Commonwealth Court Holds That Award of Attorney's Fees and Penalties is Mandatory Under the Procurement Code Upon a Finding of Bad Faith
October 29, 2014 —
William J. Taylor and Michael Jervis – White and Willams LLPIn a decision regarding a payment claim by a highway contractor against the City of Allentown, the Commonwealth Court of Pennsylvania has held that an award of attorney's fees and penalties is mandatory under the terms of the Pennsylvania Procurement Code, 62 Pa.C.S. § 3901 et seq., upon a finding of bad faith by the non-paying government agency, even though the statute only states that a court “may” award such fees and penalties.
In A. Scott Enterprises, Inc. v. City of Allentown, Cmwlth. Ct. No. 2163 C.D. 2013, the plaintiff, A. Scott Enterprises, Inc. (Scott), won a contract with the City of Allentown (City) to construct a one mile roadway. Several weeks after commencing work, Scott learned that soil at the construction site was potentially contaminated with arsenic, and was instructed by the City to suspend its work. Because of the soil contamination, additional work would be required to complete the project and Scott submitted proposals for the additional work plus its suspension costs. However, the City never approved the additional work and the project was never completed. The City never paid Scott for costs incurred due to the suspension of the work and Scott filed suit to recover its losses. The jury found that the City had breached the contract with Scott and had acted in bad faith in violation of the Procurement Code, and awarded damages to Scott for its unreimbursed suspension costs. However, the trial court denied Scott’s request for an award of attorney's fees and penalty interest. Both Scott and the City appealed the final judgment to the Commonwealth Court, which reversed the trial court’s refusal to award attorney's fees and penalties.
Reprinted courtesy of
William J. Taylor, White and Williams LLP and
Michael Jervis, White and Williams LLP
Mr. Taylor may be contacted at taylorw@whiteandwilliams.com; Mr. Jervis may be contacted at jervism@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
OSHA Issues Guidance on Mitigating, Preventing Spread of COVID-19 in the Workplace
February 22, 2021 —
Amy R. Patton & Blake A. Dillion - Payne & FearsOn January 29, 2021, the Occupational Safety and Health Administration (“OSHA”) issued new employer guidance on mitigating and preventing the spread of COVID-19 in the workplace. This guidance is intended to help employers and workers outside the healthcare setting to identify risks of being exposed to and of contracting COVID-19 and to determine any appropriate control measures to implement. While this guidance is largely duplicative of prior OSHA and Centers for Disease Control and Prevention (“CDC”) guidance and recommendations, it contains a few new and updated recommendations that employers should note:
Face Coverings
OSHA recognizes that face coverings, either cloth face coverings or surgical masks, are simple barriers that help prevent the spread of COVID-19, and are beneficial for the wearer as well as others. OSHA recommends that employers should provide all workers with face coverings, unless their work task requires a respirator. These face coverings should be provided at no cost and should be made of at least two layers of tightly woven breathable fabric, and should not have exhalation valves or vents. Employers should also require any other individuals at the workplace (i.e., visitors, customers, non-employees) to wear a face covering unless they are under the age of 2 or are actively consuming food or beverages on site. Wearing a face covering does not eliminate the need for physical distancing of at least six feet apart.
Employers must discuss the possibility of “reasonable accommodations” for any workers who are unable to wear or have difficulty wearing certain types of face coverings due to a disability. In workplaces with employees who are deaf or have hearing deficits, employers should consider acquiring masks with clear coverings over the mouth.
Reprinted courtesy of
Amy R. Patton, Payne & Fears and
Blake A. Dillion, Payne & Fears
Ms. Patton may be contacted at arp@paynefears.com
Mr. Dillion may be contacted at bad@paynefears.com
Read the court decisionRead the full story...Reprinted courtesy of
Urban Retrofits, Tall Buildings, and Sustainability
January 14, 2025 —
Christopher G. Hill - Construction Law MusingsAs I took a small break between cases and contract reviews, an article in the November 2, 2009 issue of ENR Magazine caught my eye. The article discusses the efforts of a Chicago architect to create a holistic approach to the renovation and “de-carbonization” of the Chicago Loop area. The plan involves large scale energy retrofits and sustainable reuse of Chicago’s tall buildings.
Another interesting aspect of this article points out that tall buildings in general have hit the construction skids in the US and Latin America, this is not the case in Europe and the Middle East. However, those buildings that are going up (and up and up) are trying to go “green.” Several of the worlds tallest buildings, or soon to be so, are seeking LEED gold or platinum certification.
These two trends, in my view, are healthy. First of all, much like the goal of Build2Sustain, the Chicago effort is a move toward sustainable reuse and retrofit/renovation. I see this as a great trend and a way to perform the “Three R’s” (Reduce, Reuse, Recycle), by reusing existing building materials and footprints without the cost and use of newer materials from tear downs and rebuilds.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Federal Judge Dismisses Insurance Coverage Lawsuit In Construction Defect Case
December 09, 2011 —
CDJ STAFFA federal judge dismissed a coverage lawsuit brought by Mid Continent Casualty Company against its insured, Greater Midwest Builders Ltd.
Plaintiff brought this declaratory judgment action in response to a suit filed in Johnson County District Court, seeking a judicial determination that it had no coverage obligation for claims asserted against its insured. This case was stayed until the state court action entered judgment against the insured. The prevailing parties then commenced a garnishment action against the plaintiff, and another insurance company, in state court in Missouri. The court was asked whether it should lift the stay and proceed with the case, or decline jurisdiction in favor of resolution in the Missouri state court.
The court granted the motion to dismiss holding that proceeding with the case would lead to protracted, piecemeal litigation, while deferring to the Missouri state court would decide all the claims involved in the dispute.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
New York Climate Mobilization Act Update: Reducing Carbon Emissions and Funding Solutions
August 30, 2021 —
Caroline A. Harcourt - Gravel2Gavel Construction & Real Estate BlogIn our June 16 CMA Update, we discussed how the New York City Climate Mobilization Act (CMA) will affect building owners and the market for CMBS mortgage loans (loans pooled and resold as commercial mortgage-backed securities). (For more information on C-PACE financing, see Sustainable Buildings and Development: Carbon Emissions and the Recent Climate Mobilization Act of New York City.) In this update, we will outline some of the funding solutions that are available to New York City building owners looking to retrofit their buildings in order to comply with the CMA’s requirements.
Funding Solutions for Covered Building Owners
The cost of retrofitting buildings to incorporate energy efficient features and to achieve compliance with the CMA can be daunting.
Read the court decisionRead the full story...Reprinted courtesy of
Caroline A. Harcourt, PillsburyMs. Harcourt may be contacted at
caroline.harcourt@pillsburylaw.com
Landowners Try to Choke Off Casino's Water With 19th-Century Lawsuit
December 17, 2015 —
Edvard Pettersson – BloombergCalifornia’s latest water war is being waged at the edge of wine country against an Indian tribe planning a massive casino expansion as a group of landowners tries to stop them with a lawsuit from 1897.
The Santa Ynez Band of Chumash Indians is spending $170 million to build out its resort, featuring a 12-story tower on a bucolic landscape where only the mountains are higher. The tribe has also snapped up 1,400 more acres to house cramped residents of its reservation.
Read the court decisionRead the full story...Reprinted courtesy of
Edvard Pettersson, Bloomberg
Court Adopts Magistrate's Recommendation to Deny Insurer's Summary Judgment Motion in Collapse Case
June 06, 2018 —
Tred R. Eyerly - Insurance Law HawaiiThe district court accepted the magistrate's recommended ruling denying the insurer's motion for summary judgment on breach of contract and bad faith claims in a case involving collapse. Jang v. Liberty Mut. Fire Ins. Co., 2018 U.S. Dist. LEXIS 51880 (D. Conn. March 27, 2018).
After purchase of their home, the insureds' inspector found large cracks in the foundation. Liberty denied coverage, contending that the basement wall was collapsing due to settling earth or movement. The insureds' expert later found the foundation had cracks from the oxidation of iron sulfide minerals in the foundation's concrete. The insureds sued for breach of contract, bad faith, and violations of the Connecticut Unfair Insurance Practice Act and the Unfair Trade Practices Act.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
The Anatomy of a Construction Dispute Stage 3- The Last Straw
January 28, 2015 —
Christopher G. Hill – Construction Law MusingsOver the past two weeks here at Construction Law Musings, I’ve discussed the first two stages of a typical construction dispute (if such a thing exists): the claim, and how to bring heat short of litigation/arbitration. As promised, this week I’ll be discussing the next step or “last straw” in a construction dispute, namely, arbitration or litigation to enforce all of those rights that you preserved in the first two stages.
Construction litigation is expensive, time consuming, and, quite frankly, a pain in the neck. Because of this fact, I almost always recommend that my construction clients exhaust all of the non-litigation methods (including mediation of course) of resolving their disputes prior to “going nuclear” and filing suit. Unfortunately, even the most diligent attempts at less formal resolution means can be unfruitful and more formal means become necessary.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com