Attorney's Erroneous Conclusion that Limitations Period Had Not Expired Was Not Grounds For Relief Under C.C.P. § 473(b)
February 27, 2019 —
David W. Evans & Stephen J. SquillarioIn Jackson v. Kaiser Foundation Hospitals, Inc. (2/8/19 No. A150833), the First District Court of Appeal affirmed the trial court’s denial of a motion for relief from a voluntary dismissal, without prejudice, filed by the plaintiff based on the erroneous conclusion of an attorney who she had consulted (but who had not yet appeared as counsel in her case) that the applicable statute of limitations had not yet expired. In reality, the limitations period had expired on the same date plaintiff had filed her complaint in propria persona. The plaintiff later retained the attorney on a limited basis to present the motion for relief pursuant to Code of Civil Procedure § 473(b) based on the attorney’s affidavit of fault. Therein, the attorney testified that he had advised the plaintiff to dismiss her action voluntarily based on a misinterpretation of the applicable limitations period, which the attorney characterized as having been based on his “mistake, inadvertence, surprise, or neglect.”
Section 473 provides two distinct provisions for relief from default or dismissal – one is discretionary, while the other is mandatory. Discretionary relief is available in the case of an attorney’s mistake, inadvertence, surprise, or excusable neglect. In contrast, mandatory relief is available where the resulting dismissal was caused by an attorney’s mistake, whether or not excusable. In denying the plaintiff’s motion, the trial court reasoned that the plaintiff could not rely upon Section 473(b) because (1) the attorney did not represent the plaintiff at the time and (2) this provision did not apply to the voluntary dismissal of an action without prejudice.
Reprinted courtesy of
David W. Evans, Haight Brown & Bonesteel LLP and
Stephen J. Squillario, Haight Brown & Bonesteel LLP
Mr. Evans may be contacted at devans@hbblaw.com
Mr. Squillario may be contacted at ssquillario@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Application of Efficient Proximate Cause Doctrine Supports Coverage
January 06, 2012 —
Tred R. Eyerly - Insurance Law HawaiiRelying on the efficient proximate cause doctrine, the court determined coverage potentially existed for damage caused by water. Union Sav. Bank v. Allstate Indem. Co., 2011 U.S. Dist. LEXIS 134398 (S.D. Ind. Nov. 21, 2011).
The Tods purchased property that was mortgaged by Union Savings. The Tods obtained a Landlords Policy for the property from Allstate. When the Tods were in default on their loan, Union Savings notified them that foreclosure proceedings would commence. Union Savings sent an appraiser to the property who discovered water in the basement. Water and electricity to the building were off. Union Savings notified Allstate and later filed a formal claim under the mortgagee clause in the Landlords Policy. This clause stated, "A covered loss will be payable to the mortgagees named on the policy declaration. . . ."
Allstate denied coverage, citing exclusions for water damage.
Read the full story…
Reprinted courtesy of Tred R. Eyerly, Insurance Law Hawaii. Mr. Eyerly can be contacted at te@hawaiilawyer.com
Read the court decisionRead the full story...Reprinted courtesy of
Preparing Your Business For Internal Transition
October 14, 2019 —
Stephen P. Katz, Esq. - ConsensusDocsWhen is it right to start thinking about succession planning and preparing a construction company for transition? Many would agree – in concept, at least – that serious thought regarding succession and transition planning should begin at a company’s inception and be revisited throughout its lifecycle, but as a practical matter, it is frequently not part of the mindset when growing a business. This article explores issues that construction company owners should consider in order to achieve smooth transition of ownership and control. We will address three critical questions:
- What happens to the business when an owner retires;
- In the event an owner(s) become disabled; and,
- Unplanned exit/owner pre-deceases her/his exit from the company
Owners who do not plan carefully for transition are often faced with the less than appealing option of liquidating their business for much less than its value, or by closing the business with no return upon that event. However, those who plan carefully can realize the value of their life’s work, pass the business to the next generation and see their legacy continue.
Read the court decisionRead the full story...Reprinted courtesy of
Stephen P. Katz, Esq., Peckar & Abramson, P.C.Mr. Katz may be contacted at
skatz@pecklaw.com
Reaffirming the Importance of Appeal Deadlines Under the Contract Disputes Act
January 26, 2017 —
Chadd Reynolds – Autry, Hanrahan, Hall & Cook, LLPA recent United States Court of Federal Claims (“COFC”) decision emphasizes the importance of deadlines for appealing a contracting officer’s (“CO”) decision under the Contract Disputes Act (“CDA”). On July 22, 2016, the COFC granted the consolidation of two naval contract dispute appeals totaling nearly $12.4 million in response to Nova Group/Tutor-Saliba’s (“NTS”) motion to resolve two Requests for Equitable Adjustment (“REA”) in the same forum. See Nova Group/Tutor-Saliba v. United States, No. 15-885C, 2016 WL 4009886, at *5 (Fed. Cl. July 22, 2016). NTS’s motion before the COFC sought to transfer an appeal of a REA before the COFC to the Armed Services Board of Contract Appeals (“ASBCA”), where another appeal of a REA arising under the same contract was presently on appeal. The COFC rejected NTS’s appeal to transfer the REA to the ASBCA because NTS did not appeal the REA within the 90-day limit under the CDA. Instead, the COFC allowed NTS to transfer the REA before the ASBCA to the COFC because timeliness was not an issue.
Read the court decisionRead the full story...Reprinted courtesy of
Chadd Reynolds, Autry, Hanrahan, Hall & Cook, LLPMr. Reynolds may be contacted at
reynolds@ahclaw.com
The Importance of a Notice of Completion to Contractors, Subcontractors and Suppliers
August 12, 2024 —
William L. Porter - Porter Law GroupThe recording of a valid “Notice of Completion” with the County Recorder is an event of significance to owners, contractors, subcontractors and suppliers alike. The recording of a Notice of Completion is one of several methods used to trigger the time period for the recording of mechanics liens and service of stop payment notices. Although the recording of a Notice of Completion is not absolutely required on any given project, all those working in the construction industry should understand its significance.
When a valid Notice of Completion has not been recorded in relation to a construction project, a contractor, subcontractor, or supplier might from ninety to one hundred fifty days after completion of the project to record a mechanics lien or serve a stop payment notice to secure payment for their services on the project, depending on the facts. However, if a valid Notice of Completion is recorded, then the deadline under most circumstances accelerates and subcontractors and suppliers must record a mechanics lien or serve a stop payment notice within only thirty days thereafter. Under the same circumstances, a prime contractor has only sixty days after the recording of a valid Notice of Completion to record a mechanics’ lien. Failure to meet these deadlines often results in loss of the right to a mechanics lien or stop payment notice. There are limited exceptions to these general deadlines, depending on the facts. If you believe you may have missed an important deadline to seek collection of a construction debt, you should consult with a construction attorney immediately to secure your avenues of collection, including the mechanics lien and stop payment notice remedies, if still available.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Engineer Pauses Fix of 'Sinking' Millennium Tower in San Francisco
September 13, 2021 —
Richard Korman - Engineering News-RecordEngineers paused work for at least two weeks on the $100-million foundation upgrade for San Francisco's 645-ft-tall Millennium Tower high-rise residential condominium after measurements showed increased settlement during the installation of pile casings for the new piles.
Reprinted courtesy of
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Paris ‘Locks of Love’ Overload Bridges, Threatening Structures
June 11, 2014 —
Helene Fouquet and Mark Deen - BloombergLe Pont des Arts, the landmark Paris footbridge that links the Louvre museum to the Saint Germain neighborhood, is buckling under the weight of “love locks.”
The Paris mayor’s office closed the bridge last night to replace a grate after thousands of locks weighed down its structure. Its railings are crumbling, threatening pedestrians on the bridge and cruise boats that ply under it on the Seine River. The bridge was reopened today after it was checked for safety, with two fire-department boats standing by to avert any potential incident.
Although the origins of the trend are unclear, it has become a tradition for lovers to attach a lock to the railing on the sides of bridges in Paris to seal their love. Each lock weighs about 54 to 90 grams. The mayor of Paris’s 6th arrondissement, where the bridge is located, says the locks on the Pont des Arts weigh as much 10 tons, or 22,000 pounds. The grate that collapsed yesterday weighed about 200 kilos and the bridge has about 50 of them.
Ms. Fouquet may be contacted at hfouquet1@bloomberg.net; Mr. Deen may be contacted at markdeen@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Helene Fouquet and Mark Deen, Bloomberg
Condo Building Increasing in Washington D.C.
November 05, 2014 —
Beverley BevenFlorez-CDJ STAFFBuilder reported that in Washington D.C., "the condo pipeline has increased for the first time since 2005, according to Alexandria, Va.,-based research firm Delta Associates." Supply has grown with "3,100 units either being marketed or sold in around the nation's capital." Furthermore, "condo prices have jumped 12 percent year over year."
“The size of the projects are smaller than they were in the last boom cycle,” William Rich, senior vice president and multifamily practice director at Delta, told Builder.
Read the court decisionRead the full story...Reprinted courtesy of