Renters Trading Size for Frills Fuel U.S. Apartment Boom
July 16, 2014 —
Prashant Gopal – BloombergKatie Graham is living large. Just in a small apartment.
She moved into the new ParkCentral tower in Nashville, Tennessee, for its gym, rooftop deck with heated pool, and the bars and restaurants in the neighborhood below. She didn’t mind the size of the 562-square-foot (52-square-meter) studio.
“I just wanted to be in a good area and wanted good amenities, so I wasn’t looking for something huge,” said Graham, 25, who relocated from her hometown in Jackson, Tennessee, two hours away. “I’m by myself and don’t need all that. The bigger the area, the more furniture you have to buy.”
Young professionals are paying top-market rents to live in new upscale apartment towers sprouting in Nashville and other downtowns across the country. They’re sacrificing living space for a prime urban location and extras such as cooking classes, dog-wash stations and poolside Wi-Fi. Developers, in the biggest U.S. apartment-construction boom in almost a decade, are shrinking the size of units so they can command luxury rates without narrowing the pool of potential tenants.
Read the court decisionRead the full story...Reprinted courtesy of
Prashant Gopal, BloombergMr. Gopal may be contacted at
pgopal2@bloomberg.net
Checking the Status of your Contractor License During Contract Work is a Necessity: The Expanded “Substantial Compliance” under B&P 7031 is Here
June 05, 2017 —
Ivo G. Daniele – Newmeyer & Dillion LLP News AlertIt is paramount that a contractor diligently maintains its license prior to and during the performance of any contract work. Failure to do so could result in barring a contractor from receiving payment and/or disgorgement of profits received under the construction contract.
California Business and Professions Code section 7031 is part of the Contractors State License Law (Business & Prof. section 700 et seq.), and is both feared and loathed by all contractors performing work in the state of California. This draconian statute is known as the “Shield” and was enacted over 70 years ago for the singular purpose to bar all actions by contractors seeking compensation for unlicensed contract work – even precluding a contractor from enforcing his or her mechanic’s lien rights. However, a contractor could potentially avoid the harshness of B&P 7031 by establishing that he or she had substantially complied with the appropriate licensing requirements.
SUBSTANTIAL COMPLIANCE WITH LICENSE REQUIREMENTS PRIOR TO 2017 AMENDMENT
The substantial compliance exception is found in section B&P 7031(e), which authorizes the court to determine that there has been substantial compliance with licensure requirements, if the contractor has shown at an evidentiary hearing that he or she engaged in the unlicensed work had:
- Been duly licensed as a contractor in this state prior to the performance of the act or contract;
- Acted reasonably and in good faith to maintain the license;
- Did not know or reasonably should not have known that he or she was not licensed when he or she performed the work; and
- Acted promptly and in good faith to reinstate the license once it learned the license had lapsed.
Although not impossible, satisfying all four requirements of the exception was challenging for the contractor, specifically, requirement # (3) – the lack of knowledge that he or she was unlicensed during performance of work.
SUBSTANTIAL COMPLIANCE POST 2017
Fortunately, Governor Brown heard the collective cry for relief and signed Assembly Bill 1793 (“AB 1793”) into law. The new bill revises the criteria for the court to determine if a contractor is in substantial compliance with the licensing requirements by deleting requirement # (3) in its entirety and modestly amending requirement # (4) to require the contractor to act promptly and in good faith to remedy the failure to comply with the licensure requirements upon learning of the failure.
As a result, the substantial compliance exception under B&P 7031(e) reads as follows:
(e) The judicial doctrine of substantial compliance shall not apply under this section where the person who engaged in the business or acted in the capacity of a contractor has never been a duly licensed contractor in this state. However, notwithstanding subdivision (b) of Section 143, the court may determine that there has been substantial compliance with licensure requirements under this section if it is shown at an evidentiary hearing that the person who engaged in the business or acted in the capacity of a contractor
(1) had been duly licensed as a contractor in this state prior to the performance of the act or contract, (2) acted reasonably and in good faith to maintain proper licensure, and (3) acted promptly and in good faith to remedy the failure to comply with the licensure requirements upon learning of the failure.
This new legislation has tempered the burden of proof born by the contractor in establishing substantial compliance, although be it minor in its modification, the fact of the matter remains the same – be diligent in maintaining your license during all phases of contract work.
Ivo Daniele is a seasoned associate in the Walnut Creek office focusing his practice on commercial transactions and business and construction litigation. For questions regarding California Business and Professions Code section 7031, please feel free to contact Ivo Daniele at (925) 988-3222 or ivo.daniele@ndlf.com.
About Newmeyer & Dillion
For more than 30 years, Newmeyer & Dillion has delivered creative and outstanding legal solutions and trial results for a wide array of clients. With over 70 attorneys practicing in all aspects of business, employment, real estate, construction and insurance law, Newmeyer & Dillion delivers legal services tailored to meet each client’s needs. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer & Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949-854-7000 or visit www.ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
Florida Governor Signs Construction Defect Amendments into Law
September 17, 2015 —
Beverley BevenFlorez-CDJ STAFFAccording to Jeffrey Gilbert and Anaysa Gallardo Stutzman of Cozen O’Connor, Rick Scott, governor of Florida, signed HB 87 into law, which “amends the notice and opportunity to cure provisions of Chapter 558, Florida’s Construction Defect Statute.” The amendments go into effect October first.
HB 87 requires “property owners to provide concrete details of the alleged defects.” Gilbert and Stutzman claimed, “Overall, these amendments seek to further the intended public policy purpose of Chapter 558, which is to provide an alternative dispute resolution mechanism and result in fewer lawsuits and lower litigation costs incurred by parties involved in construction defect matters.”
Read the court decisionRead the full story...Reprinted courtesy of
Duty to Defend Requires Payments Under Policy's Supplemental Payments Provision
February 16, 2017 —
Tred R. Eyerly – Insurance Law HawaiiThe California Court of Appeal determined there was no duty to indemnify and the insured had to reimburse the insurer's contribution to a settlement. Nevertheless, there was a duty to defend, meaning the insured did not have to reimburse amounts it was entitled to under the supplemental payments provision. Navigators Specialty Ins. Co. v. Moorefield Constr., 2016 Cal. App. LEXIS 1132 (Cal. Ct. App. Dec. 27, 2016).
Moorefield was the general contractor for a shopping center project to be developed by DBO Development No. 28 (DBO). The project included the construction of a 30,055-square-foot building to by used as a Best Buy store. In January 2002, DBO entered a 15-year lease with Best Buy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Government’s Termination of Contractor for Default for Failure-To-Make Progress
July 10, 2023 —
David Adelstein - Florida Construction Legal UpdatesWhenever you elect to terminate the other party for cause or for default, you need to JUSTIFY the basis of the cause or default. The reason being is that a termination for default or cause is the harshest contractual remedy. This is why the other party will typically either (i) convert the termination for default into one for convenience, or (ii) if there is no termination for convenience provision in the contract, argue the terminating party breached the contract by terminating the contract without rightful justification.
The key is if you are going to terminate a party for cause of default, make sure you have memorialized the persuasive reasons for exercising the termination, and can otherwise reasonably support the justification. Do not, and I repeat, do not haphazardly exercise a termination for default and think you do not have to justify the basis for the termination.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Court Finds That $400 Million Paid Into Abatement Fund Qualifies as “Damages” Under the Insured’s Policies
November 21, 2022 —
Lorelie S. Masters & Yaniel Abreu - Hunton Insurance Recovery BlogIn
Sherwin-Williams Co. v. Certain Underwriters at Lloyd’s London, et al., the Court of Appeals for Ohio’s Eighth District reversed the lower court, finding that money paid by the insured into an abatement fund was “damages” as that undefined term was used in the policyholder’s insurance policies. 2022-Ohio-3031, ¶ 1. Sherwin-Williams is a cautionary tale about how insurers may try to narrow the meaning of undefined terms in their insurance policies.
The dispute in Sherwin-Williams focused on coverage for $400 million that the policyholder and other defendants were ordered to pay into an abatement fund to be used by California cities and counties to mitigate the hazards caused by lead paint in homes. Id. ¶ 1. Although the underlying litigation proceeded in California, Ohio law governed coverage, which raised issues of first impression in Ohio. Id. Among other things, the insurers argued that the money paid into the abatement fund did not qualify as “damages” under the policies. Id. ¶ 57. The insured argued that, because the insurers did not define “damages” in the policies, the term had to be given its ordinary meaning. Id. ¶ 56.
Reprinted courtesy of
Lorelie S. Masters, Hunton Andrews Kurth and
Yaniel Abreu, Hunton Andrews Kurth
Ms. Masters may be contacted at lmasters@HuntonAK.com
Mr. Abreu may be contacted at yabreu@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Project Bankruptcy Law
February 05, 2014 —
Beverley BevenFlorez-CDJ STAFFGarret Murai, on the California Construction Law Blog, discusses the ins and outs of bankruptcy in construction projects. Murai discusses “bankruptcy basics” and answers questions regarding filing for project owners, general contractors, and subcontractors.
Murai explained the importance of learning about how bankruptcy affects construction projects: “Bankruptcy on a construction project is one of the biggest fears for owners and contractors. At best it can slow down a project and at worst it can cause a domino effect of bankruptcies as contractors and suppliers aren’t paid, causing the entire project to fail.”
Read the court decisionRead the full story...Reprinted courtesy of
Business Interruption Claim Granted in Part, Denied in Part
February 16, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe court granted portions of the business interruption claim, while denying other portions. Phoenix Ins. Co. v. Infogroup, Inc., 2015 U.S. Dist. LEXIS 162810 (S. D. Iowa Nov. 30, 2015).
Phoenix insured Infogroup's business buildings and personal business property, including data and data processing equipment. In late May 2011, warnings were issued of possible flooding from the Missouri River. On June 1, 2011, Infogroup moved and relocated its business operations and data centers away from the river and did not intend to return to the facilities. On July 19, 2011, Phoenix advanced $500,000 to Infogroup for anticipated claims under the policy. On August 22, 2011, heavy rain left surface water in the parking lot at Infogroup's facilities. Infogroup claimed that it suffered minor property damage during July and August, 2011, including damage to an uninterruptable power source and damage to a server.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at