Risk Management for Condominium Conversions
July 31, 2013 —
David McLain, Higgings, Hopkins, McLain & Roswell, LLCOne of the bright spots in the Colorado construction industry over the last few years has been the construction of for-rent apartments. It seems as though apartments are going up everywhere you look along the Front Range. As market forces change, it will be interesting to see whether these units will remain apartments or whether they will be converted into for-sale condominiums or townhouses. One of the risk management strategies we have recently discussed with our general contractor clients who have been asked to build apartments is to ensure that the project remains a for-rent apartment project through the applicable statute of repose, conservatively assumed to be eight years. Unfortunately this is not always feasible, usually because the owner and/or lender are not interested in encumbering the property for such a long period of time, and want to retain the ability to convert the project if and when market forces allow, even if that is before the running of the statute of repose. The purpose of this article is to discuss the insurance and risk management ramifications of converting a project too early.
I have recently heard from several sources in the insurance industry that there are owners and contractors who are currently building apartments with the idea that they will be held as apartments for two to three years and then converted to for-sale condominiums or townhomes. While this strategy may have great appeal from a business point of view, it has a very serious risk management downside. Apparently, these owners and contractors are operating under the mistaken belief that they will have no liability exposure to the ultimate purchasers of the converted units or to the homeowners association for construction defects. This is an incorrect belief.
Read the court decisionRead the full story...Reprinted courtesy of
David M. McLainDavid M. McLain can be contacted at
mclain@hhmrlaw.com
New Case Alert: Oregon Supreme Court Prohibits Insurer’s Attempt to Relitigate Insured’s Liability
November 17, 2016 —
Austin D. Moody – Saxe Doernberger & Vita, P.C. BlogIn a big win for policyholders, the Oregon Supreme Court recently ruled that that insurance companies are not allowed to relitigate the nature of damages awarded against their insureds during an underlying trial.
In a coverage dispute stemming from a contractor’s faulty work on a condominium development, the insurer argued that at least a portion of the damages awarded represented the cost of repairing the contractor’s own work product. Coverage for such damages would be explicitly excluded by the policy. However, the Oregon Supreme Court found that the jury had been instructed that it could not award damages for the contractor’s own faulty workmanship. The court declined to give the insurer a chance to attempt to reclassify the nature of these damages.
Read the court decisionRead the full story...Reprinted courtesy of
Austin D. Moody, Saxe Doernberger & Vita, P.C.Mr. Moody may be contacted at
adm@sdvlaw.com
Seabold Construction Ties Demise to Dispute with Real Estate Developer
April 29, 2024 —
Richard Korman - Engineering News-RecordWhen Harry W. Seabold, co-founder and CEO of Seabold Construction, died unexpectedly in January 2023 at age 69, the Beaverton, Ore.-based general contractor, which had been in business since 1984, kept chugging along for a year on two adjacent North Portland apartment projects.
Reprinted courtesy of
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Last, but NOT Least: Why You Should Take a Closer Look at Your Next Indemnification Clause
March 09, 2020 —
Aimee Cook Oleson - Construction & Infrastructure Law BlogIndemnification clauses appear in nearly every agreement, but they are often overlooked as mere boilerplate provisions after the parties have painstakingly negotiated all of the other terms. It is not uncommon for parties to simply re-use the indemnity language from a prior agreement without considering whether it is a good fit for their current project. This can be a big mistake that may lead to ambiguities and uncertainties if a dispute arises down the road. A standard or canned indemnification clause might work to undo all of the effort that has gone into properly allocating risk. These clauses often contain language such as “notwithstanding anything to the contrary herein,” or the like, which can alter and override other provisions in the agreement.
Indemnification clauses are arguably the most important part of an agreement when an accident or dispute arises on a project. Therefore, they deserve an extra look before finalizing an agreement. Here are a few issues to keep in mind when reviewing your next indemnification clause:
- Have you included all necessary parties?
- Any party who could face potential liability should be included as an indemnified party. This often includes entities and persons related to the contracting parties, not just the parties themselves.
- A well drafted indemnity clause will ensure that all parties are liable for the result of their own work and negligence and that of any party that they have hired to work on a project. This includes employees, agents, subcontractors, or any other similar party.
Read the court decisionRead the full story...Reprinted courtesy of
Aimee Cook Oleson, Sheppard MullinMs. Oleson may be contacted at
AOleson@sheppardmullin.com
Motions to Dismiss, Limitations of Liability, and More
January 23, 2023 —
Christopher G. Hill - Construction Law MusingsRemember BAE Sys. Ordnance Sys. V. Fluor Fed. Sols? I examined that case on two occasions previously here at Construction Law Musings. Previously the discussions were about the
mix (or lack thereof) between fraud and contract and about how
careful contract drafting is key.
In the
most recent opinion in this ongoing litigation from March of 2022, the Court examined various motions to dismiss the Complaint and Counterclaim in the matter. As a reminder, the basic facts are as follows.
The US Army Joint Munitions Command (“Army”) contracted with BAE Systems OrdnanceSystems, Inc. (“BAE”) to operate and maintain the Radford Army Ammunition Plant (“RFAAP”)under a basic ordering agreement (“BOA”). Under BOA Task Order 002, BAE contracted to replace the legacy NC facility at the RFAAP with a newer one (the “NC Project”). Initially, BAE subcontracted the NC Project to Lauren Engineers & Constructors (“Lauren”), but later terminated Lauren. Despite terminating Lauren, BAE’s timeline to complete the NC Project remained unchanged and BAE was required to use Lauren’s design for the NC Project. BAE gave interested bidders access to the Lauren design and other related documents and required the selected subcontractor to perform in accordance with the 85% complete Lauren design, that the Lauren design could be relied on for accuracy, and the selected subcontractor only had to complete the unfinished parts. Fluor Federal Solutions, LLC (“Fluor”) submitted a request for information (“RFI”) asking BAE about the standards referenced in the SOW. Fluor was unable to determine the completeness of the Lauren design but relied on BAE’s assertion that the design was 85% complete. BAE rejected Fluor’s initial bid as being too high given what BAE had already paid Lauren for its design and told Fluor to lower its bid because the design was close to complete. Fluor lowered its price and submitted another bid proposal that outlined a firm-fixed-price design/build that forecasted 32 months to complete the NC Project. BAE awarded Fluor an Undefinitized Contract Action (“UCA”) in the amount of $9 million dollars, later increased to $32 million. Under the UCA, Fluor began procuring materials and physical construction before a formal subcontract was agreed upon. On December 17, 2015, BAE and Fluor agreed to a fixed-price design and build subcontract (the “Subcontract”) in which Fluor agreed to design, construct, and partially commission the NC Project for $245,690,422.00, which included money spent already in the UCA. When this litigation began, Fluor was scheduled to complete its work by December 2020, 2.5 years beyond the originally agreed-upon completion date.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
The Risks and Rewards of Sustainable Building Design
July 25, 2021 —
Caroline A. Harcourt & Adam Weaver - Gravel2GavelThe shift towards a “greener” environment has resulted in cities and states implementing electrification mandates, which will have a major impact on both current and future building design. Currently, most commercial and residential end users are already all-electric. However, there are some exceptions, such as space and water heating, that use a significant amount of energy. Several states, including California and New York, have cities that have introduced legislation requiring new construction to be all-electric. This means, for example, using electricity for heating rather than fossil fuels such as natural gas. Mandate or not, building owners and developers should consider the risks and rewards of an all-electric design.
General Rewards
- Reaching Climate Goals: As part of the Clean Energy Plan, as described in a previous post, President Biden has created a goal for the United States of achieving a carbon pollution-free American utility sector by 2035. Because residential and commercial building account for 40 percent of energy consumption in the United States, all-electric building designs will help governments and businesses reach the ambitious climate goals that have been set for the coming years.
Reprinted courtesy of
Caroline A. Harcourt, Pillsbury and
Adam Weaver, Pillsbury
Ms. Harcourt may be contacted at caroline.harcourt@pillsburylaw.com
Mr. Weaver may be contacted at adam.weaver@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Nomos LLP Partner Garret Murai Recognized by Super Lawyers
August 03, 2022 —
Garret Murai - California Construction Law BlogNomos LLP Partner Garret Murai has been recognized as a 2022 Northern California Super Lawyers honoree in the area of Construction Litigation. This is the ninth consecutive year that he has been recognized by Super Lawyers.
Super Lawyers, an annual listing of outstanding lawyers from more than 70 practice areas who have attained a high degree of peer recognition and personal achievement, is limited to no more than five percent (5%) of lawyers in a state who are selected through a multiphase process that includes a statewide survey of lawyers, independent research evaluation and peer reviews by practice area.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Oregon Bridge Closed to Inspect for Defects
February 25, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to The Oregonian, the Morrison Bridge in Multnomah county, Oregon will be closed Sunday, February 23rd “so county crews can inspect the decking that has caused problems since it was installed” in 2012. The “southernmost eastbound lane has been closed for weeks while crews conducted inspections.”
The defects appeared “almost immediately after the project” was completed, reported The Oregonian. Drivers have “dealt with a bumpy, noisy ride as the loose decking panels flopped beneath them.”
Multnomah county has sued “Conway Construction, the company the installed the decking, as well as Strongwell Corp., the company that supplied Conway with the decking materials, and Zellcomp, the company that made the decking materials, to determine who should foot the bill for extensive repairs or outright replacement of the decking.”
Read the court decisionRead the full story...Reprinted courtesy of