Federal Court Asks South Dakota Supreme Court to Decide Whether Injunction Costs Are “Damages,” Adopts Restatement’s Position on Providing “Inadequate” Defense
August 13, 2019 —
Anthony L. Miscioscia & Timothy A. Carroll - White and Williams LLPDo costs associated with complying with an injunction constitute covered “damages?” The U.S. District Court for the District of South Dakota recently certified that question to the South Dakota Supreme Court, in Sapienza v. Liberty Mutual Fire Insurance Company, No. 3:18-CV-03015-RAL, 2019 U.S. Dist. LEXIS 84973 (D.S.D. May 17, 2019). If the South Dakota Supreme Court takes on the question, it will become one of the few highest state courts to do so.[1] The Sapienza case is also notable because the court adopted § 12 of the Restatement of the Law of Liability Insurance (Restatement) regarding an insurer’s potential liability for providing an “inadequate” defense. In doing so, the Sapienza court joins a growing list of courts to rely upon or cite to the Restatement.
The Sapienza case arose out of an underlying dispute between residential neighbors over the size and location of the Sapienzas’ new house they built in a historic district in Sioux Falls, SD. The newly-built house allegedly prevented the neighbors from using their fireplace, blocked natural light the neighbors previously enjoyed, and decreased the value of the neighbors’ house. The neighbors sought a permanent injunction requiring the Sapienzas to modify or relocate the house. The Sapienzas’ homeowners’ insurer provided them with defense counsel, but the insurer instructed the Sapienzas that it would not cover any costs associated with an injunction as such costs did not constitute covered “damages.”
Reprinted courtesy of
Timothy Carroll, White and Williams LLP and
Anthony Miscioscia, White and Williams LLP
Mr. Schulman may be contacted at carrollt@whiteandwilliams.com
Mr. Anderson may be contacted at misciosciaa@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Real Estate & Construction News Roundup (10/1/24) – Hybrid Work Technologies, AI in Construction and the Market for Office Buildings
November 05, 2024 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, commercial mortgage bond market in trouble, commercial real estate investments, pressure on mortgage REITs, and more!
- Short-term issues facing U.S. commercial real estate have made it an investment opportunity and values have bottomed out. (CNBC)
- As organizations report plans to shake up their real estate portfolios, the flight to quality spurs interest in space planning, amenities and hybrid work technologies. (Joe Burns, Facilities Dive)
- The conversation about AI’s potential benefits and risks has been a common refrain in construction recently. (Matthew Thibault, Construction Dive)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Reminder: The Devil is in the Mechanic’s Lien Details
February 16, 2017 —
Christopher G. Hill – Construction Law MusingsAs readers of Construction Law Musings are well aware, mechanic’s liens and their picky and at times overly form oriented nature are near and dear to my heart as a construction attorney here in Virginia. I recently had the opportunity to meet this head on in Hanover County, Virginia Circuit Court. I was defending a suit to enforce a mechanic’s lien in the context of a lien that had been released pursuant to a bond deposited with the court under Va. Code 43-71 on behalf of my client, the defendant in that suit.
The case, G.H. Watts Construction, Inc. v. Cornerstone Builders, LLC, involved a memorandum of lien recorded by G. H. Watts without the assistance of an attorney in which the claimant was identified as “G. H. Watts Construction, Inc.” while the signatory on the memorandum of lien and the claimant identified in the notary block were identified as “Gary H. Watts” and “Gary Watts” respectively. Nowhere on the memorandum was Gary Watts’ capacity as it related to the company, nor did it state that Gary Watts was an agent for claimant.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Standard Lifetime Shingle Warranties Aren’t Forever
April 03, 2013 —
CDJ STAFFOlympia Construction’s roofing division explained to the web site Thurston Talk how long “lifetime” warranties on shingles really last. Your lifetime? You’re likely to live out the effective period of your lifetime shingle warranty. They note that 100% coverage of the shingle replacement typically lasts only for ten years (and does not cover removal of the existing defective shingles). After that, coverage continues to decline without covering any of the labor. And this can be significant, since they noted that they have seen cases in which a batch of defective shingles means that every home on the block has a defect claim.
Read the court decisionRead the full story...Reprinted courtesy of
Ensuing Loss Provision Found Ambiguous
April 25, 2012 —
Tred R. Eyerly - Insurance Law HawaiiAfter the insurer denied coverage in a homeowner’s policy for construction defects under various exclusions, the court found the ensuing loss provision was ambiguous.Kesling v. Am. Family Mut. Ins. Co., 2012 U.S. Dist. LEXIS 38857 (D. Colo. March 22, 2012).
After purchasing a home from the sellers, the insureds noticed problems with the deck of the home. Massive cracking appeared, causing lifting and leaking on the deck and water running through the exterior foundation wall into the home. There was also damage to the roof and crawlspace.
The insureds had a homeowner’s policy with American Family, which covered accidental direct physical loss to property described in the policy unless the loss was excluded. They requested coverage for "conditions, defects and damages." American Family denied coverage because wear and tear, as well as damage to foundations, floors and roofs were excluded. The policy did provide coverage, however, for "any resulting loss to property described . . . above, not excluded or excepted in this policy.
When coverage was denied, the insureds sued American Family.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
Risk Management and Contracting after Hurricane Irma: Suggestions to Avoid a Second Disaster
September 14, 2017 —
Stephen H. Reisman, Gary M. Stein & Adam P. Handfinger – Peckar & Abramson, P.C.Peckar & Abramson attorneys have assisted contractors in the immediate aftermath of several Hurricanes, including Andrew in 1992, Wilma in 2005, Ike in 2008, and Sandy in 2012. Based on this experience, we offer some post-storm strategies for contracting and risk management in three situations:
- Ongoing projects in the area directly impacted by the storm;
- Projects remote from the storm-impacted areas, but which may be affected by material or labor shortages; and
- Requests for assistance in recovery/clean-up/rebuild eff orts, which would be new projects.
Projects Directly Impacted By Hurricane Irma:
1. Immediately review each Owner contract to determine what notices are required for delays and/or extra costs arising from the storm. Contract notice requirements and time limits vary, whether for force majeure or other similar time and compensation rights. There is no effective one-size-fits-all solution. While the initial notice letters will likely look very similar, you should make sure that each is sent as required by the contract. Check each contract’s requirements for particulars regarding content, the form of delivery, and parties and individuals designated to receive the letters as well as carbon copy recipients like the architect. Follow-up notices and time periods differ from contract to contract and should be tracked so that if, for example, a follow-up notice is required in a week per the contract terms, it is tracked to ensure compliance.
Reprinted courtesy of Haight Brown & Bonesteel LLP attorneys
Stephen H. Reisman,
Gary M. Stein and
Adam P. Handfinger
Mr. Reisman may be contacted at sreisman@pecklaw.com
Mr. Stein may be contacted at gstein@pecklaw.com
Mr. Handfinger may be contacted at ahandfinger@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
The G2G Year in Review: 2019
February 03, 2020 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogAs we kick off the new decade, we wanted to share the top five most-read articles of 2019 from Gravel2Gavel. The most-read blog posts covered 2019 real estate and construction industry trends ranging from affordable housing to the new State Bill 35 (SB 35) to sustainability in modern real estate. Our posts provided deep insight and detailed case studies, and summarized hot topics that addressed the legal implications and exciting disruptions that are affecting the industry. We hope you enjoy the roundup:
- Assessing SB 35—Success or Failure? by Robert Howard, Alexander Walker and Matt Olhausen
Robert, Alex and Matt examined the newly implemented SB 35 and highlighted real examples of SB 35 in action.
- Update Your California Release Provisions to Include Amended Section 1542 Language by William S. Hale, P.E.
Bill Hale encouraged readers to update their California release provisions to include Amended Section 1542 Language, which ensures that the releasing party is consciously releasing both known and unknown claims that may be later discovered.
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Alexander Moore Promoted to Managing Partner of Kahana Feld’s Oakland Office
May 08, 2023 —
Alexander R. Moore - Kahana FeldKahana Feld is pleased to announce that Alexander R. Moore, Esq., has been promoted to Managing Partner of our Oakland office. Mr. Moore has been at Kahana Feld since 2021 and is a member of the construction defect and general liability practice groups.
Mr. Moore has over 23 years of experience representing individual and commercial clients in complex disputes arising out of construction contracts, construction defect allegations, premises liability matters, landlord-tenant disputes, and contractual disputes arising out of various business relationships involving financial services companies, technology companies, telecommunications companies, real estate brokerages, non-profits, and a range of small businesses. When not focused on litigation, Mr. Moore enjoys consulting on transactional matters including the development of construction and business contracts. He has extensive experience evaluating rights and obligations under construction contracts and related insurance programs. He also assists clients in the implementation of pre-litigation risk management strategies.
Read the court decisionRead the full story...Reprinted courtesy of
Alexander R. Moore, Kahana FeldMr. Moore may be contacted at
amoore@kahanafeld.com