Limiting Plaintiffs’ Claims to a Cause of Action for Violation of SB-800
November 18, 2011 —
Samir R. Patel, Esq., Lorber, Greenfield, & Polito, LLPThere has been a fair share of publicity about the SB-800 amendments to the Civil Code (Civil Code section 896, et seq.) that codified construction defect litigation in 2002. Most of the publicity is geared toward the pre-litigation standards allowing a builder the right to repair before litigation is commenced by a homeowner. Less focus and attention has been given to the fact that violation of the SB-800 performance standards is being used by plaintiff’s counsel as an additional tool in the plaintiff’s pleading tool box against builders. Closer scrutiny to SB-800 reveals that those provisions should in fact act as a limitation to the pleading tools available to plaintiffs and an additional tool for builders in the defense of cases governed by SB-800.
The typical construction defect complaint contains the boiler plate versions of numerous causes of action. These causes of action include Strict Liability, Negligence, Negligence Per Se, Breach of Contract, Breach of Contract – Third-Party Beneficiary, Breach of Express Warranties, Breach of Implied Warranties, among others. The wide array of causes of action leave a defendant “pinned to the wall” because they require a complex defense on a multitude of contract and tort related causes of action. Furthermore, the statutes of limitations as to these claims widely differ depending upon if the particular defect is considered latent or patent. The truth of the matter remains, no matter what the circumstances, if a construction defect matter ultimately goes to trial, it is inevitable that plaintiffs will obtain a judgment on at least one of these causes of action.
On its own, the Strict Liability cause of action can be a thorn in a defendant’s side. A builder is obviously placing a product into the stream of commerce and strict liability is a tough standard to defend against, particularly when it concerns intricate homes comprised of multiple components that originally sold for hundreds of thousands of dollars. A Negligence cause of action can also be difficult to defend because the duty of care for a builder is what a “reasonable” builder would have done under the circumstances. An interpretation of this duty of care can easily sway a jury that will almost always consist of sympathetic homeowners. A Negligence Per Se cause of action can also leave a defendant vulnerable to accusations that a builder violated the Uniform Building Code or a multitude of other obscure municipal construction-related code provisions during the construction of the home. Lastly, the Breach of Contract cause of action leaves a builder relying on dense and intricate purchase and sale agreements with dozens of addenda which leave the skeptical jurors turned off by what they view as one-side, boilerplate provisions. Ultimately, when a matter is about to go to trial, the complexity of these complaints can benefit a plaintiff and increase a plaintiff’s bargaining power against a defendant who is attempting to avoid a potentially large judgment.
Enter the SB-800 statutes. The SB-800 statutes apply to all homes sold after January 1, 2003. Civil Code section 938 specifically states that “[t]his title applies only to new residential units where the purchase agreements with the buyer was signed by the seller on or after January 1, 2003.” (Civil Code §, 938.) As time progresses, more residential construction defect cases will exclusively fall under the purview of SB-800. Slowly but surely more SB-800 governed litigation is being filed, and its exclusive application is looming on the horizon.
On its surface, this “right to repair” regime has left builders with a lot to be desired despite the fact that it is supposed to allow the builder the opportunity to cure any deficiencies in their product before litigation can be filed by potential plaintiffs. However, the application of the time line for repair has shown to be impractical for anything but the most minor problems involving only small numbers of residential units. Moreover, the fact that the fruits of the builder’s investigation into the claimed defects in the pre-litigation context can freely be used as evidence against it in litigation makes builders proceed with trepidation in responding with a repair. For these reasons, more SB-800 litigation can be expected to result due to the shortcomings of the pre-litigation procedures, and savvy defense counsel should anticipate the issues to be dealt with in presenting the defense of such cases at trial.
This fact should not necessarily be met with fear or disdain. Within the SB-800 statutes, the legislature made it clear that they were creating a new cause of action for construction defect claims, but it further made it clear that this cause of action is a plaintiff’s exclusive remedy. The legislature giveth, but at the same time, the legislature taketh away. Throughout numerous provisions within the SB-800 statutes, the Civil Code states that claims for construction defects as to residential construction are exclusively governed by the Civil Code, and that the Civil Code governs any and all litigation arising under breaches of these provisions. Civil Code section 896 specifically states:
In any action seeking recovery of damages arising out of, or related to deficiencies in, the residential construction … the claimant’s claims or causes of action shall be limited to violation of, the following standards, except as specifically set forth in this title. (Civil Code §, 896.)
Civil Code section 896 then provides approximately fifty-plus standards by which a construction defect claim is assessed under that provision. Civil Code section 896 covers everything from plumbing to windows, and from foundations to decks, and in several instances expressly dictates statutes of limitations as to specific areas of construction that severely truncate the 10-year latent damage limitations period. As for any construction deficiencies that are not enumerated within Civil Code section 896, Civil Code section 897 explicitly defines the intent of the standards and provides a method to assess deficiencies that are not addressed in Civil Code section 896. Civil Code section 897 states:
Intent of Standards
The standards set forth in this chapter are intended to address every function or component of a structure. To the extent that a function or component of a structure is not addressed by these standards, it shall be actionable if it causes damage. (Civil Code §, 897.)
Therefore, Civil Code section 897 acts as a catch-all by which defects that are not covered within Civil Code section 896 can be evaluated on a damage standard mirroring the Aas case (damages must be present and actual). The result of sections 896 and 897 being read in combination is a comprehensive, all-inclusive set of performance standards by which any defect raised by Plaintiffs can be evaluated and resolved under a single SB-800 based cause of action.
Civil Code section 943 makes clear that a cause of action for violation of SB-800 performance standards is a plaintiff’s sole remedy for a residential construction defect action. Specifically, Civil Code section 943 states:
Except as provided in this title, no other cause of action for a claim covered by this title or for damages recoverable under 944 is allowed. In addition to the rights under this title, this title does not apply to any action by a claimant to enforce a contract or express contractual provision, or any action for fraud, personal injury, or violation of a statute. (Civil Code §, 943.)
Civil Code section 944 provides the method for computing damages within a construction defect action, as follows:
If a claim for damages is made under this title, the homeowner is only entitled to damages for the reasonable value of repairing any violation of the standards set forth in this title, [and] the reasonable cost of repairing any damages caused by the repair efforts… . (Civil Code §, 944.)
A cursory review of these statutes yields the conclusion that the legislature was attempting to create an exclusive cause of action that trumps all other causes of action where SB-800 applies. The remedy available to plaintiffs is limited to that allowed by the Civil Code. As noted above, “[n]o other cause of action for a claim covered by this title…is allowed.” (Civil Code §, 943.) Therefore, Civil Code sections 896, 897, 943, and 944 specifically prohibit the contract-based and tort-based causes of action typically pled by plaintiffs.
Plaintiff’s counsel has seized upon the language of section 943 to advance the argument that SB-800 still allows a plaintiff to advance typical contract and tort based causes of action. On the surface, this argument may seem compelling, but a minimum of scrutiny of the express language of section 943 dispels this notion. Section 943 says that it provides rights “[i]n addition” to those under the SB-800 Civil Code provisions. Clearly, the language in section 943 is intended to expressly underscore the fact that a plaintiff is not precluded from seeking relief in addition to that allowed under SB-800 for damages not arising from a breach of the SB-800 standards or for damages in addition to those recoverable under Section 944. This language does not provide an unfettered license to bring a Strict Liability, Negligence or other cause of action against a builder where SB-800 applies.
In fact, this language only keeps the door open for plaintiffs to pursue such causes of action not arising from a breach of the SB-800 standards should there be such supporting allegations. For example, if a plaintiff alleges that a builder breached an “express contractual provision” related to the timing of the completion of the home and close of escrow, and the contract specifies damages in this regard, a plaintiff may have a viable separate cause of action for Breach of Contract for recovery of those damages precisely because that is not an issue expressly dealt with in SB-800 in the performance standards under sections 896 and 897, or in the damage recovery terms under 944. As it stands, the vast majority of complaints are seeking redress for violation of the same primary right; that is, defects specifically outlined in Section 896 and 897 or which result in damages as stated in Section 944.
So, how does a builder defend against a complaint that contains multiple causes of action regarding construction defects for a home sold after January 1, 2003? There are numerous ways to approach this. First and foremost, these superfluous and improper causes of action can be attacked by demurrer seeking dismissal of all causes of action other than the cause of action alleging violation of SB-800. If the the time period within which to file a demurrer has passed already, a motion for judgment on the pleadings can be utilized to attack the improper causes of action in the same way as a demurrer can be used for this purpose.
The limitation to a demurrer or motion for judgment on the pleadings is that the judge is restricted to viewing only the four corners of the pleading when making a ruling. It is typical for plaintiffs’ counsel to cleverly (or one might even say, disingenuously) leave the complaint purposely vague to avoid a successful defense attack on the pleadings by not including the original date the residence was sold. In that instance, a motion for summary adjudication can be used to attack a plaintiff’s complaint. By simply providing evidence that the homes were originally sold after January 1, 2003, the improper causes of action should be subject to dismissal by summary adjudication. If the plaintiff is a subsequent purchaser, the builder still has recourse to enforce the pleading limitations under SB-800. Civil Code section 945 states that “[t]he provisions, standards, rights, and obligations set forth in this title are binding upon all original purchasers and their successors-in-interest.” (Civil Code §, 945.)
Attacking a plaintiff’s complaint to eliminate multiple causes of action can have numerous benefits. The practical result is that a plaintiff will only have one viable cause of action. The advantage is that the SB-800 performance standards include the defined performance standards and shortened statutes of limitations periods with regard to specific issues. Furthermore, as to defects which are not specifically provided for in Civil Code section 896, Civil Code section 897 requires a proof of actual damages. Therefore, a plaintiff must provide evidence of current damages and not simply conditions that may potentially cause damage in the future.
The Appellate Courts have yet to directly address and interpret these SB-800 provisions. The time for that is undoubtedly drawing near. For now, however, plaintiffs will have to find ways to accurately plead construction defect claims within the confines of one cause of action for breach of the performance standards enumerated within the Civil Code.
Printed courtesy of Lorber, Greenfield & Polito, LLP. Mr. Patel can be contacted at spatel@lorberlaw.com and Mr. Verbick at tverbick@lorberlaw.com.
Read the court decisionRead the full story...Reprinted courtesy of
Court of Appeal Puts the “Equity” in Equitable Subrogation
October 05, 2020 —
Garret Murai - California Construction Law BlogSubrogation as a concept is well understood in insurance circles. According to the Institute of Risk Management Institute’s glossary of insurance terms subrogation is “the assignment to an insurer by the terms of [a] policy or by law, after payment of a loss, of the rights fo the insured to recover the amount of the loss from one legally liable for it.” In other words, if an insurer comes out of pocket for something someone else broke, the insurer can turn to that responsible party for reimbursement of its out of pocket costs.
Typically, subrogation is, as stated in IRMI’s glossary of insurance terms, a matter of contract and the rights and responsibilities of parties are set forth within the terms of a policy. However, subrogation may, as stated in IRMI’s glossary, also be matter of law. And this is where equitable subrogation comes in.
“Equitable subrogation,” according to IRMI, is “the right of subrogation granted under common law when one party has made a payment on behalf of another and becomes entitled to whatever recovery rights the other party has against a responsible third party.”
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
The Comcast Project is Not Likely to Be Shut Down Too Long
July 13, 2017 —
Wally Zimolong - Supplemental ConditionsJan Von Bergen at the Philadelphia Inquirer reported that work on Comcast’s new tower came to a halt this morning when striking members of Local 542 picketed the Comcast tower project and other union trades refused to cross the picket line. However, this show of solidarity (during the afternoon on the Friday before the Fourth of July) is unlikely to last past the long weekend. Why? Because any conduct by Local 542 aimed at encouraging a work stoppage by other union members is illegal and the companies that employ the sympathetic union members are in breach of contract if they do not work on Tuesday.
Any actions by Local 542 to encourage members of a different trade unions to honor their picket line is a secondary boycott. The National Labor Relations Act prohibits secondary boycotts. Specifically, the NLRA prohibits a union for inducing employees of an employer not subject to a labor dispute to refuse to work.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
Top 10 OSHA Violations For The Construction Industry In 2023
February 26, 2024 —
Dominic Donato & Jeff Miragliotta - Kahana FeldEvery year, the Occupational Safety and Health Administration (OSHA) publishes their top violations in the construction industry. And typically, the most common violations are consistent year after year. What separates 2023 is the number of citations involving Fall Protection, Scaffolding, Ladders, and the failure to use personal protective equipment (PPE) or other life safety equipment (LSE). The following is the list of the Top Ten OSHA violations for 2023:
(10) Toxic and Hazardous Substances. There were 382 citations issued for “hazardous communication” and improper warnings issued to construction employees.
(9) Excavations. There were 395 citations issued for failure to provide proper and specific excavation requirements and instructions.
(8) Scaffolding – Aerial Lifts. There were 481 citations issued for improper lifting equipment and supports for building scaffolding.
Reprinted courtesy of
Dominic Donato, Kahana Feld and
Jeff Miragliotta, Kahana Feld
Mr. Donato may be contacted at ddonato@kahanafeld.com
Mr. Miragliotta may be contacted at jmiragliotta@kahanafeld.com
Read the court decisionRead the full story...Reprinted courtesy of
Injury to Employees Endorsement Eliminates Coverage for Insured Employer
February 01, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe court granted summary judgment to the insurer based upon an endorsement which barred coverage for injuries to employees. Northfield Ins. Co. v. Z&J Mgt. LLC, 2020 N.Y. Misc. LEXIS 10801 (N.Y. Sup. Ct. Dec. 18, 2020).
Ravi Sooklal sued his employer, Z&J Management LLC (Z&J), for injuries at the job site. Northfield, who had issued a CGL policy to Z&L, denied coverage based upon two endorsements. The first was titled "Injury to Employees of Insureds" and the second was "Employers' Liability." Northfield sued for a declaratory judgment and now moved for summary judgment.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Real Estate & Construction News Roundup (05/10/23) – Wobbling Real Estate, Booming (and Busting) Construction, and Eye-Watering Insurance Premiums
May 22, 2023 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, the commercial real estate sector continues to wobble, construction booms and busts, flood insurance premiums reach eye-watering levels, and more.
- In its latest Financial Stability report, the Federal Reserve acknowledges that the shaky commercial real estate sector could potentially harm the U.S. financial system. (Courtenay Brown, Axios)
- New data from the California Department of Finance shows that even though the state’s population significantly decreased during the COVID-19 pandemic, home building soared, reaching levels not seen since 2008. (Terry Castleman, Los Angeles Times)
- Already weakened by rising interest rates, inflation and debt, Sweden’s real estate sector took another hit as SBB’s shares continued to slump. (Reuters)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
General Contractor’s Excess Insurer Denied Equitable Contribution From Subcontractor’s Excess Insurer
December 15, 2016 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Advent v. National Union Fire Ins. Co., etc. (No. H041934 filed 12/6/16), a California appeals court refused to order a subcontractor’s excess insurer to contribute to a general contractor’s excess insurer because the general contractor did not qualify as an additional insured of the subcontractor’s insurer, and the policy wording made the subcontractor’s excess insurer second level excess above the general contractor’s own excess insurance.
Advent was the general contractor on a housing development and Johnson was a sub-subcontractor providing concrete on perimeter walls. A Johnson employee dispatched to retrieve plywood dumped between some of the buildings somehow fell down an open stairwell inside one of the unfinished buildings and suffered serious injury. He sued Advent and others for negligence, but could not remember how he fell.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Oregon Supreme Court Confirms Broad Duty to Defend
November 21, 2017 —
Theresa A. Guertin - Saxe Doernberger & Vita, P.C. BlogOriginally published by CDJ on January 13, 2017
The Supreme Court of Oregon issued a decision at the end of last year which perfectly illustrates the lengths to which a court may go to grant a contractor’s claim for defense from its insurer in a construction defect suit. In West Hills Development Co. v. Chartis Claims, Inc.,1 the Court held that a subcontractor’s insurer had a duty to defend a general contractor as an additional insured because the allegations of a homeowner’s association’s complaint could be interpreted to fall within the ambit of coverage provided under the policy—despite the fact that the policy only provided ongoing operations coverage, and despite the fact that the subcontractor was never mentioned in the complaint. The decision is favorable to policyholders but also provides an important lesson: that contractors may avoid additional insured disputes if those contractors have solid contractual insurance requirements for both ongoing and completed operations risks.
Read the court decisionRead the full story...Reprinted courtesy of
Theresa A. Guertin, Saxe Doernberger & Vita, P.C.Ms. Guertin may be contacted at
tag@sdvlaw.com