There Are Consequences to Executed Documents Such as the Accord and Satisfaction Defense
October 01, 2024 —
David Adelstein - Florida Construction Legal UpdatesA federal government contractor in Jackson Construction Co., Inc. v. U.S., 62 Fed.Cl. 84 (Fed.Cl. 2024) sought delay damages against the government. It lost. The reason for the loss is a crucial reminder that documents parties sign ALWAYS matter. ALWAYS!!
In Jackson Construction Co., the contractor’s delay claim was premised on relocating a waterline. The contractor, however, received additional money for relocating the waterline, but no additional time, and this was memorialized in a modification to the contract (i.e., a change order). In executing the modification for the additional work, the contractor did NOT reserve rights for time or money. Indeed, the modification reflected that the monetary adjustment constitutes full compensation for the additional work including delay, namely:
The contract period of performance remains the same. It is further understood and agreed that this adjustment constitutes compensation in full on behalf of the contractor and his subcontractors and suppliers for all costs and markup directly or indirectly, including extended overhead, attributable to the change order, for all delays related thereto, and for performance of the change within the time frame stated.
Jackson Construction Co., supra, at 90.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Taylor Morrison Home Corp’ New San Jose Development
October 15, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Silicon Valley Business Journal reported that Taylor Morrison Home Corp has made the “biggest land acquisition so far in San Jose” after acquiring “an 8-acre chunk of dirt in the developing Montecito Vista area where it has plans to build out 184 townhomes.”
The developer “paid about $32.5 million, or roughly $176,600 per buildable unit, for the land, according to public tax records,” according to the Silicon Valley Business Journal. Construction is scheduled to begin November of 2015 and models should be ready by April of 2016.
Read the court decisionRead the full story...Reprinted courtesy of
Texas Windstorm Insurance Agency Under Scrutiny
April 05, 2011 —
Beverley BevenFlorez CDJ STAFFRepresentative Larry Taylor has introduced a bill in the Texas Legislature (HB 2818) that would further regulate the Texas Windstorm Insurance Agency (TWIA). According to Taylor, “In order to be adequately prepared for future hurricane seasons, it is imperative that TWIA be operating at maximum efficiency, that the Reserve Trust Fund be solvent and that the agency have adequate management measures in place to protect consumers and ensure that claims are paid in a timely manner. House Bill 2818 is an important step in the right direction toward restoring public confidence in TWIA.”
HB 2818 includes measures that would create an expert panel that would advise the commissioner on how to evaluate loss from the storm, and a greater transparency of TWIA Board meetings and actions.
In addition, the Texas Department of Insurance (TDI) has placed TWIA on Administrative Oversight. According to TDI, “While under Administrative Oversight, the Department may require its prior review and approval of executive decisions, certain expenditures, and other transactions. The insurer is required to fully cooperate with the Department and provide complete and timely disclosure of all information responsive to Department requests.”
Read the full story (Rep. Taylor’s Press Release)...
Read the full story (Texas Department of Insurance’s Press Release)...
Read the court decisionRead the full story...Reprinted courtesy of
Supreme Court Overrules Longstanding Decision Supporting Collection of Union Agency Fees
July 02, 2018 —
Amy R. Patton, Blake A. Dillion, & Eric C. Sohlgren - Payne & FearsIn a 5 to 4 opinion, the United States Supreme Court overruled a longstanding decision which required government employees who are represented by but do not belong to a union, to pay a fair share or agency fee to cover the union's costs for collective bargaining activities. In Janus v. American Federation of State, County, and Municipal Employees, Council 31, 585 U.S. ___ (2018), the Supreme Court found that requiring such fees from nonconsenting public sector employees violates the First Amendment: "[n]either an agency fee nor any other form of payment to a public-sector union may be deducted from an employee, nor may any other attempt be made to collect such a payment, unless the employee affirmatively consents to pay."
Reprinted courtesy of Payne & Fears attorneys
Amy R. Patton,
Blake A. Dillion and
Eric C. Sohlgren
Ms. Patton may be contacted at arp@paynefears.com
Mr. Dillion may be contacted at bad@paynefears.com
Mr. Sohlgren may be contacted at ecs@paynefears.com
Read the court decisionRead the full story...Reprinted courtesy of
Preservationists Want to Save Penn Station. Yes, That Penn Station.
December 20, 2021 —
Kriston Capps - BloombergIn November, as one of her first major acts since taking office, New York Governor Kathy Hochul pared back development plans for New York City’s Pennsylvania Station set in place by her predecessor, disgraced former governor Andrew Cuomo.
The Cuomo plan would have greatly expanded Penn Station and upscaled the neighborhood; Hochul’s vision narrows the scope of work, but it still stands to dramatically transform the subterranean transportation hub, which has been the focus of various unrealized redesign dreams for decades. On Dec. 8, critics and supporters sounded off on the Penn Station scheme in a public hearing. More than 200 people registered to weigh in on how the 10 new skyscrapers coming to the area (shrunk down a bit under Hochul) would affect the scale and character of the community, and the historic buildings that would need to be razed to make way for new development.
Read the court decisionRead the full story...Reprinted courtesy of
Kriston Capps, Bloomberg
Minnesota Addresses How Its Construction Statute of Repose Applies to Condominiums
April 27, 2020 —
William L. Doerler - The Subrogation StrategistCourts often struggle with the question of when the statute of repose starts to run for construction projects that involve multiple buildings or phases. In Village Lofts at St. Anthony Falls Ass’n v. Housing Partners III-Lofts, LLC, 937 N.W.2d 430 (Minn. 2020) (Village Lofts), the Supreme Court of Minnesota addressed how Minnesota’s 10-year statute of repose, Minn. Stat. § 541.051, applies to claims arising from the construction of a condominium complex. The court held that the statute of repose begins to run at different times for: a) statutory residential warranty claims brought pursuant to Minn. Stat. §§ 327A.01 to 327A.08, et. seq.; and b) common law claims arising out of the defective and unsafe condition of the condominium buildings.
As stated in Village Lofts, Housing Partners III-Lofts, LLC (Housing Partners) developed the Village Lofts at St. Anthony Falls, a condominium complex consisting of Building A and Building B. Housing Partners retained Kraus-Anderson Construction Company (Kraus-Anderson) as the general contractor for Building A. Kraus-Anderson retained Elness Sweeney Graham Architects, Inc. (ESG), Doody Mechanical, Inc. (Doody) and Kenneth S. Kendle, P.E. (Kendle) to work on Building A. In September 2002, the City of Minneapolis (City) issued a partial certificate of occupancy (CO) for Building A, including the building’s public spaces. On October 4, 2002, Housing Partners filed the declaration creating the Village Lofts at St. Anthony Falls condominium, to be operated by Village Lofts at St. Anthony Association (Village Lofts Association). On October 10, 2002, Housing Partners sold the first unit in Building A and in November of 2003, the City issued a CO for the entire building, excluding two units.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Doerler, White and Williams LLPMr. Doerler may be contacted at
doerlerw@whiteandwilliams.com
More on Fraud, Opinions and Contracts
February 06, 2019 —
Christopher G. Hill - Construction Law MusingsHere at Construction Law Musings, I have discussed the interaction between fraud and contracts on many occasions. Recently, I got to put my advice into action. I am counsel for the plaintiff in the matter of Environmental Staffing Acquisition Corp. v. Beamon, et. al. in the Portsmouth, VA Circuit Court and recently got a great opinion (.pdf) right on point that was recently featured in Virginia Lawyers Weekly.
The basic facts are these. My client, Environmental Staffing (En-Staff) filed a Little Miller Act claim and a claim for breach of contract for Beamon’s failure to pay for temporary staffing that En-Staff provided it at the Jeffry Wilson housing project demolition in Portsmouth, VA. Beamon then counterclaimed for fraud and breach of contract claiming that some statements to the effect that a particular supervisor was qualified along with presentation of the individual’s resume constituted fraud. My client demurred to the two fraud counts (actual and constructive).
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Three Key Takeaways from Recent Hotel Website ADA Litigation
April 26, 2021 —
Shane Singh & Grace Mehta - Lewis BrisboisDespite the COVID-19 pandemic and its chill on the hospitality industry, ADA-related digital lawsuits increased by approximately 23% in 2020. Many of these lawsuits are filed against hotels. The complaints allege that a hotel’s online reservation system failed to provide enough detail for individuals with disabilities to decide if the hotel meets their accessibility needs.
These plaintiffs will often claim that it is insufficient to describe an aspect of a hotel or room as “accessible” because the term is an opinion or conclusion. Plaintiffs argue that a hotel’s reservation system must report specific information, such as the dimensions of space under accessible desks and sinks, the slopes of surfaces, doorway clearance, and numerous other technical requirements under the ADA.
Many hotels are fighting back, arguing that the detail provided is sufficient and in compliance with the ADA. So far this year, in February 2021, two judges in the U.S. District Court for the Central District of California, Judge Percy Anderson and Judge Cormac Carney, agreed with the defendants, dismissing three cases with prejudice.
Reprinted courtesy of
Shane Singh, Lewis Brisbois and
Grace Mehta, Lewis Brisbois
Mr. Singh may be contacted at Shane.Singh@lewisbrisbois.com
Ms. Mehta may be contacted at Grace.Mehta@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of