Alaska Supreme Court Dismisses Claims of Uncooperative Pro Se Litigant in Defect Case
August 11, 2011 —
CDJ STAFFThe Alaska Supreme Court found that in the case of Khalsa v. Chose, Ms. Khalsa? failure to cooperate with the courts has obligated them to dismiss her claims against Mr. Chose. Ms. Khalsa bought a home kit from Mandala Custom Homes of Nelson, British Columbia, Canada. Mr. Chose, one of the owners of Mandala was paid by Ms. Khalsa to supervise assembly in Fairbanks. After construction, the roof developed leaks. Ms. Khalsa stated that when climbing a ladder to inspect a skylight leak, she fell and injured herself.
During the subsequent suit, Khalsa proved uncooperative. She skipped a pretrial conference. She attended a hearing that set discovery deadlines but then did not comply with discovery, including her failure to provide medical records documenting her injuries. She eventually said that she would only be able to travel from Arizona to Alaska if the defendants paid for her and her caretaker?s expenses.
When finally deposed, Khalsa terminated the deposition after five minutes, alleging the deposition was “intentionally designed to cause [her] to endure further emotional distress, due to the psychological trauma . . . that was caused or contributed to by the defendants.”
Eventually, the lower court sanctioned her twice. In July, 2008, the court concluded that her failure to provide medical records required dismissal of her injury lawsuit. In October of that year, the court dismissed all remaining claims due to her “pattern of excuses and long delays in providing information for discovery culminating in her refusal to participate in her deposition by the defendants.” Further, Khalsa has argued that the trial court displayed “prejudice and bias toward the pro se plaintiff.”
The Alaska Supreme Court rejected all of Ms. Khalsa?s claims, dismissing her case. They did, however, note that she has thirty days to file an appeal.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Circumstances In Which Design Professional Has Construction Lien Rights
February 24, 2020 —
David Adelstein - Florida Construction Legal UpdatesIf you are a design professional (architect, landscape architect, interior designer, engineer, surveyor, or mapper) you have construction lien rights in the event you are not paid. This does not mean your lien rights are absolute so it is important to understand the circumstances which allow you to record a construction lien on a project. These circumstances are contained in Florida Statute s. 713.03:
(1) Any person who performs services as architect, landscape architect, interior designer, engineer, or surveyor and mapper, subject to compliance with and the limitations imposed by this part, has a lien on the real property improved for any money that is owing to him or her for his or her services used in connection with improving the real property or for his or her services in supervising any portion of the work of improving the real property, rendered in accordance with his or her contract and with the direct contract.
(2) Any architect, landscape architect, interior designer, engineer, or surveyor and mapper who has a direct contract and who in the practice of his or her profession shall perform services, by himself or herself or others, in connection with a specific parcel of real property and subject to said compliances and limitations, shall have a lien upon such real property for the money owing to him or her for his or her professional services, regardless of whether such real property is actually improved.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
In One of the First Civil Jury Trials to Proceed Live in Los Angeles Superior Court During Covid, Aneta Freeman Successfully Prevailed on Behalf of our Client and Obtained a Directed Verdict and Non-Suit
July 05, 2021 —
Aneta B. Freeman – Chapman Glucksman Dean & Roeb News AlertIn one of the first civil jury trials to proceed live in Los Angeles Superior Court during Covid, Aneta Freeman obtained a rare directed verdict and nonsuit in a complex, high exposure action, after seven days of trial. The dismissal was obtained after the parties rested after the liability phase of the bifurcated trial.
Ms. Freeman represented a general contractor in an action in which Plaintiff alleged that the general contractor and the County of Los Angeles (which was dismissed earlier on statutory immunity grounds) created a dangerous condition when they allegedly allowed mosquitos to breed in 2015 during construction at a flood retention basin in Marina Del Rey.
Plaintiff contracted West Nile Virus, and subsequently developed myasthenia gravis and a myriad of other conditions and ailments. Plaintiff relied heavily on a 2015 report from the Los Angeles West Vector Control District which suggested that the construction was the source of mosquitos which resulted in a “cluster” of West Nile Virus cases in the Marina Del Rey and surrounding areas.
In pretrial motions, Ms. Freeman successfully excluded that report, opinion testimony from the vector control former executive director, narrowed the scope of plaintiff’s entomologist testimony, and excluded Brad Avrit from testifying for the Plaintiff on construction standard of care.
The matter proceeded with a stipulated a 10 person jury, and all participants socially distanced and masked throughout the trial. Witnesses appeared live, with the exception of Plaintiff’s entomologist, portions of whose video deposition were played.
Following seven days of trial after both parties rested, Judge Mark Young granted the general contractor’s nonsuit and also, in the alternative, a directed a verdict for our client.
Plaintiff had demanded $10,000,000 of the County and the general contractor globally prior to trial, and $5,000,000 from the general contractor. The general contractor issued two CCP 998s, which were ignored by Plaintiff.
Read the court decisionRead the full story...Reprinted courtesy of
Aneta B. Freeman, Chapman Glucksman Dean & RoebMs. Freeman may be contacted at
afreeman@cgdrlaw.com
Montana Court Finds Duty to Defend over Construction Defect Allegation
February 14, 2013 —
CDJ STAFFThe U.S. District Court for Montana recently ruled on a case with underlying construction defect issues. Brian Margolies discussed Lukes v. Mid-Continent on the blog run by his firm, Traub Lieverman Straus & Shrewsberry LLP. In the construction defect case, the homeowner “alleged that the siding warped and pulled away from the house, which allowed for water intrusion and resulting exterior and interior damage.” Further, there were claims that “the insured or its subcontractor failed to install proper flashing, which also allowed for water intrusion.”
The insured was Bernie Rubio, who had a general liability policy from Mid-Continent. Mid-Continent disclaimed coverage, citing sections of the business risk exclusions. The court did not find the clauses ambiguous, but concluded that they didn’t apply to the facts of the case.
While the court concluded that Mid-Continent had a duty to defend, they did not determine if there was a duty to indemnify.
Read the court decisionRead the full story...Reprinted courtesy of
TOLLING AGREEMENTS: Construction Defect Lawyers use them to preserve Association Warranty Claims during Construction Defect Negotiations with Developers
March 07, 2014 —
Nicholas D. Cowie – Maryland Condo Construction Defect Law BlogIf properly drafted, a tolling agreement stops, or “tolls,” the running of the statue of limitations and other time periods aplicable to an association’s legal claims while it attempts to negotiate the repair of and/or monetary compensation for construction deficiencies with the developer and other responsible parties. In short, it is a “time -out” that allows and association to preserve its legal claim so it can focus on settling its claims rather than pursing them in court.
Too often, condominium associations and homeowner associations (“HOA”) unknowingly allow their legal claims for construction defects to expire during lengthy negotiations with developers and builders. If negotiations fail, the association may turn to a construction defect attorney for legal representation only to find their construction defect legal claims are time barred because the statute of limitations or other legal time period has expired.
This article explains how condominium associations and HOAs can avoid this scenario by the use of tolling agreements to preserve their legal claims while engaged in potentially lengthy negotiations with developers to correct construction defects.
Read the court decisionRead the full story...Reprinted courtesy of
Nicholas D. Cowie, Maryland Condo Construction Defect Law BlogMr. Cowie may be contacted at
ndc@cowiemott.com
Avoid a Derailed Settlement in Construction
March 28, 2022 —
Patrick Barthet - Construction ExecutiveMore and more construction cases are settling because lawyers know juries can prove to be unpredictable. The litigation process, as well as any actual trial, can be stressful, expensive and quite lengthy. Settlements are, for the most part, private while suits are public. Current reports find more than 90% of civil cases filed in state circuit courts are disposed of before trial. When that doesn't happen, things could go very poorly, as the case below illustrates.
The Case
Adam was seriously injured in a collision with a dump truck owned by Bang and driven by Tomas. While suit by Adam against Bang and Tomas was pending, Adam suggested they settle by having Bang pay him. Upon receipt of the offer, Bang's lawyer reached out confirming that his client was okay with the settlement amount but wished to add that the settlement also include the satisfaction of a lien filed by Adam's workers' compensation carrier. Adam's attorney refused that additional request, but that didn't stop Bang's lawyer. Based on the fact that Adam had agreed to the settlement amount, the lawyer filed a boiler plate notice of acceptance of settlement and had Bang issue a settlement check payable to Adam in the amount Adam had requested. Adam remained unwilling to compromise. He continued to resist the modified terms, which added satisfaction of the worker’s compensation lien. Bang then filed a motion to enforce settlement, arguing that since there was agreement on the settlement amount, Adam was required to do the deal.
Reprinted courtesy of
Patrick Barthet, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Barthet may be contacted at
pbarthet@barthet.com
Cost of Materials Holding Back Housing Industry
June 28, 2013 —
CDJ STAFFAs home building makes its recovery, there’s another hurdle to overcome: the cost of building materials. The Toledo Blade reports that the rise in the costs of materials makes homes built this year several thousands of dollars more expensive than those built last year. One builder, James Moline, said that he “ended up eating some of the lumber prices on a deal this spring because lumber prices went up so much.”
The cost of framing lumber has increased by about two-thirds, while the cost of strand board has more than doubled. Happily, material costs seem to have hit their high and in recent months have started to lower. The rise, according to Robert Denk, a senior economist at the National Association of Home Builders, is due to suppliers cutting back on capacity when demand dwindled, and despite the increase in building starts, suppliers have yet to bring that capacity back.
Read the court decisionRead the full story...Reprinted courtesy of
California Supreme Court Finds that the Notice-Prejudice Rule Applicable to Insurance is a Fundamental Public Policy of the State
October 14, 2019 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Pitzer College v. Indian Harbor Ins. Co. (No. S239510, filed 8/29/19), the California Supreme Court held that California’s notice-prejudice rule is a fundamental public policy in the insurance context, supporting the application of California law under a choice of laws analysis. In addition, the Court held that the rule generally applies to consent (aka “no voluntary payments”) provisions in first party insurance policies but not to consent provisions in third party liability policies.
Pitzer College discovered soils contamination while building a new dormitory. Under pressure to complete construction before the start of the school year, Pitzer proceeded to remediate the soils, incurring $2 million in expense. Pitzer submitted a claim to Indian Harbor, which provided Pitzer insurance covering legal and remediation expenses resulting from pollution conditions discovered during the policy period.
The policy contained a notice provision requiring Pitzer to provide oral or written notice of any pollution condition to Indian Harbor and, in the event of oral notice, to “furnish … a written report as soon as practicable.” In addition, a consent provision required Pitzer to obtain Indian Harbor’s written consent before incurring expenses, making payments, assuming obligations, and/or commencing remediation due to a pollution condition. The consent provision had an emergency exception for costs incurred “on an emergency basis where any delay … would cause injury to persons or damage to property or increase significantly the cost of responding to any [pollution condition],” in which case Pitzer was required to notify Indian Harbor “immediately thereafter.” Lastly, a choice of law provision stated that New York law governed all matters arising under the policy.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of