“Pay When Paid” Provisions May Not Be Dead, at Least Not Yet
August 24, 2020 —
Garret Murai - California Construction Law BlogSophisticated contractors know that in California contractual “pay when paid” provisions are enforceable but that “pay if paid” provisions are not.
“Pay If Paid” v. “Pay When Paid” Provisions
A “pay if paid” provision is one in which a higher tier party agrees to pay a lower tier party “if” it is paid in turn by a still higher party. Most commonly they are found in subcontracts between general contractors and subcontractors and provide that the general contractor will pay the subcontractor “if” the general contractor is paid by the project owner. However, they can also be found in subcontracts between higher and lower tiered subcontractors and between subcontractors and material suppliers and equipment lessors. In California, such provisions, which create a condition precedent to payment, namely, a condition that must precede payment to a lower tiered party, are void as a matter of law.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Sanibel Causeway Repair: Contractors Flooded Site With Crews, Resources
November 15, 2022 —
Derek Lacey - Engineering News-RecordAfter Hurricane Ian slammed into southwest Florida, washing out the Sanibel Causeway and cutting off thousands of Sanibel Island residents, another flood hit the area: construction crews and resources that swarmed the area to rebuild two roadway sections and five washed-out approaches to restore access.
Reprinted courtesy of
Derek Lacey, Engineering News-Record
Mr. Lacey may be contacted at laceyd@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
The Future Has Arrived: New Technologies in Construction
October 17, 2022 —
Sarah Biser - ConsensusDocsThe construction industry has traditionally been slow to adapt to new technologies, but things are changing.
Construction companies are keen to control costs (including increased costs due to supply chain issues), improve efficiency, maintain productivity while dealing with labor shortages, and enhance safety, and protect data bases from cyberattacks. New technologies, including robotics, 3D printing, cloud and mobile computing, augmented reality, blockchain, and cybersecurity, are helping construction companies achieve those goals.
Here are some key takeaways.
Augmented Reality (AR) vs. Virtual Reality
Augmented Reality is a technology that superimposes a computer generated image upon a user’s view of the real work. Virtual Reality, on the other hand, creates a virtual environment to replace the real one.
AR has uses in many industries. For example, shoppers using AR can see what furniture or appliances will look like in their own homes and offices. Medical professionals can also use the technology to visualize organs and simulate procedures prior to operations.
Read the court decisionRead the full story...Reprinted courtesy of
Sarah B. Biser, Fox Rothschild LLP (ConsensusDocs)Ms. Biser may be contacted at
sbiser@foxrothschild.com
Court Rules on a Long List of Motions in Illinois National Insurance Co v Nordic PCL
May 10, 2012 —
CDJ STAFFThe case Illinois National Insurance Co. v Nordic PCL, et al. “involves a dispute about whether insurance benefits are available to a general contractor who built structures that allegedly have construction defects. Plaintiffs Illinois National Insurance Company (‘Illinois National’) and National Union Fire Insurance Company of Pittsburgh, PA (‘National Union’) (collectively, the ‘Insurers’), commenced this action for declaratory relief against Defendant Nordic PCL Construction, Inc., f/k/a Nordic Construction, Ltd. ("Nordic"), on August 23, 2011.”
The court was asked to rule on a long list of motions: “Counterclaim Defendants’ Request for Judicial Notice in Support of Their (1) Motion to Dismiss the Counterclaim and (2) Motion to Strike Portions of the Counterclaim, ECF No. 16 (‘Request for Judicial Notice’); Counterclaim Defendants’ Motion to Dismiss Counterclaim Filed October 24, 2011, ECF No. 14 (‘Motion to Dismiss Counterclaim’); Counterclaim Defendants’ Motion to Strike Portions of the Counterclaim Filed October 24, 2011, ECF No. 15 (‘Motion to Strike’); Third-Party Defendant Marsh USA, Inc.’s Motion to Dismiss or, in the Alternative, Stay Proceedings in Favor of Pending State Action, ECF No. 33 (‘Marsh’s Motion To Dismiss Or Stay’); Defendant and Third-Party Plaintiff Nordic PCL Construction, Inc., f/k/a Nordic Construction Ltd.’s Substantive Joinder to Third-Party Defendant Marsh USA Inc.’s Motion to Dismiss or, in the Alternative, Stay Proceedings in Favor of Pending State Action, ECF No. 36 (‘Nordic’s Joinder’); and Third-Party Defendant Marsh USA, Inc.’s Motion for Judgment on the Pleadings on Counts V and VI of Defendant/Third-Party Plaintiff Nordic PCL Construction, Inc.’s Third-Party Complaint, ECF No. 29 (‘Marsh’s Motion for Judgment on the Pleadings’).”
In result, the court reached the following decisions: “The court GRANTS IN RELEVANT PART the Insurers’ Request for Judicial Notice to the extent it covers matters relevant to these motions; GRANTS IN PART the Insurers’ Motion to Dismiss Counterclaim, but gives Nordic leave to amend the Counterclaim in certain respects; DENIES the Insurers’ Motion to Strike; DENIES Marsh’s Motion To Dismiss Or Stay and Nordic’s Joinder; and GRANTS Marsh’s Motion for Judgment on the Pleadings.”
The court provides a bit of background on the case: “This action arises out of alleged construction defects involving two projects on which Nordic acted as the general contractor. Nordic is a defendant in a pending state court action with respect to one of the projects and says it spent more than $400,000 on repairs with respect to the other project. Nordic tendered the defense of the pending state court action to the Insurers and sought reimbursement of the cost of repairs already performed. The Insurers responded by filing this action to determine their rights under the insurance policies issued to Nordic.”
Furthermore, the court presented a brief procedural history: “The Insurers commenced this declaratory action in this court on August 23, 2011. The Complaint asserts two claims, one seeking a declaration that the Insurers have no duty to provide a defense or indemnification regarding the Safeway Action, the other seeking such a declaration regarding the Moanalua Claims. Along with its Answer, Nordic filed a Counterclaim against the Insurers. The Counterclaim asserts breach of contract, breach of the covenant of good faith and fair dealing, misrepresentations and omissions of material fact, and bad faith, and seeks declaratory relief against the Insurers.”
The procedural history continues: “Nordic also filed a Third-Party Complaint against Marsh, the broker that had procured the Policies from the Insurers for Nordic. Nordic alleges that it reasonably believed that the Policies would provide completed operations insurance coverage for the types of construction defects alleged in the Safeway Action and Moanalua Claims. The Third-Party Complaint asserts breach of contract, negligence, promissory estoppel, breach of fiduciary duties, implied indemnity, and contribution and equitable subrogation.”
In conclusion, “The court GRANTS IN RELEVANT PART the Insurers’ Request for Judicial Notice. With regard to the Insurers’ Motion to Dismiss Counterclaim, the court GRANTS the motion as to Count I (breach of contract), Count II (duty of good faith and fair dealing), Count III (fraudulent and negligent misrepresentation), the portion of Count IV (bad faith) premised on fraud, and Count IV (declaratory relief). The court DENIES the motion as to Count IV (bad faith) that is not premised on fraud. Except with respect to the "occurrence" issue, which the court disposes of here on the merits, and Count V, which concerns only a form of relief, Nordic is given leave to amend its Counterclaim within three weeks of the date of this order. The court DENIES the Insurers’ Motion to Strike, DENIES Marsh’s Motion to Dismiss or Stay and Nordic’s Joinder, and GRANTS Marsh’s Motion for Judgment on the Pleadings with respect to Counts V and VI of the Third-Party Complaint.”
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
D.R. Horton Earnings Rise as Sales and Order Volume Increase
May 07, 2015 —
John Gittelsohn – BloombergD.R. Horton Inc., the largest U.S. homebuilder by revenue, said fiscal second-quarter earnings rose as sales increased in a sign of growing demand for new homes.
Net income climbed to $147.9 million, or 40 cents a share, for the three months ended March 31 from $131 million, or 38 cents, a year earlier, the Fort Worth, Texas-based company said Wednesday in a statement. The average of 15 analyst estimates was 38 cents a share, according to data compiled by Bloomberg.
“The spring selling season at D.R. Horton is off to a strong start,” Chairman Donald R. Horton said in the statement. “Our increasingly diverse product offerings are enabling us to expand our industry-leading market share.”
Read the court decisionRead the full story...Reprinted courtesy of
John Gittelsohn, BloombergMr. Gittelsohn may be contacted at
johngitt@bloomberg.net
Approaches to Managing Job Site Inventory
August 30, 2017 —
Jessica Stark - Construction InformerThere is no question that organization on the job site can mean the difference between efficient performance and costly errors. A simple mistake can cost a company thousands, which is why details are carefully articulated and supervisors become better scrutinizers than magazine editors. But for some reason, many companies don’t consider managing job site inventory under this same attentive category, or perhaps they don’t know about the technology available to help them do it.
Whole Inventory, Big to Small
For contractors, keeping track of every piece of material and equipment lowers losses and keeps crews busy. This is especially true for contractors in the trades who often have specialized equipment in inventory such as power supplies, HVAC “smart energy” components or inspection equipment. Once everything is accounted for, the possibility of loss is decreased and there’s a chance to evaluate the use of all materials and equipment. This can show the efficiency of allotted resources. Is there enough equipment on the site to get tasks completed? Is there a need for more? Less? Having excess equipment can sometimes prepare a crew for problem scenarios. But it can also mean the construction company is overpaying for unneeded resources. However, the only way to know is by effectively managing job site inventory. That includes all equipment and materials.
Read the court decisionRead the full story...Reprinted courtesy of
Jessica Stark, Construction Informer
Macron Visits Notre Dame 2 Years After Devastating Fire
April 26, 2021 —
The Associated Press (Thomas Adamson & Jeffrey Schaeffer) - BloombergParis (AP) -- Two years after a fire tore through Paris’ most famous cathedral and shocked the world, French President Emmanuel Macron on Thursday visited the building site that Notre Dame has become to show that French heritage has not been forgotten despite the pandemic.
Flanked by ministers, architects and the retired French army general who is overseeing the restoration of the 12th-century monument, Macron viewed the progress of the ambitious rebuilding project. He offered the pandemic-weary French public hope that a completion date will arrive one day, if not in the near future.
“We're seeing here how, in two years, a huge job has been accomplished,” Macron said, recalling the “emotion” throughout France at the images of flames devouring Notre Dame on April 15, 2019. “We also see what remains to be done.”
Read the court decisionRead the full story...Reprinted courtesy of
Bloomberg
California’s Prompt Payment Laws: Just Because an Owner Has Changed Course Doesn’t Mean It’s Changed Course on Previous Payments
April 20, 2016 —
Garret Murai – California Construction Law BlogWe’ve written before about California’s prompt payment laws which are designed to help contractors get paid in a timely and orderly fashion, which is always nice, right?
California’s prompt payment laws require that project owners pay their direct contractors, who are in turn required to pay their subcontractors who are in turn required to pay their sub-subcontractors and so on within certain statutorily set deadlines, or be subject to prompt payment penalties nearly as high as the interest you pay on your credit cards.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com