Expert's Opinions On Causation Leads Way To Summary Judgment For Insurer
August 10, 2017 —
Tred R. Eyerly - Insurance Law HawaiiAlthough the insured claimed damages to her home was caused by vibrations from nearby construction, the court held she failed to overcome the insurer's expert's opinion that the damage resulted from excluded causes such as wear and tear, cracking and settling. King v. Am Family Ins., 2017 Ohio App. LEXIS 2565 (Ohio Ct. App. June 26, 2017).
The insured had a homeowners policy with American Family. The insured sued American Family, alleging that damage to her home was caused by vibrations caused by construction equipment at a nearby high school. The damage included cracks, leaks and mold.
American Family moved for summary judgment, attaching an affidavit from a structural engineering consulting firm. The report outlined alleged damages, including cracks throughout the house, and opined that the areas of concern had been present and progressing for years. Some damaged areas were discolored and patched. Accordingly, the report concluded that the damages were not caused by vibrations from construction.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly - Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Determining the Cause of the Loss from a Named Windstorm when there is Water Damage - New Jersey
March 23, 2020 —
Anna M. Perry - Saxe Doernberger & VitaWater damage, while one of the leading causes of loss under a property policy, often results in some of the most complex claims due to the intersection of exclusions, sublimits, and complex wording within the policy. One particularly difficult issue is whether water damage caused by a storm surge is covered by the flood sublimit, or under the general policy or water limit. In New Jersey Transit Corp. v. Certain Underwriters at Lloyd’s (“NJTC v. Lloyd’s”), the New Jersey Appeals Court found that the “flood” sublimit of the policy should not apply as the cause of the loss was a “named windstorm” and not a “flood.”
In NJTC v Lloyd's the court was asked to determine whether a flood sublimit applied to losses sustained during Superstorm Sandy. The court found that although there was “flooding,” the water damage was more closely related to the “named windstorm”, and therefore, the $400 million policy limits should apply. The court focused its analysis on the definitions for “flood” and “named windstorm” and by applying the efficient proximate cause doctrine to determine which would apply.
When reviewing the definitions within the property policies, the court determined that although the loss would qualify under the definition of “flood,” the policy also contained a definition for “named windstorm” which “more specifically encompasses the wind driven water or storm surge associated with a ‘named windstorm’”1. In addition, the policy did not specifically state that “storm surge” associated with a “named windstorm” should be considered a “flood” event and fall under the “flood” sublimit.
Read the court decisionRead the full story...Reprinted courtesy of
Anna M. Perry, Saxe Doernberger & VitaMs. Perry may be contacted at
amp@sdvlaw.com
New Plan Submitted for Explosive Demolition of Old Tappan Zee Bridge
December 19, 2018 —
Eydie Cubarrubia - Engineering News-RecordWorker safety concerns sparked a new plan on how to demolish the remnants of the old Tappan Zee Bridge in New York.
Read the court decisionRead the full story...Reprinted courtesy of
Eydie Cubarrubia, ENRMs. Cubarrubia may be contacted at
cubarrubiae@enr.com
THE CALIFORNIA SUPREME COURT HAS RULED THAT THE RIGHT TO REPAIR ACT (SB800) IS THE EXCLUSIVE REMEDY FOR CONSTRUCTION DEFECT CLAIMS NOT INVOLVING PERSONAL INJURIES WHETHER OR NOT THE UNDERLYING DEFECTS GAVE RISE TO ANY PROPERTY DAMAGE in McMillin Albany LL
January 24, 2018 —
Chapman, Glucksman, Dean, Roeb, & BargerRICHARD H. GLUCKSMAN, ESQ.
GLENN T. BARGER, ESQ.
JON A. TURIGLIATTO, ESQ.
DAVID A. NAPPER, ESQ.
The Construction Industry finally has its answer. The California Supreme Court ruled that the Right to Repair Act (SB800) is the exclusive remedy for construction defect claims alleged to have resulted from economic loss, property damage, or both. Our office has closely tracked the matter since its infancy. The California Supreme Court’s holding resolves the split of authority presented by the Fifth Appellate District’s holding in
McMillin Albany LLC v. Superior Court (2015) 239 Cal.App.4th 1132, which outright rejected the Fourth Appellate District’s holding in
Liberty Mutual Insurance Co. v. Brookfield Crystal Cove LLC (2013) 219 Cal.App.4th 98.
By way of background, the Fourth District Court of Appeal held in
Liberty Mutual that compliance with SB800’s pre-litigation procedures prior to initiating litigation is only required for defect claims involving violations of SB800’s building standards that have not yet resulted in actual property damage. Where damage has occurred, a homeowner may initiate litigation under common law causes of action without first complying with the pre-litigation procedures set forth in SB800. Two years later, the Fifth District Court of Appeal, in
McMillin Albany, held that the California Legislature intended that all claims arising out of defects in new residential construction sold on or after January 1, 2003 are subject to the standards and requirements of the Right to Repair Act, including specifically the requirement that notice be provided to the builder prior to filing a lawsuit. Thus, the Court of Appeal ruled that SB800 is the exclusive remedy for all defect claims arising out of new residential construction sold on or after January 1, 2003.
After extensive examination of the text and legislative history of the Right to Repair Act, the Supreme Court affirmed the Fifth District Court of Appeal’s ruling that SB800 preempts common law claims for property damage. The Complaint at issue alleged construction defects causing both property damage and economic loss. After filing the operative Complaint, the homeowners dismissed the SB800 cause of action and took the position that the Right to Repair Act was adopted to provide a remedy for construction defects causing only economic loss and therefore SB800 did not alter preexisting common law remedies in cases where actual property damage or personal injuries resulted. The builder maintained that SB800 and its pre-litigation procedures still applied in this case where actually property damages were alleged to have occurred.
The Supreme Court found that the text and legislative history reflect a clear and unequivocal intent to supplant common law negligence and strict product liability actions with a statutory claim under the Right to Repair Act. Specifically the text reveals “…an intent to create not merely
a remedy for construction defects but
the remedy.” Additionally certain clauses set forth in SB800 “…evinces a clear intent to displace, in whole or in part, existing remedies for construction defects.” Not surprisingly, the Court confirmed that personal injury damages are expressly not recoverable under SB800, which actually assisted the Court in analyzing the intent of the statutory scheme. The Right to Repair Act provides that construction defect claims not involving personal injury will be treated the same procedurally going forward whether or not the underlying defects gave rise to any property damage.
The Supreme Court further found that the legislative history of SB800 confirms that displacement of parts of the existing remedial scheme was “…no accident, but rather a considered choice to reform construction defect litigation.” Further emphasizing how the legislative history confirms what the statutory text reflects, the Supreme Court offered the following summary: “the Act was designed as a broad reform package that would substantially change existing law by displacing some common law claims and substituting in their stead a statutory cause of action with a mandatory pre-litigation process.” As a result, the Supreme Court ordered that the builder is entitled to a stay and the homeowners are required to comply with the pre-litigation procedures set forth in the Right to Repair Act before their lawsuit may proceed.
The seminal ruling by the California Supreme Court shows great deference to California Legislature and the “major stakeholders on all sides of construction defect litigation” who participated in developing SB800. A significant win for builders across the Golden State, homeowners unequivocally must proceed via SB800 for all construction defect claims arising out of new residential construction sold on or after January 1, 2003. We invite you to contact us should you have any questions.
Reprinted courtesy of Chapman Glucksman Dean Roeb & Barger attorneys
Richard Glucksman,
Glenn Barger,
Jon Turigliatto and
David Napper
Mr. Glucksman may be contacted at rglucksman@cgdrblaw.com
Mr. Barger may be contacted at gbarger@cgdrblaw.com
Mr. Turgliatto may be contacted at jturigliatto@cgdrblaw.com
Mr. Napper may be contacted at dnapper@cgdrblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
What Should Be in Every Construction Agreement
November 04, 2019 —
Patrick Barthet - Construction ExecutiveA detailed and coherent construction agreement in place on every job minimizes confusion, makes clear everyone’s respective responsibilities and reduces disputes. There are six things that should be addressed in every construction agreement.
DEFINE THE SCOPE
Define what the scope of work is that will be provided. Will it be only materials; will it be materials and labor; or will it be just labor? Be very clear and specific in how the scope of work is spelled out. Many contracts state that the contractor is responsible for all work that’s shown on the plans and specifications, as well as that which is reasonably inferable. While subjective—even if not actually on the plans or specifications, someone may believe that something should be part of the contractor’s work. This could expand what has to be done beyond what was understood or priced.
LIST ALL THE EXCLUSIONS
Do the parties each have the same understanding as to what is covered in the contract? How often are contractors faced with customers thinking something was included as part of the work? The contractor may have believed that task, or that material, or that specially fabricated item was excluded. But was it? Did the contractor articulate what was and was not in the scope and price? Specifically listing what is excluded can obviate this problem. Articulate what is not in the price or scope and reduce the chance of one party believing that something is to be done when it isn't.
Reprinted courtesy of
Patrick Barthet, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Barthet may be contacted at
pbarthet@barthet.com
Record-Setting Construction in Fargo
November 07, 2012 —
CDJ STAFFPrairie Business reports that Fargo is experiencing the most new construction it has ever seen, totaling $434 million in value, which exceeds the previous high in 2006 of $428 million. Many of the construction starts are for single family homes, although there is also an increase in construction of apartments and townhomes.
The Home Builders Association of Fargo-Moorhead also noted that there was also a large of remodeling projects. Terry Becker, the president of the HBA, said that “remodeling is just huge right now.”
Read the court decisionRead the full story...Reprinted courtesy of
When Your “Private” Project Suddenly Turns into a “Public” Project. Hint: It Doesn’t Necessary Turn on Public Financing or Construction
September 28, 2017 —
Garret Murai - California Construction Law BlogIn 1931, during the Great Depression, the federal government enacted the Davis-Bacon Act to help workers on federal construction projects. The Davis-Bacon Act, also known as the federal prevailing wage law, sets minimum wages that must be paid to workers on federal construction projects based on local “prevailing” wages. The law was designed to help curb the displacement of families by employers who were recruiting lower-wage workers from outside local areas. Many states, including California, adopted “Little Davis-Bacon” laws applying similar requirements on state and local construction projects.
California’s current prevailing wage law requires that contractors on state and local public works projects pay their employees the general prevailing rate of per diem wages based on the classification or type of work performed by the employee in the locality where the project is located, as well as to hire apprentices enrolled in state-approved apprentice programs and to make monetary contributions for apprenticeship training.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
OSHA Announces Expansion of “Severe Violator Enforcement Program”
November 15, 2022 —
Kip J. Adams & Steven G. Gatley - Lewis Brisbois(October 28, 2022) - Employers beware! The Occupational Safety and Health Administration (OSHA) is significantly expanding its “Severe Violator Enforcement Program” (SVEP). Employers that are placed into the program by OSHA will be significantly scrutinized, with the potential for very damaging information about their failure to maintain a safe workplace being made public for customers, partners, and vendors to see.
As the name suggests, the program is meant to identify, classify, and then stringently monitor employees deemed to be “severe violators” of the OSH Act. According to the OSHA website alert, to be deemed a “severe violator”, the agency must find that the employer has demonstrated “indifference” to the regulations by committing “willful, repeated, or failure-to-abate” violations.
Reprinted courtesy of
Kip J. Adams, Lewis Brisbois and
Steven G. Gatley, Lewis Brisbois
Mr. Adams may be contacted at Kip.Adams@lewisbrisbois.com
Mr. Gatley may be contacted at Steven.Gatley@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of