Wyncrest Commons: Commonly Used Progress Payments in Construction Contracts Do Not Render Them Installment Contracts
December 11, 2023 —
Benjamin J. Hochberg - Peckar & Abramson, P.C.In BIL-JIM Construction Company, Inc. v. Wyncrest Commons, LP, 2023 WL 7276637 (Unpublished, decided November 3, 2023), the New Jersey Appellate Division was asked to consider two issues regarding the interpretation and application of a construction contract that utilized the standard form American Institute of Architects owner/contractor agreement (AIA Document A101-2007) (the “AIA Contract”). Specifically, it was asked to consider: 1) whether a modified AIA Contract was an “installment contract,” whereby each progress payment was subject to its own statute of limitations; and 2) whether and when work had been approved in the context of New Jersey’s Municipal Land Use Law. While the decision is presently unpublished, it provides guidance as to how form contracts utilizing the same or similar terms will be treated by New Jersey’s courts and is a reminder that the potential for future claims must be considered during contract negotiations.
Discussion
The primary issue in Wyncrest was whether an AIA Contract was an “installment contract,” and the remaining issues turned on the resolution of this question. Wyncrest, the owner for the project at issue, did not dispute that its contractor, BIL-JIM Construction Company, Inc., had not been fully paid for work that it had performed in connection with a construction project located in Ocean County, New Jersey. Instead, Wyncrest argued that because its AIA Contract with BIL-JIM required that invoices be presented and paid monthly, it constituted an “installment contract.” As such, older payments would be treated as individual transactions and were time barred by the applicable statute of limitations. The trial court agreed with Wyncrest’s characterization of the AIA Contract as an “installment contract,” and found that BIL-JIM’s invoices were each subject to their own statute of limitations. However, the trial court disagreed with Wyncrest’s argument that BIL-JIM’s claim for retainage—which was submitted at the end of its work at the project—was time barred.
Read the court decisionRead the full story...Reprinted courtesy of
Benjamin J. Hochberg, Peckar & Abramson, P.C.Mr. Hochberg may be contacted at
bhochberg@pecklaw.com
Court Rules that Damage From Squatter’s Fire is Not Excluded as Vandalism or Malicious Mischief
April 15, 2015 —
Valerie A. Moore, Christopher Kendrick, and Colin T. Murphy – Haight Brown & Bonesteel LLPIn Ong v. Fire Insurance Exchange (No. B252773, filed 4/3/15), a California appeals court ruled that a vacancy exclusion limited to damage caused by “vandalism or malicious mischief” did not bar coverage for damage to a vacant property caused by a warming fire purposely started by a transient that got out of control and spread to other parts of the property.
In Ong, the insured’s rental premises had been vacated by tenants and the utilities turned off. Nearly two years later, the insured submitted a claim for fire damage that had just occurred. An investigator reported finding signs that a squatter had been living in the building, stating that: “[I]t appears the fire may have been initiated as the result of an uncontrolled warming fire started by an unauthorized inhabitant.” The investigator found firewood and a mattress, and concluded that holes burned in the floor were the result of the squatter attempting to throw burning wood out the door when the fire got out of control.
The policy excluded vandalism as follows: “We do not cover direct or indirect loss from: . . . 4. Vandalism or Malicious Mischief, breakage of glass and safety glazing materials if the dwelling has been vacant for more than 30 consecutive days . . . just before the loss. A dwelling under construction is not considered vacant.” The term “Vandalism” was not defined in the policy. The insurer denied coverage based on the exclusion, stating: “Our investigation indicates that this loss was the result of vandalism. A trespasser entered the vacant dwelling and intentionally set a fire on the kitchen floor.”
Reprinted courtesy of Haight Brown & Bonesteel LLP attorneys
Valerie A. Moore,
Christopher Kendrick and
Colin T. Murphy
Ms. Moore may be contacted at vmoore@hbblaw.com.
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Mr. Murphy may be contacted at cmurphy@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Bally's Secures Funding for $1.7B Chicago Casino and Hotel Project
August 12, 2024 —
Annemarie Mannion - Engineering News-RecordPlans for a $1.7-billion casino and adjacent 34-story hotel are advancing in Chicago as the gaming operator reports it has secured $940 million to complete funding for the project and has set demolition for a printing press building now occupying the site for this summer.
Reprinted courtesy of
Annemarie Mannion, Engineering News-Record
Ms. Mannion may be contacted at manniona@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Hawaii Supreme Court Tackles "Other Insurance" Issues
February 25, 2014 —
Tred Eyerly – Insurance Law HawaiiResponding to four certified questions from the Ninth Circuit, the Hawaii Supreme Court addressed various issues raised by competing "other insurance" provisions in two CGL policies. Nautilus Ins. Co. v. Lexington Ins. Co., 2014 Haw. LEXIS 59 (Haw. Feb. 13, 2014).
Coverage for a development on Maui was at issue. The developer, VP & PK (ML) LLC, was insured by Lexington. The other insurance provision in Lexington's policy provided it was excess over "any other primary insurance available to you covering liability for damages arising out of the premises . . . for which you have been added as an additional insured."
Kila Kila Construction was one of VP & PK's subcontractors. Kika Kila was not an additional insured under Lexington's policy. Kila Kila had its own CGL policy with Nautilus. The Nautilus other insurance clause stated the insurance was excess over "any other primary insurance available to you covering liability arising out of the premises or operations for which you ahve been added as an additional insured." An endorsement added VP & PK as an additional insured, but only for liability arising out of Kila Kila's negligence.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Pennsylvania “occurrence”
December 30, 2013 —
Scott Patterson — CDCoverageIn Indalex Inc. v. National Union Fire Ins. Co. of Pittsburgh, PA, 2013 WL 6237312 (Pa. Super. 2013), insured Indalex was sued in multiple underlying actions, filed in states other than Pennsylvania, alleging that Indalex defectively designed or manufactured windows and doors resulting in leaks causing damage beyond the Indalex product, including mold, wall cracks, and personal injuries. The complaints included strict liability, negligence, breach of warranty, and breach of contract causes of action. After Indalex’s primary CGL policies exhausted, Indalex filed a declaratory judgment action against its umbrella insurer National Union.
Read the court decisionRead the full story...Reprinted courtesy of
Scott PattersonScott Patterson can be contacted at cdcoverage.com
Congress Addresses Homebuilding Credit Crunch
May 20, 2011 —
CDJ STAFFThe National Association of Home Builders (NAHB) reports that Representatives Gary Miller (CA), Brad Miller (NC) and twenty-nine cosponsors have put forth a bill with bipartisan support to “address the severe credit crunch for acquisition, development, and construction (AD&C) financing.” They report in addition to more than 1.4 million construction workers who have been “idled since 2006,” the housing slump has cost 3 million jobs and $145 million in wages.
NAHB reports that they worked closely with lawmakers on the bill. The association had members meet with legislators both in D.C. and in their home districts. They state that HR 1755 would help homebuilders “find the credit they need to move forward with new or existing projects.”
The bill would allow lenders to use the value upon completion when assessing loan collateral and ban the use of foreclosed or distressed sale properties in assessing values of projects. The would bill would also lessen restrictions by banking regulators, which the lead sponsors said “have hindered federal and state chartered banks and thrifts’ ability to make and maintain loans to qualified small home builders that have viable projects.”
The NAHB is urging members of Congress to cosponsor the bill and is urging the Senate to introduce a companion bill.
Read the full story…
Read HR 1755
Read the court decisionRead the full story...Reprinted courtesy of
Motions to Dismiss, Limitations of Liability, and More
January 23, 2023 —
Christopher G. Hill - Construction Law MusingsRemember BAE Sys. Ordnance Sys. V. Fluor Fed. Sols? I examined that case on two occasions previously here at Construction Law Musings. Previously the discussions were about the
mix (or lack thereof) between fraud and contract and about how
careful contract drafting is key.
In the
most recent opinion in this ongoing litigation from March of 2022, the Court examined various motions to dismiss the Complaint and Counterclaim in the matter. As a reminder, the basic facts are as follows.
The US Army Joint Munitions Command (“Army”) contracted with BAE Systems OrdnanceSystems, Inc. (“BAE”) to operate and maintain the Radford Army Ammunition Plant (“RFAAP”)under a basic ordering agreement (“BOA”). Under BOA Task Order 002, BAE contracted to replace the legacy NC facility at the RFAAP with a newer one (the “NC Project”). Initially, BAE subcontracted the NC Project to Lauren Engineers & Constructors (“Lauren”), but later terminated Lauren. Despite terminating Lauren, BAE’s timeline to complete the NC Project remained unchanged and BAE was required to use Lauren’s design for the NC Project. BAE gave interested bidders access to the Lauren design and other related documents and required the selected subcontractor to perform in accordance with the 85% complete Lauren design, that the Lauren design could be relied on for accuracy, and the selected subcontractor only had to complete the unfinished parts. Fluor Federal Solutions, LLC (“Fluor”) submitted a request for information (“RFI”) asking BAE about the standards referenced in the SOW. Fluor was unable to determine the completeness of the Lauren design but relied on BAE’s assertion that the design was 85% complete. BAE rejected Fluor’s initial bid as being too high given what BAE had already paid Lauren for its design and told Fluor to lower its bid because the design was close to complete. Fluor lowered its price and submitted another bid proposal that outlined a firm-fixed-price design/build that forecasted 32 months to complete the NC Project. BAE awarded Fluor an Undefinitized Contract Action (“UCA”) in the amount of $9 million dollars, later increased to $32 million. Under the UCA, Fluor began procuring materials and physical construction before a formal subcontract was agreed upon. On December 17, 2015, BAE and Fluor agreed to a fixed-price design and build subcontract (the “Subcontract”) in which Fluor agreed to design, construct, and partially commission the NC Project for $245,690,422.00, which included money spent already in the UCA. When this litigation began, Fluor was scheduled to complete its work by December 2020, 2.5 years beyond the originally agreed-upon completion date.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Substantial Completion Explained: What Contractors & Owners Should Know
January 17, 2022 —
Travis Colburn - Ahlers Cressman & SleightA project’s Substantial Completion date is a critical construction milestone for contractors and owners. Depending on the contract, the date of Substantial Completion has project-specific contractual and statutory consequences.
Substantial Completion is an “event” – there is no universal definition of the term. It is generally understood to be (1) a point in time (2) when work performed by the contractor is sufficiently complete (3) where it can be used or occupied for the owner’s intended purpose. The date of Substantial Completion is generally established at the time of contract formation (either as a negotiated or a contract set date), and that date may be adjusted over the course of a project to account for excusable delays.
As a construction professional, your attorney should review and tailor any written agreement to your project-specific needs and risk tolerances prior to execution. Savvy construction professionals often start with standard form agreements promulgated by the American Institute of Architects (“AIA”), the Design-Build Institute of America (“DBIA”), or the Engineers Joint Contract Document Committee (“EJCDC”) as the basis for their construction contracts. The AIA, DBIA, and EJCDC standard forms each contains contract provisions relating to when and what happens once Substantial Completion has occurred, subject to any agreed-to, project-specific deviations.
Read the court decisionRead the full story...Reprinted courtesy of
Travis Colburn, Ahlers Cressman & SleightMr. Colburn may be contacted at
travis.colburn@acslawyers.com