The Burden of Betterment
February 23, 2017 —
Ryan M. Charlson, Esq. - Florida Construction Law NewsThe concept of betterment has long been used by defendants in cases involving defective design or construction to limit the damages awarded to a plaintiff.[1] The theory behind betterment is that: “if in [the] course of making repairs [an] owner adopts a more expensive design, recovery should be limited to what would have been the reasonable cost of repair according to original design.”[2] Betterment is often raised as an affirmative defense, requiring a defendant to prove that the plaintiff has received a good or service that is superior to that for which the plaintiff originally contracted. A recent South Florida case seems, at first blush, to suggest the burden of establishing the value of betterments may fall to the plaintiff, although a closer reading indicates the decision is likely to have limited applicability.
In Magnum Construction Management Corp. v. The City of Miami Beach, the Third District Court of Appeal was asked to review the damages award to the City for construction defects associated with the redesign and improvement of a park.[3] The completed project contained landscaping deficiencies, along with other “minor defects” in the playground’s construction.[4] After a unilateral audit, and without providing the contractor its contractually required opportunity to cure the defects, the City “removed, redesigned, and replaced the playground in its entirety.”[5] It did so despite no recommendation by the City’s own expert to perform such work.[6] During the bench trial, the “only measure of damages provided by the City was the costs associated with the planning, permitting, and construction of a park that is fundamentally different from the one it contracted with [the contractor] to build.”[7]
Read the court decisionRead the full story...Reprinted courtesy of
Ryan M. Charlson, Cole, Scott & Kissane, P.A.Mr. Charlson may be contacted at
ryan.charlson@csklegal.com
Good News on Prices for Some Construction Materials
June 28, 2021 —
ABC - Construction ExecutiveThe elevated price of softwood lumber, a major talking point during much of the pandemic, appears to have peaked in early May at more than $1,700 per thousand board feet. As of June 23, the price has fallen below $900 per board feet, down about 49% in less than two months.
That’s still an unusually lofty price by historic standards—prices remain almost twice as high as in February 2020—but the trend is very much in the right direction. Builders that had been hoarding lumber have now begun to sell from their own inventory, other builders have delayed lumber purchases in anticipation of lower prices and sawmill operators have been adding shifts, as well as expanding capacity, all of which puts downward pressure on prices.
Reprinted courtesy of
ABC, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Underpowered AC Not a Construction Defect
November 07, 2012 —
CDJ STAFFAfter buying a home in Louisiana, Mike Gines determined that the home’s air conditioning unit was insufficient to maintain an appropriate temperature. He contacted the home builder, D.R. Horton, Inc., which worked with the air conditioning installer, Reliant Heating & Air Conditioning, in order to repair the system. When the problems persisted, Gines filed a class action petition against Horton and Reliant in state court. Horton and Reliant moved the case to the federal courts, whereupon Gines asserted the defendants were in violation of the Louisiana New Home Warranty Act (NHWA). Horton stated that the claim under the NHWA was invalid, because Gines had not alleged actual physical damage to his home.
The district court granted Horton’s motion to dismiss. Gines sought a reversal from the Fifth Circuit Court of Appeals and sought to have two questions of state law addressed by the Louisiana Supreme Court.
The district court ruled that the NHWA was the “sole remedy under Louisiana law for a purchaser of a new home with construction defects. Gines argued that court erred in this, but also conceded that this was the conclusion of the Louisiana Supreme Court.
Further, Gines argued that a provision in the NHWA that allows the inclusion of construction defects that do not cause damage was satisfied by paragraph 6 of the contract. The court noted that Gines did not attach a copy of the contract to either the original or amended complaint, and so the court does not need to address these claims. However, the court cautioned that if a copy had been included, they still would have rejected the claim, as “the cited language does not indicate a waiver of the physical damage requirement.” They also note that “paragraph 13 of the contract shows that Gines was aware to the absence of any such waiver in the contract.”
The court concludes that “the moral of this story is that in order to avoid the harsh result that has obtained here, the buyer of a newly constructed home in Louisiana should seek to obtain in the contract of sale an express waiver of the actual damage requirement of the NHWA.” The appeals court affirmed the decision of the circuit court and denied the application to certify questions to the Louisiana Supreme Court.
Read the court decisionRead the full story...Reprinted courtesy of
Brown Paint Doesn’t Cover Up Construction Defects
April 25, 2012 —
CDJ STAFFIn a decision that describes the case as illustrating “the perils that real estate brokers and their agents assume when acting as a dual listing agent to both the buyers and sellers of the same house,” the California Court of Appeals has issued a decision in William L. Lyon & Associates v. The Superior Court of Placer County. Lyon & Associates sought summary judgment to dismiss the claims of the Henleys who bought a home in a transaction where a Lyon agent represented both sides.
The prior owners of the home, the Costas, had used a Lyon agent in purchasing their home. When they later sought to sell it, that agent “became aware of some of the house’s defects and problems.” In response, the Costas sought the help of another agent, Connie Gidal, also of Lyons & Associates. Photos taken in the presence of Ms. Gidal show defects of the paint and stucco. The Costas also took the step of painting the house dark brown. During the sale process, “rain caused many of the painted-over defects to reappear.” The Costas “purchased more dark brown paint and covered up the newly visible damage prior to inspection by the Henleys.”
With the damage concealed, the Henleys bought the home in May 2006. The agreement with Lyons & Associates noted that “a dual agent is obligated to disclose known facts materially affecting the value or desirability of the property to both parties.” Escrow closed on May 9, 2006. The contract with the broker included a two-year limit on the time to bring legal action.
The Henleys moved in during June 2006, and “began to discover construction defects that had been concealed by the Costas.” In addition to the painted-over stucco problems, the Henleys found that the Costas had “installed quartzite stone overlays on the backyard steps in a manner that caused water intrusion on the house’s stucco walls.”
In May 2009, the Henleys sued the Costas, Ron McKim Construction, Lyons & Associates, and Ms. Gidal. Their complaint alleged that Lyons & Associates had committed breach of contact, negligence, fraud, breach of fiduciary duty, and negligent nondisclosure in connection with the construction defects. The Costas named Lyons in a cross complaint. Lyons moved for summary judgments on the grounds that the two-year statute of limitations had expired before the complaint and cross-complaint were filed. Both the Henleys and the Costas opposed this claim. The court denied the motion and Lyons appealed.
The appeals court upheld the denial, noting that the both California Supreme Court decision and later action by the legislature compels real estate brokers and salespersons “to conduct a reasonably competent and diligent visual inspection of the property offered for sale.” The court noted that under California law, brokers have responsibilities to both sellers and buyers. The section of law cited by Lyons applies to seller’s agents. The court rejected the contention by Lyons that they were “cooperating brokers.” The Henleys were “not constrained by the two-year statute of limitations.”
Lyons contended that even if California’s statute did not apply, there was a contractual limit of two years. The court also rejected this, agreeing with the Henleys that “the two-year limitation period must be extended by the discovery rule.”
The court noted that “Lyon & Associates may not reap the benefit of a shortened contractual limitation period when its own alleged malfeasance contributed to the delay in the discovery of the buyer’s injury.” The court found that the Henleys could proceed with their breach of contract claim, because, “when a breach of contract is committed in secret, such as the intentional nondisclosure of a real estate broker regarding a previously visible construction defect, the contractual limitations period is properly held subject to the discovery rule.” The court felt that the interpretation favored by the California Association of Realtors would “halve the applicable statute of limitations period.”
In addition to rejecting Lyon request for summary judgment on the claims made by the Henleys, the court also rejected the request of summary judgment on the claims made by the Costas, concluding that neither claim is time-barred. Costs were awarded to both the Henleys and Costas.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
"Multiple Claims" Provisions on Contractor's Professional Liability Policy Creates a Trap for Policyholders
May 24, 2021 —
Michael V. Pepe - Saxe Doernberger & VitaIn Berkley Assurance Company v. Hunt Construction Group, Inc., 465 F.Supp.3d 370 (S.D.N.Y., 2020), professional liability insurer Berkley sued its insured, Hunt, a construction management firm, seeking a declaration that it did not owe Hunt a duty to defend and indemnify against breach of contract claims. The United States District Court for the Southern District of New York granted Berkley’s motion for summary judgment and denied Hunt’s motion for partial summary judgment. Among other things, the court held that the policy’s automatic extended reporting period did not apply to Hunt’s first claim. The multiple claims provision barred Hunt’s second claim because the claims were related.
The court’s holding creates a potential trap for policyholders who wait to see how a claim develops before reporting it to their insurance carrier. This case demonstrates that waiting to see how a claim develops can result in a loss of coverage. Policyholders need to be aware of this trap and report all claims and circumstances immediately.
Read the court decisionRead the full story...Reprinted courtesy of
Michael V. Pepe, Saxe Doernberger & VitaMr. Pepe may be contacted at
MPepe@sdvlaw.com
LA Metro To Pay Kiewit $297.8M Settlement on Freeway Job
December 08, 2016 —
Greg Aragon – Engineering News-RecordThe Los Angeles County Metropolitan Transportation Authority (LA Metro) has reached an agreement with Kiewit Corp. and will pay the contractor $297.8 million for project change orders on the Interstate 405-Sepulveda Pass Widening Project, in Los Angeles.
Read the court decisionRead the full story...Reprinted courtesy of
Greg Aragon, Engineering News-RecordENR may be contacted at
ENR.com@bnpmedia.com
NY Pay-to-Play Charges Dropped Against LPCiminelli Executive As Another Pleads Guilty
June 06, 2018 —
Mary B. Powers & Debra K. Rubin - Engineerings News-RecordThe former president of New York contractor LPCiminelli—the firm that has been at the center of an alleged pay-to-play scheme playing out since 2016 when he and two other executives were indicted—got a reprieve as federal prosecutors said they were dropping all charges against him, including wire fraud, conspiracy to commit wire fraud and making false statements to federal agents, according to a June 1 court filing.
Reprinted courtesy of
Mary B. Powers, ENR and
Debra K. Rubin, ENR
Ms. Rubin may be contacted at rubind@enr.com
Read the court decisionRead the full story...Reprinted courtesy of
ASCE Statement on Senate Passage of the Water Resources Development Act of 2024
August 12, 2024 —
Marsia Geldert-Murphey, President of the American Society of Civil EngineersWASHINGTON — The
American Society of Civil Engineers (ASCE) commends the Senate for passing S. 4367, the Thomas R. Carper Water Resources Development Act (WRDA) of 2024. Both the House and Senate versions of WRDA will help improve America's ports and inland waterways, enhance flood risk management and storm risk reduction programs, and prioritize ecosystem restoration. ASCE now urges Congress to swiftly conference and pass a final WRDA bill in the upcoming months.
The Senate version of WRDA includes key provisions that will help ensure the ongoing operation of America's inland waterways systems, which received a 'D+' on the
2021 Report Card for America's Infrastructure, including adjustments to the cost share requirements for rehabilitation projects that receive funding the Inland Waterways Trust Fund (IWTF). These changes will ensure the IWTF remains available for future projects to help reduce the backlog of inland waterways projects. This bill also creates a Levee Owners Advisory Board, which has the potential to improve communication between the U.S. Army Corps of Engineers, other federal agencies, and levee owners and operators.
Now that the House and Senate have passed their versions of WRDA, we encourage lawmakers to include several provisions included in the House version in their final conference bill. This includes the reauthorization of the National Dam Safety Program through 2028, provisions that reduce restrictions on the amount of funds states can receive in National Dam Safety Program State Assistance Grants; improves access to the High Hazard Potential Dam Rehabilitation Grant Program; and requires the incorporation of low-head dams into the National Inventory of Dams, and an extension of the National Levee Safety program through 2033.
ABOUT THE AMERICAN SOCIETY OF CIVIL ENGINEERS
Founded in 1852, the American Society of Civil Engineers represents more than 160,000 civil engineers worldwide and is America's oldest national engineering society. ASCE works to raise awareness of the need to maintain and modernize the nation's infrastructure using sustainable and resilient practices, advocates for increasing and optimizing investment in infrastructure, and improve engineering knowledge and competency. For more information, visit www.asce.org or www.infrastructurereportcard.org and follow us on Twitter, @ASCETweets and @ASCEGovRel.
Read the court decisionRead the full story...Reprinted courtesy of