California Builders’ Right To Repair Is Alive
March 19, 2014 —
David J. Byassee - Ulich & Terry LLPThe California Supreme Court surprised everyone on December 11, 2013 when it denied Brookfield Homes’ request for review of the ruling in the case of Liberty Mutual Ins. Co. v. Brookfield Crystal Cove, LLC (2014) 219 Cal.App.4th 98, which was decided by the Court of Appeal for the Fourth Appellate District Division Three (Orange County). In that case the Court of Appeal held that the Right to Repair Act aka SB800 is not the exclusive remedy for a homeowner seeking damages for construction defects that have resulted in property damage. Under the ruling, homeowners may choose to sue builders under common law theories of liability such as strict liability and negligence, in addition to liability under the Act. This ruling made homeowners' compliance with the prelitigation requirements of the Act optional and thereby put builders' “right to repair” in jeopardy. The ruling undermined the expectations of California's homebuilders who, for the past decade, understood that their liability is limited by the Act and that they have a right to repair.
Since the Liberty Mutual case was handed down, the topic has become a hotbed item with several divisions of the Court of Appeal. On February 19, 2014, the Court of Appeal for the Second Appellate District Division Three (Los Angeles County) issued a ruling against Premier Homes in the case of Burch v. Superior Court 2014 Cal.App.LEXIS 159 that, without independent analysis, simply adopted the holding in the Liberty Mutual case.
But on February 21, 2014, the Court of Appeal for the Second Appellate District Division Four (Los Angeles County) ruled in the case of KB Home Greater Los Angeles, Inc. v.Superior Court 2014 Cal.App.LEXIS 167 that a homeowner's failure to give the builder an opportunity to inspect and repair a construction defect excused the builder's liability under the Act. Additionally, the Court of Appeal went out of its way to state it had ruled earlier in that case that the Act is the exclusive remedy.
The various rulings lay a foundation for ultimate intervention by the California Supreme Court. In the meantime, these opposing cases will be cited by counsel for homeowners and builders alike for opposing positions as they continue to navigate construction defect disputes.
Mr. Byassee is a strategic litigator specializing in representation of builders and developers. For more information regarding dispute resolution procedures under SB800, Mr. Byassee may be contacted at (949) 250-9797 or by email at dbyassee@ut-law.com.
Published courtesy of
David J. Byassee, Ulich & Terry LLP
Read the court decisionRead the full story...Reprinted courtesy of
Thank You for 14 Consecutive Years of Legal Elite Elections
December 29, 2020 —
Christopher G. Hill - Construction Law MusingsThanks to the Virginia legal community that has continued to elect me to the Virginia Business Legal Elite in the Construction Law Category for 14 years running. The 14 consecutive years of election to the Legal Elite in the Construction Category spans my time as a solo construction attorney. The fact that you all have continued to elect “100%” of the lawyers at The Law Office of Christopher G. Hill, PC for the last 10 years is most gratifying and only confirms that my decision to “go solo” over 10 years ago was a good one. To be included in this list of top construction attorneys is both humbling and gratifying. For the complete list of the Virginia construction lawyers that were elected along with me, see the 2020 Virginia Business Legal Elite in Construction Law.
Reprinted courtesy of
The Law Office of Christopher G. Hill
Mr. Hill may be contacted at chrisghill@constructionlawva.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Settlement Agreement? It Ain’t Over ‘Til it’s . . . Final, in Writing, Fully Executed, and Admissible
April 12, 2021 —
Todd Likman - Colorado Construction LitigationAs litigators we have all been there: nearing the end of a hard-fought mediation that lasted all day. Your significant other texts to ask what is for dinner; daycare closes in thirty minutes; the dog needs to be let out. The mediator, a retired judge, gently reminds you of his prior commitment—a speaking engagement at a volunteer charity dinner event that night. Though the parties started the day at opposite ends of the spectrum, after numerous counteroffers, persistent negotiation, and mediation tactics, they finally strike a deal.
As the mediator prepares a document memorializing the terms of settlement, the parties wait with bloodshot eyes, and a sense of guarded accomplishment considering compromises were
made, but alas, an outcome seems certain. You text your significant other to indicate that you will pick something up for dinner on your way home.
Then, the mediator informs you that computer problems are preventing finalization and transmission of the document for signature. The mediator offers to send an e-mail setting forth the material settlement terms and asks each party to respond via e-mail to confirm the terms are correct, which the parties do. After a quick e-mail to your experts and case team asking them to cease trial preparation work, you leave for home.
Read the court decisionRead the full story...Reprinted courtesy of
Todd Likman, Higgins, Hopkins, McLain & RoswellMr. Likman may be contacted at
likman@hhmrlaw.com
When Your “Private” Project Suddenly Turns into a “Public” Project. Hint: It Doesn’t Necessary Turn on Public Financing or Construction
September 28, 2017 —
Garret Murai - California Construction Law BlogIn 1931, during the Great Depression, the federal government enacted the Davis-Bacon Act to help workers on federal construction projects. The Davis-Bacon Act, also known as the federal prevailing wage law, sets minimum wages that must be paid to workers on federal construction projects based on local “prevailing” wages. The law was designed to help curb the displacement of families by employers who were recruiting lower-wage workers from outside local areas. Many states, including California, adopted “Little Davis-Bacon” laws applying similar requirements on state and local construction projects.
California’s current prevailing wage law requires that contractors on state and local public works projects pay their employees the general prevailing rate of per diem wages based on the classification or type of work performed by the employee in the locality where the project is located, as well as to hire apprentices enrolled in state-approved apprentice programs and to make monetary contributions for apprenticeship training.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
If I Released My California Mechanics Lien, Can I File a New Mechanics Lien on the Same Project? Will the New Mechanics Lien be Enforceable?
December 29, 2020 —
William L. Porter - Porter Law GroupIf I Released My California Mechanics Lien, Can I File a New Mechanics Lien on the Same Project? Will the New Mechanics Lien be Enforceable?
In general, the answer to the above questions is “Yes”, but only if you meet the following requirements:
- You must only release the mechanics lien itself, but not the “right” to a mechanics lien: There is an important distinction to be made between releasing a mechanics lien and releasing the right to a mechanics lien. Whether you do one or the other will depend on the specific language used in your release. In the case of Santa Clara Land Title Co. v. Nowack and Associates, Inc. (1991) 226 Cal. App.3d, 1558 a “release of mechanics lien” document was recorded TO THE County Recorder’s office which included a statement that the mechanics lien was “fully satisfied, released and discharged”. Based on this language, the court concluded that the mechanics lien claimant had waived its “right” to a further mechanics lien on the same property for the work in question. The court concluded that since the release stated that the claim was “fully satisfied” the right to mechanics lien on the project had forever been waived. The Nowak case can be distinguished from the case of Koudmani v. Ogle Enterprises, Inc., (1996) 47 Cal.App.4th 1650, where the release of mechanics lien only stated that the mechanics lien was “otherwise released and discharged” and not that it was “satisfied”. Based on the distinction drawn from the two cases, a simple mechanics lien release that only releases the mechanics lien itself, but not the “right” to a mechanics lien should be used. At the following link you will find a proper form to achieve this purpose: https://www.porterlaw.com/wp-content/uploads/2019/06/03PRI-Mechanics-Lien-Release.pdf
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Missouri Legislature Passes Bill to Drastically Change Missouri’s “Consent Judgment” Statute
August 10, 2021 —
Jason Taylor - Traub Lieberman Insurance Law BlogOn June 29, 2021, Missouri Governor Mike Parson signed SB-HB 345 into law, which will drastically change Section 537.065 of the Missouri Revised Statutes. Section 537.065 provides an insured who has been denied insurance coverage a statutory mechanism to settle certain tort claims through an agreement akin to a consent judgment. Typically referred to as a “065 Agreement,” the statute allows a plaintiff and insured-tortfeasor to settle a claim for damages and specify which assets are available to satisfy the claim, typically the tortfeasor’s available insurance policy. In the past, such agreements were often accomplished without the insurer’s participation or even its knowledge. Under such agreements, the insured-tortfeasor assigns all rights to the insurance policy to the plaintiff and agrees not to contest the issues of liability or damages. In exchange the plaintiff agrees not to execute any judgment against the insured. The parties conduct what amounts to an uncontested and often “sham” trial resulting in a judgment far in excess of any actual damages or applicable policy limits had the case been contested. In a subsequent proceeding to collect on the judgment, the tortfeasor’s insurer is bound by the determinations of liability and damages made in the underlying action.
This statutory framework presented plenty of opportunities for abuse. In 2017, the statute was amended in order to address some of those issues, including a requirement that the insured provide notice of a settlement demand under Section 065 and providing insurers a limited right to intervene in the tort action before liability and damages have been determined. Ostensibly, the intent of the 2017 amendments was to reduce the number of large and uncontested judgments and allow the insurance carrier an opportunity to continue litigating the injured party’s claim where the insured has no incentive or is contractually prohibited from doing so. Yet, creative plaintiff’s attorneys found several “loopholes” around these changes, most prominently, by moving their disputes from state court to binding arbitration and dispensing with notice to the insurer altogether, or at least until after the arbitration has concluded.
Read the court decisionRead the full story...Reprinted courtesy of
Jason Taylor, Traub LiebermanMr. Taylor may be contacted at
jtaylor@tlsslaw.com
Official Tried to Influence Judge against Shortchanged Subcontractor
February 10, 2012 —
CDJ STAFFA contractor testified in the trial of former Cuyahoga County Commissioner Jimmy Dimora. According to Fox 8 in Cleveland, Ohio, Sean Newman, the president of Letter Perfect testified that his company was a subcontractor on the reconstruction of the locker rooms at the Cleveland Browns Stadium. Newman said his company was paid only $400,000 of their $650,000 bid. When Letter Perfect sued the contractor, D.A.S. Construction, Dimora called the judge to influence her to rule in favor of D.A.S.
The judge in the earlier case, Bridgett McCafferty, has been found guilty of lying to the FBI during their investigation and is serving a 14-month prison sentence.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Miller Act Payment Bond Surety Bound to Arbitration Award
December 29, 2020 —
David Adelstein - Florida Construction Legal UpdatesHere is an interesting case binding a Miller Act payment bond surety to an arbitration award against its prime contractor (bond principal) that it received sufficient notice of. Notice is the operative word. The surety could have participated in the arbitration, elected not to, and when its prime contractor (bond principal) lost the arbitration, it was NOT given another bite out of the apple to litigate facts already been decided.
In BRC Uluslararasi Taahut VE Ticaret A.S. v. Lexon Ins. Co., 2020 WL 6801933 (D. Maryland 2020), a prime contractor was hired by the federal government to make security upgrades and interior renovations to a United States embassy in the Czech Republic. The prime contractor hired a subcontractor to perform all of the installed contract work. The prime contractor terminated the subcontractor for default during the course of construction.
The subcontractor demanded arbitration in accordance with the subcontract claiming it was wrongfully terminated. The subcontractor also filed a lawsuit asserting a Miller Act payment bond claim against the prime contractor’s surety (as well as a breach of contract action against the prime contractor). The subcontractor made clear it intended to pursue its claims in arbitration and hold the payment bond surety jointly and severally liable. The parties agreed to stay the lawsuit since the facts were identical to those being arbitrated. The arbitration went forward and an award was entered in favor of the subcontractor and against the prime contractor for approximately $2.3 Million.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com