date of the offer. Given this powerful impact, OOJs should be an integral part of pre-litigation planning and overall litigation strategy.
About the Author
Casey J. Quinn is an associate in the Las Vegas office of
Newmeyer & Dillion LLP. His practice focuses on complex commercial, construction, and insurance litigation and appellate work. Casey can be reached by email at Casey.Quinn@ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
The Partial Building Collapse of the 12-Story Florida Condo
June 28, 2021 —
Beverley BevenFlorez – CDJ StaffOn Thursday, the Champlain Towers South Condo building in Surfside, Florida suffered a partial collapse. As of Monday morning, the official death toll stood at 10 with 151 persons unaccounted for, according to the Miami Herald.
NPR uncovered minutes from a November 15th, 2018 Chaplain Tower South Condominium Association board meeting where the inspector made assurances that “the building was ‘in very good shape.’” However, “an
engineering report from five weeks earlier” alleged “that failed waterproofing in a concrete structural slab needed to be replaced ‘in the near future.’” Daniella Levine Cava, the Miami-Dade County mayor, told reporters that “officials ‘knew nothing’ about the report.”
The New York Times on Sunday reported that experts looking at video footage of the incident believe that the cause is centered on a location “in the lowest part of the condominium complex — possibly in or below the underground parking garage — where an initial failure could have set off a structural avalanche.” The cause of the incident remains unclear, however. This “progressive collapse” could have been caused by a number of different factors “including design flaws or the less robust construction allowed under the building codes of four decades ago.”
A witness, according to the New York Times, saw a hole appear near the pool: “Michael Stratton said his wife, Cassie Stratton, who is missing, was on the phone with him and was looking out through the window of her fourth-floor unit when, she told him, the hole appeared. After that, the call cut off.”
Possible reasons for the “initial failure at the bottom of the building could include a problem with the deep, reinforced concrete pilings on which the building sits — perhaps set off by an unknown void or a sinkhole below — which then compromised the lower columns. Or the steel reinforcing the columns in the parking garage or first few floors could have been so corroded that they somehow gave way on their own. Or the building itself could have been poorly designed, built with substandard concrete or steel — or simply with insufficient steel at critical points.”
"It will take many months to complete the analysis necessary to understand the cause or causes of the collapse,” Eric Ruzicka, a partner at the international law firm Dorsey & Whitney and a commercial litigator who specializes in the area of construction and real estate litigation, stated in a media release. “Often, information that comes out early can be very misleading or misunderstood unless the full context of the information is known.”
Ruzicka explained that Florida’s statues of limitations and repose may be relevant. “These statutes will likely eliminate the liability of those involved in the original development, design and construction of the building. Rather, victims and their families' recovery will be limited to those involved in the building's maintenance and those assessing the condition of the building over the past four years.”
Miami and Sunny Isles Beach have announced they will audit older structures in their communities “ahead of the mandatory 40-year recertification,” the Miami Herald reported.
Read the full story (Miami Herald)...
Read the full story (NPR)...
Read the full story (NY Times)...
Read the court decisionRead the full story...Reprinted courtesy of
Colorado homebuilders target low-income buyers with bogus "affordable housing" bill
March 05, 2015 —
Jesse Howard Witt – Acerbic Witt“Affordable housing” is the latest catchphrase for Colorado homebuilders seeking immunity from warranty claims and repair requests.
In 2013, the homebuilders’ lobby said it was about public transportation. In 2014 they said it was about community building. Now it’s 2015, and the lobbyists are claiming that a lack of affordable housing is the reason why politicians should eliminate consumer protections for homebuyers.
The Colorado Senate recently announced the introduction of SB 15-177. If passed, the bill will make it illegal for homeowner associations to hire construction experts or lawyers unless they can first satisfy a complicated disclosure and voting process. Although sponsors portray the bill as an innocuous measure that merely requires more community involvement, its provisions have actually been tailored to take advantage of recent court decisions that make it difficult for homeowner associations to vote on measures outside of a meeting or act quickly to resolve construction defect disputes. The intent is to make it nearly impossible for homeowners to retain construction experts or legal representation before the statute of limitations period expires, thereby making homebuilders immune from any potential claims. The bill will also eliminate the right to a jury trial in many cases, forcing any disputes that overcome the procedural hurdles into costly, private arbitration proceedings. The sponsors argue that these measures are necessary to encourage builders to erect more cheap condominiums.
Read the court decisionRead the full story...Reprinted courtesy of
Jesse Howard Witt, The Witt Law FirmMr. Witt welcomes comments at www.acerbicwitt.com
Construction Slow to Begin in Superstorm Sandy Cases
March 12, 2014 —
Beverley BevenFlorez-CDJ STAFFU.S. Senator Robert Mendendez of New Jersey, “has called on government officials to speed up the way home rebuilding aid is reaching thousands of New Jersey victims of Superstorm Sandy,” according to CBS New York. Mendendez stated that out of the 12,000 people who have received “preliminary approval for aid” under New Jersey’s “Reconstruction, Elevation and Mitigation program,” only “2,700 have been told they can begin construction.” The storm occurred more than sixteen months ago.
“Part of the problem,” Mendendez told CBS New York, “has been that state officials have placed federally required environmental and historic preservation reviews at the end of the lengthy aid application process. That delays rebuilding because federal rules allow reconstruction work to begin once those reviews are completed.”
CBS New York reported that the state announced that those “using their own contractors to rebuild homes can request 50 percent of their grant in advance under the change, which went into effect Monday.”
Read the court decisionRead the full story...Reprinted courtesy of
Supreme Judicial Court of Maine Addresses Earth Movement Exclusion
March 01, 2021 —
James M. Eastham - Traub LiebermanIn Bibeau v. Concord Gen. Mut. Ins. Co., 2021 WL 243867, 2021 ME 4, the Supreme Judicial Court of Maine addressed an earth movement exclusion contained in a residential homeowners policy. In 2017, the insured submitted a claim to Concord for damage to the insured’s home which included foundation cracks and settlement resulting in interior damage to the home. The insured contended that the damage was the result of a 2006 water line leak. Concord denied the claim based on the Earth Movement exclusion contained in it’s policy which precluded coverage for losses caused by earthquakes, landslides, mudslides, mudflow, subsidence, sinkholes or “[a]ny other earth movement including earth sinking, rising or shifting; caused by or resulting from human or animal forces or any act of nature”.
The insured filed suit asserting a breach of the policy and unfair claims settlement practices. According to the insured’s expert, the damage was caused by a 2006 water line leak -- which in turn caused the foundation to settle. Concord's expert, however, concluded that the settling was caused by the house being built on “unprepared or uncontrolled fill” which allowed the house to settle at different rates. Despite the disagreement regarding the cause of the settling, the parties ultimately agreed that the damage was the result of earth moving under the house's foundation. Concord moved for summary judgment and the trial court entered summary judgment for Concord, reasoning that because there was no genuine dispute that the losses were caused by “subsurface soils being undermined and earth movement,” the Earth Movement exclusion precluded coverage. The trial court further concluded that the disagreement over the cause of the settlement was not material because regardless of the cause of the earth movement, the losses were clearly excluded by the policy's Earth Movement exclusion.
Read the court decisionRead the full story...Reprinted courtesy of
James M. Eastham, Traub LiebermanMr. Eastham may be contacted at
jeastham@tlsslaw.com
Partner Vik Nagpal is Recognized as a Top Lawyer of 2020
June 29, 2020 —
Bremer Whyte Brown & O'Meara LLPPlease join us in congratulating San Diego Partner
Vik Nagpal for being recognized as a Top Lawyer of 2020 by San Diego Magazine! San Diego Magazine works with Martindale-Hubbell to choose top lawyers who have reached the highest level of ethical standards and professional excellence. Vik Nagpal was evaluated and given the highest ratings by the colleagues using a peer reviewed
Vik Nagpal is the managing partner of Bremer Whyte Brown & O’Meara LLP’s San Diego offices, as well as directing the firm’s business development.
Read the court decisionRead the full story...Reprinted courtesy of
Bremer Whyte Brown & O'Meara LLP