Attention Contractors: U.S. Department of Labor Issues Guidance on Avoiding Discrimination When Using AI in Hiring
November 25, 2024 —
Matthew DeVries - Best Practices Construction LawI recently blogged about the use of
AI and ChatGBT in the construction industry. Today’s guest post by
Alexandra Shulman and
Leah Lively addresses the recent guidance by the USDOL on the issue of using AI when hiring in recruitment, which is applicable to those constructions who use AI in the recruitment process.
AI in hiring: About 80% of U.S. and almost all Fortune 500 companies use AI-powered hiring software. AI may be used to target online advertising for job opportunities and to match candidates to jobs on employment platforms (e.g., LinkedIn, Indeed). AI may also be used to reject or rank applicants using automated resume screening and chatbots based on knockout questions, keyword requirements, or specific qualifications or characteristics.
Read the court decisionRead the full story...Reprinted courtesy of
Matthew DeVries, BuchalterMr. DeVries may be contacted at
mdevries@buchalter.com
Replevin Actions: What You Should Know
November 08, 2021 —
Craig H. O'Neill - White and Williams LLPA contractor client of White and Williams recently found itself in a prickly situation. They had default terminated a subcontractor on a major commercial project and withheld payment to that subcontractor on an outstanding invoice as permitted under the terms of the subcontract until the project was completed. Clearly irate over being terminated, the subcontractor walked-off of the project with thousands of dollars’ worth of project materials and equipment that had been paid for by the owner. While on some projects this may amount to nothing more than an annoyance or inconvenience, in this case it was a significant problem because some of the wrongfully removed materials were custom manufactured overseas and not easily replaceable. The client therefore needed to take immediate action to retrieve the stolen materials so that the project would not be delayed. Specifically, it needed to file a replevin action against the subcontractor.
A replevin action is a little known but powerful area of the law. In its simplest terms, replevin is a procedure whereby seized goods may be provisionally restored to their owner pending the outcome of an action to determine the rights of the parties concerned. The requirements of a replevin action differ by jurisdiction. For example, in Pennsylvania, the Rules of Civil Procedure devote an entire section to replevin actions and spell out in precise detail the steps that must be taken. While you should be sure to strictly comply with the rules in your jurisdiction, here are a few general points to keep in mind:
- Where to File: A replevin action is typically commenced by filing a complaint in the appropriate jurisdiction. Generally speaking, it is best to file the action in the jurisdiction where the improperly seized materials are being held. If that location is unknown, you can also typically file the action in the jurisdiction where the project is located.
Read the court decisionRead the full story...Reprinted courtesy of
Craig H. O'Neill, White and Williams LLPMr. O'Neill may be contacted at
oneillc@whiteandwilliams.com
Approaches to Managing Job Site Inventory
January 04, 2018 —
Jessica Stark - Construction InformerOriginally Published by CDJ on August 30, 2017
There is no question that organization on the job site can mean the difference between efficient performance and costly errors. A simple mistake can cost a company thousands, which is why details are carefully articulated and supervisors become better scrutinizers than magazine editors. But for some reason, many companies don’t consider managing job site inventory under this same attentive category, or perhaps they don’t know about the technology available to help them do it.
For contractors, keeping track of every piece of material and equipment lowers losses and keeps crews busy. This is especially true for contractors in the trades who often have specialized equipment in inventory such as power supplies, HVAC “smart energy” components or inspection equipment. Once everything is accounted for, the possibility of loss is decreased and there’s a chance to evaluate the use of all materials and equipment. This can show the efficiency of allotted resources. Is there enough equipment on the site to get tasks completed? Is there a need for more? Less? Having excess equipment can sometimes prepare a crew for problem scenarios. But it can also mean the construction company is overpaying for unneeded resources. However, the only way to know is by effectively managing job site inventory. That includes all equipment and materials
Read the court decisionRead the full story...Reprinted courtesy of
Jessica Stark, Construction Informer
Pre-Suit Settlement Offers and Construction Lien Actions
July 21, 2018 —
David Adelstein - Florida Construction Legal UpdatesIt is unfortunate, but in certain matters, a construction lien foreclosure action is not actually driven by the principal amount in dispute. Oh no. Rather, it is driven by attorney’s fees. That’s right. Attorney’s fees. This is true even though Florida applies the significant issues test to determine the prevailing party for purposes of attorney’s fees. However, oftentimes the prospect of attorney’s fees is enough for parties to fear that exposure.
There is a 1985 Florida Supreme Court case that I like to cite if applicable, C.U. Associates, Inc. v. R.B. Grove, Inc., 472 So.2d 1177, 1179 (Fla. 1985), that finds, “in order to be a prevailing party entitled to the award of attorney’s fees pursuant to section 713.29 [a construction lien claim], a litigant must have recovered an amount exceeding that which was earlier offered in settlement of the claim.” Accord Sullivan v. Galske, 917 So.2d 412 (Fla. 2d DCA 2006) (explaining that although contractor is receiving a judgment in his favor, he may not be the prevailing party if the homeowner offered to settle prior to the lawsuit for an amount equal to or greater than the award in the judgment).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Delays Caused When Government (Owner) Pushes Contractor’s Work Into Rainy / Adverse Weather Season
January 13, 2020 —
David Adelstein - Florida Construction Legal UpdatesThere are a number of horizontal construction projects where a contractor’s sequence of work and schedule is predicated on avoiding the rainy season (or certain force majeure events). The reason is that the rainy season will result in delays due to the inability to work (and work efficiently) during the adverse weather (including flooding caused by the weather). If the work is pushed into the rainy season, is such delay compensable if the government (or owner) delayed the project that pushed work out into the rainy season? It very well can be.
For example, in Meridian Engineering Co. v. U.S., 2019 WL 4594233 (Fed. Cl. 2019), a contractor was hired by the Army Corps of Engineers to construct a flood control project for a channel in Arizona. Due to delays, including those caused by the government, the project was pushed into the monsoon season, which caused additional delays largely due to flooding caused by the heavy rain. One issue was whether such delays were compensable to the contractor – the government raised the argument that the contractor assumed the risk of potential flooding from the rainy season. The Court found this argument unconvincing:
[The contractor’s] initial construction schedule planned for a completion of the channel invert work, a necessary step in protecting the site from flooding, to be completed by late June 2008…[M]any issues arose in the project’s early stages that led to cumulative substantial delay, including those caused by the government’s failure….The government cannot now claim that [the contractor] assumed the risk of flooding from monsoon season when the government was largely responsible for [the contractor’s] inability to complete the project prior to the beginning of the monsoon season. Simply put, the government cannot escape liability for flood damages when the government is responsible for causing the contractor to be working during the flood-prone season.
Meridian Engineering, 2019 WL at *7 (internal citations omitted)
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
California Governor Signs SB 496 Amending California’s Anti-Indemnity Statute
June 05, 2017 —
William S. Bennett - Saxe Doernberger & Vita, P.C.The bill amends Cal. Civ. Code § 2782.8 as it applies to indemnity agreements with design professionals. The pre-existing § 2782.8 prohibited public agencies from requiring indemnity from design professionals for anything other than claims arising out of, pertaining to, or relating to the negligence, recklessness, or willful misconduct of the design professional.
Under the newly passed bill, the indemnity restrictions imposed on public agencies when contracting with design professionals will now apply to all parties contracting with design professionals for professional services (effective Jan. 1, 2018). These restrictions also apply to a party contractually imposing a defense obligation on the design professional.
The revised statute specifically identifies architects, landscape architects, professional engineers, and professional land surveyors as included within the meaning of “design professional,” however it is unclear whether that is the extent of the phrase’s meaning.
Read the court decisionRead the full story...Reprinted courtesy of
William S. Bennett, Saxe Doernberger & Vita, P.C.Mr. Bennett may be contacted at
wsb@sdvlaw.com
New York Appellate Court Expands Policyholders’ Ability to Plead and Seek Consequential Damages
February 27, 2019 —
Michael S. Levine & Joshua S. Paster - Hunton Andrews KurthIn a huge win for policyholders, a New York appellate court, in D.K. Property, Inc. v National Union Fire Insurance Company of Pittsburgh, Pa., held that an insured need not provide a detailed factual description or explanation for why consequential damages are recoverable at the pleading stage. Rather, an insured’s complaint must only (i) specify the types of consequential damages claimed; and (ii) allege that those damages reasonably were contemplated by the parties prior to contracting.
Here, D.K. Property’s building was damaged as a result of construction on an adjoining building, and it timely filed a claim with National Union under a policy that covers “direct physical loss or damage to” the building. National Union neither paid the claim nor disclaimed coverage. Instead, according to D.K. Property, National Union made unreasonable and increasingly burdensome information demands over a three-year period, which it alleges was a “tactic” to make pursuing the claim so expensive that D.K. Property would abandon the claim. As a result of the delay, D.K. Property alleges the structural damage to its building has worsened.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Joshua S. Paster, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Paster may be contacted at jpaster@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Key Economic & Geopolitical Themes To Monitor In 2024
January 16, 2024 —
Global Insights Center Staff - The HartfordSlowing US Economic Growth and Flattening Interest Rates
Growth in the first half of 2023 averaged approximately 2.0%, driven mainly by private sector investments outside of the residential housing sector, government spending, and strong consumer demand. In 2024, The Hartford’s Global Insights Center is expecting investments and government spending to continue and may support growth in the year. However, consumer health may start to weaken due to elevated leverage, higher interest rates, and sticky inflation.
Since the Federal Reserve began to increase interest rates, consumer activity and household finances have not been tremendously affected. However, as revolving interest rates (credit card loans) continue to reset that may change, especially since household savings rates fell below pre-pandemic levels and may affect consumer demand.
Read the court decisionRead the full story...Reprinted courtesy of