Safe Harbors- not just for Sailors anymore (or, why advance planning can prevent claims of defective plans & specs) (law note)
August 17, 2011 —
Melissa Brumback, Construction Law in North CarolinaHave you ever considered a “Safe Harbor Provision” for your Owner-Architect or Owner-Engineer contract? Maybe it is time that you do.
As you are (probably too well) aware, on every construction project there are changes. Some of these are due to the owner’s change of heart, value engineering concerns, contractor failures, and material substitutions. Some may be because of a design error, omission, or drawing conflict. It happens.
A “Safe Harbor Provision” is a provision that establishes an acceptable percentage of increased construction costs (that is, a percentage of the project’s contingency). The idea is that if the construction changes attributable to the designer is within this percentage, no claim will be made by the Owner for design defects.
Read the full story…
Reprinted courtesy of Melissa Brumback of Ragsdale Liggett PLLC. Ms. Brumback can be contacted at mbrumback@rl-law.com.
Read the court decisionRead the full story...Reprinted courtesy of
Insurer Incorrectly Relies Upon "Your Work" Exclusion to Deny Coverage
June 10, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe Eleventh Circuit reversed the district court's determination that there was no coverage based upon the policy's "your work" exclusion. Southern-Owners Ins. Co. v. Mac Contractors of Fla, LLC, 2019 U.S. App. LEXIS 10689 (11th Cir. April 11, 2019).
Mac Contractors contracted with the homeowners to custom build their home. After construction began, Mac left the site before completing the project and before the issuance of a certificate of occupancy. The homeowners sued, alleged damage to wood floors and the metal roof.
Southern-Owners originally agreed to defend under the CGL policy, but later withdrew the defense and filed this action for declaratory relief. The parties cross-filed motions for summary judgment. Southern-Owners argued that the "your work" exclusion applied to bar coverage. The "your work" exclusion barred coverage for "'property damage' to 'your work' arising out of it or any part of it and included in the 'products' completed operations hazard.'" The "products' completed operations hazard" included all "'property damage' occurring away from premises you own or rent and arising out of . . . 'your work' except . . . (1) products that are still in your physical possession; or (2) work that has not yet been completed or abandoned."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
New Mexico Architect Is Tuned Into His State
February 08, 2021 —
David M. Brown - Engineering News-RecordFor 40-plus years, Van Gilbert has combined his love for the topography, history and culture of New Mexico with an equally passionate dedication to designing not just structures, but buildings that help create communities.
Reprinted courtesy of
David M. Brown, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Architect Searches for Lost Identity in a City Ravaged by War
March 14, 2022 —
Donna Abu-Nasr & Mohamed Sheikh Nor - BloombergOmar Degan got used to being ridiculed when he sat down with developers. The architect wanted buildings to incorporate green spaces, use less glass but have bigger windows to allow in more air. They wanted to maximize profit.
Such a clash of visions between designer and constructor could, of course, happen anywhere. But the gulf between them was particularly wide in a place where people have been more focused on survival than sustainability.
Degan, 31, wants to transform the Somali capital of Mogadishu, a lofty ambition in a city that’s been defined by violence, piracy and terrorism over the past three decades. His persistence, though, has led to prominence by championing cultural heritage and buildings that are in tune with the environment during the frenzy of reconstruction in recent years.
Reprinted courtesy of
Donna Abu-Nasr, Bloomberg and
Mohamed Sheikh Nor, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Will a Notice of Non-Responsibility Prevent Enforcement of a California Mechanics Lien?
March 05, 2015 —
William L. Porter – Porter Law Group, Inc.The “Notice of Non-Responsibility” is one of the most misunderstood and ineffectively used of all the legal tools available to property owners in California construction law. As a result, in most cases the answer to the above question is “No”, the posting and recording of a Notice of Completion will not prevent enforcement of a California Mechanics Lien.
The mechanics lien is a tool used by a claimant who has not been paid for performing work or supplying materials to a construction project. It provides the claimant the right to encumber the property where the work was performed and thereafter sell the property in order to obtain payment for the work or materials, even though the claimant had no contract directly with the property owner. When properly used, a Notice of Non-Responsibility will render a mechanics lien unenforceable against the property where the construction work was performed. By derailing the mechanics lien the owner protects his property from a mechanics lien foreclosure sale. Unfortunately, owners often misunderstand when they can and cannot effectively use a Notice of Non-Responsibility. As a result, the Notice of Non-Responsibility is usually ineffective in protecting the owner and his property.
The rules for the use of the Notice of Non-Responsibility are found in California Civil Code section 8444. Deceptively simple, the rules essentially state that an owner “that did not contract for the work of improvement”, within 10 days after the owner first “has knowledge of the work of improvement”, may fill out the necessary legal form for a Notice of Non-Responsibility and post that form at the worksite and record it with the local County Recorder in order to prevent enforcement of a later mechanics lien on the property.
What commonly occurs however is that early in the process the owner authorizes or even requires its tenant to perform beneficial tenant improvements on the property. This authorization is often set forth in a tenant lease or other written document. The dispositive factor for determining whether the Notice of Non-Responsibility will be enforceable though is that the owner knows that these improvements will be made to the property and intends that they be made, usually long before the work begins. Indeed, the owner has usually negotiated these very terms into the lease contract. The owner then mistakenly believes that once work on the property commences it has 10 days to post and record a Notice of Non-Responsibility and thereby protect itself from a mechanics lien.
The usual error is two-fold. First, the statute states that the Notice is available when the owner “did not contract for the work of improvement”. The fact though is that the owner did contract for the work of improvement. It did so through the lease contract. This is true even though the owner’s contract was not with the contractor or supplier directly. Secondly, the 10 day period to post and record the Notice begins when the owner first “has knowledge” of the work of improvement. This knowledge was of course gained when the lease was negotiated and signed, providing knowledge typically many days before the work has begun. Thus, the 10 day period can also seldom be met. The Notice of Non-Responsibility will therefore fail both rules because the owner has in fact contracted for the improvement and because he does not act within 10 days of gaining this knowledge.
The next event in the typical scenario occurs when the tenant does not pay its contractor. The contractor then has nothing to pay its subcontractors. Material suppliers also go unpaid. Mechanics liens are then recorded by the unpaid claimants, followed by foreclosure actions within ninety days thereafter. Owners will typically point to the Notice of Non-Responsibility they posted and recorded, claiming its protection. Claimants then in turn point to the lease or other evidence that the owner knew of the pending improvements and contracted in some way that the improvements be performed, often also more than 10 days before they posted the Notice. Judges generally agree with the unpaid mechanics lien claimants and the Notice of Non-Responsibility is deemed ineffective.
The fact that the Court does not enforce the Notice of Non-Responsibility under these circumstances is not an unfair result. Since the owner authorized the work to be performed and it received a substantial benefit in the form of those improvements, it is not unfair that the owner should pay for those benefits. It would be inequitable for the owner to obtain the benefit of the improvements which it authorized but for which it did not pay, while allowing those who provided the benefit to go unpaid. Moreover, without such a system in place the door would be open to owners setting up sham “tenants” who would enter into contracts to have work performed, only to disappear when the work is completed, leaving the contractor without a source of payment. The system in place as described above prevents such duplicity. Owners would do well to arm themselves with proper knowledge of when the Notice of Non-Responsibility will and will not protect them and then responsibly use the Notice of Non-Responsibility.
For the legal eagles among you, the following cases illustrate the view of the courts, consistent with the above: Baker v. Hubbard (1980) 101 Cal.App.3d 226; Ott Hardware v. Yost (1945) 69 Cal. App.2d 593 (lease terms); Los Banos Gravel Co. v. Freeman (1976) 58 Cal.App.3d 785 (common interest); Howard S. Wright Construction Co. v. Superior Court (2003); 106 Cal.App.4th 314 (participating owner).
William L. Porter of
Porter Law Group, Inc. located in Sacramento, California may be contacted at (916) 381-7868 or bporter@porterlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Be Proactive, Not Reactive, To Preserve Force Majeure Rights Regarding The Coronavirus
March 30, 2020 —
David Adelstein - Florida Construction Legal UpdatesIf you are involved in construction, NOW is the time to consider the potential force majeure impacts associated with the pandemic Coronavirus. Things are beginning to drastically change on a minute-by-minute basis. From travel restrictions, to the suspension or cancellation of events on an international level, to company-wide policies and restrictions, the global uncertainty has led to the possibility that a force majeure delay will occur. Thinking otherwise is not being proactive. The Coronavirus, and the impacts / delays associated therewith, is beyond anyone’s control. Due to the uncertainty, it is hard to fathom at this time a reasonable challenge to someone’s reaction to this concern or their companywide response to the concern.
If you are a contractor, subcontractor, or even a supplier, my suggestions would be as follows:
- Revisit your contracts and see what type of force majeure language it has – anything relating to delays beyond your control or epidemics;
- Examine to see whether you have a basis for additional compensation AND additional time;
- Examine what type of notice you are required to provide for force majeure events;
- Be proactive – send notice now of the potentiality that this pandemic can impact / delay the job –no one should take offense to this letter as this pandemic has impacted all walks of life;
- If an impact occurs, send follow-up notice accordingly to ensure rights under the contract are preserved; and
- For future contracts, incorporate language that specifically addresses epidemics and pandemics now that the occurrence of this issue has become real.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Dorian’s Wrath: How Event Cancellation Insurance Helps Businesses Recoup Losses from Severe Weather
December 16, 2019 —
Sergio F. Oehninger, Andrea DeField & Daniel Hentschel - Hunton Insurance Recovery BlogAs the 2019 hurricane season peaks, the Bahamas and the Southeast United States have already endured a catastrophic storm. Hurricane Dorian not only tragically caused loss of life and substantial property damage, but it also led to the cancellation or postponement of major events, resulting in considerable economic losses for affected companies.
For instance, Hurricane Dorian forced the cancellation of one of the Rolling Stones’ concerts at Hard Rock Stadium in Miami, as well as the cancellation of R&B singer Chris Brown’s concert in Fort Lauderdale. Dorian also affected the college football game between Florida State University and Boise State University in Jacksonville. Having sold 45,000 tickets to the game, officials were forced to move the game inland to Tallahassee at great expense and effort.
The planners, headliners, teams and fans of these and similar events were not the only ones affected by the cancellations and schedule changes. Hotels, restaurants and businesses relying on tourism also were severely impacted by the schedule changes resulting from Hurricane Dorian over Labor Day weekend. Other programming that may have been affected includes conventions and meetings, fairs and festivals, trade shows and exhibitions, or any other corporate events planned to take place outdoors, requiring travel or with ticket-paying audiences.
Reprinted courtesy of Hunton Andrews Kurth attorneys
Sergio F. Oehninger,
Andrea DeField and
Daniel Hentschel
Mr. Oehninger may be contacted at soehninger@HuntonAK.com
Ms. DeField may be contacted at adefield@HuntonAK.com
Mr. Hentschel may be contacted at dhentschel@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Cal/OSHA Approves COVID-19 Emergency Temporary Standards; Executive Order Makes Them Effective Immediately
July 11, 2021 —
Leila S. Narvid - Payne & Fears LLPOn June 17, 2021, California's Occupational Safety and Health Standards Board (Standards Board) passed amended COVID-19 Emergency Temporary Standards (ETS). Gov. Gavin Newsom issued an Executive Order to make the amended ETS effective as soon as filed with the Secretary of State. The Office of Administrative Law (OAL) filed them, and the Secretary of State posted them, making the ETS effective immediately. These changes attempt to bring the ETS in alignment with recent changes to California Department of Public Health Order and the latest guidance from the Center for Disease Control (CDC). Highlights of the changes to the ETS can be found here.
Face Coverings in the Workplace; Elimination of Physical Distancing
Notably, fully vaccinated employees do not have to wear a face covering indoors except in limited circumstances. Unvaccinated workers will still need to wear face coverings indoors (unless they are alone in a room or eating and drinking) and in shared vehicles. All employees regardless of vaccination status do not have to wear masks outdoors. Unvaccinated employees must be trained that face coverings are recommended outdoors for individuals who are not fully vaccinated when six feet of physical distance cannot be maintained.
Read the court decisionRead the full story...Reprinted courtesy of
Leila S. Narvid, Payne & Fears LLPMs. Narvid may be contacted at
ln@paynefears.com