Best Practices: Commercial Lockouts in Arizona
April 15, 2024 —
Patrick Tighe - Snell & Wilmer Real Estate Litigation BlogIf a tenant defaults under a commercial lease, Arizona law permits the landlord to re-take possession of the premises by locking out the defaulting tenant. However, if the landlord’s lockout is wrongful, the landlord may be liable for the damages the tenant sustains because of the wrongful lockout. To minimize such liability, here are some general best practices to follow when locking out a defaulting tenant:
- Do Not Breach the Peace. It is vital when performing a lockout to not breach the peace. What constitutes a “breach of the peace” depends on the particular circumstances at hand. For example, if a tenant arrives during the lockout and becomes angry or threatens violence, the landlord should stop performing the lockout and return at a later time. As a general rule of thumb, it is best to perform lockouts in the early morning hours or in the late evening hours when the landlord is less likely to encounter the tenant.
- Provide A Notice of Default. Many commercial leases require the landlord to provide a notice of default before the landlord can lock out a defaulting tenant. Check, double check, and triple check that the landlord followed the lease’s notice of default provisions correctly, including that the landlord sent the notices to all required parties in accordance with the time requirements set forth in the lease.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick Tighe, Snell & WilmerMr. Tighe may be contacted at
ptighe@swlaw.com
Constructive Notice Established as Obstacle to Relation Back Doctrine
March 01, 2021 —
Nicholas B. Brummel & Lawrence S. Zucker II - Haight Brown & Bonesteel LLPIn Organizacion Comunidad de Alviso v. City of San Jose, the Sixth Appellate District held that the relation back doctrine was inapplicable where a plaintiff received constructive notice of a defendant’s identity months prior to the last date where filing was permitted pursuant to an applicable statute of limitations.
In Organizacion Comunidad de Alviso, Mark Espinoza, an Organizacion Comunidad de Alviso (OCA/Plaintiff) representative, asked the City of San Jose (“the city”) to place him on the public notice list for a proposed rezoning project. He also twice specifically requested a copy of the notice of determination (NOD) documenting the city’s certification of an environmental impact report (EIR) and approval of the project. Despite Espinoza diligently requesting all notices for the project, the city, in violation of the California Environmental Quality Act (CEQA), failed to send Espinoza the legally operative second NOD for the project; the first NOD was provided to OCA, but named an incorrect party in interest.
Reprinted courtesy of
Nicholas B. Brummel, Haight Brown & Bonesteel LLP and
Lawrence S. Zucker II, Haight Brown & Bonesteel LLP
Mr. Brummel may be contacted at nbrummel@hbblaw.com
Mr. Zucker may be contacted at lzucker@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Vertical vs. Horizontal Exhaustion – California Supreme Court Issues Ruling Favorable to Policyholders
May 11, 2020 —
Alan Packer & James Hultz - Newmeyer DillionFor years, when faced with damage or injury spanning several policy periods, excess general liability insurers have argued that all potentially applicable underlying policies must be exhausted before the excess drops down to provide coverage (“horizontal exhaustion”). Insureds, on the other hand, insist that they are entitled to immediately access an excess policy for any given policy year, if that year’s underlying policy has exhausted (“vertical exhaustion”). Vertical exhaustion not only enables insureds to directly tap into the excess insurance for which they paid substantial premiums, but also enables the insured to moderate risk given that different lower level policies might (1) be needed for other claims, (2) have larger self-insured retentions, or (3) have other less favorable coverage provisions. Allowing an insured to proceed via vertical exhaustion would also eliminate the heavy administrative and logistical burden that could result from having to pursue and exhaust all underlying coverage on multi-year claims.
In Montrose Chemical Corp. v. Superior Court, 2020 WL 1671560 (April 6, 2020), the California Supreme Court has come down in favor of policyholders and vertical exhaustion. The Montrose case involved contamination that allegedly occurred between 1947 and 1982 and different liability insurance towers (comprised of primary and excess layers) for each year. The insured, Montrose, maintained a tower of insurance coverage, year by year, and faced claims asserting damage that spanned several decades. Montrose sought coverage from excess insurers under a vertical exhaustion approach. Not surprisingly, Montrose’s excess insurers insisted that horizontal exclusion was required and that Montrose was required to exhausted all other policies with lower attachment points in every single involved policy period. The California Supreme Court ruled in Montrose’s favor, holding that the insured may insist upon full coverage from an excess insurer once the layer directly below it has exhausted. The Court reasoned that the burden of spreading the loss among insurers is one that is appropriately borne by insurers, not insureds.
Reprinted courtesy of
Alan H. Packer, Newmeyer Dillion and
James S. Hultz, Newmeyer Dillion
Mr. Packer may be contacted at alan.packer@ndlf.com
Mr. Hultz may be contacted at james.hultz@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
Flood Policy Does Not Cover Debris Removal from Property
May 07, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe Third Circuit affirmed the granting summary judgment to the insurer over a dispute as to debris removal under a Standard Flood Insurance Policy (SFIP). Torre v. Liberty Mut. Fire Ins. Co., 2015 U.S. App. LEXIS 4902 (3rd Cir. March 26, 2015).
The Torres' property sustained substantial damage from Hurricane Sandy. Claims for flood damage were submitted to Liberty. Liberty paid a total of $235,751.68, which included the cost of removing debris from the house. An additional $15,520 for the cost of removing sand and other debris deposited on their land in front of and behind the Torres' home was denied on the grounds that the SFIP did not cover such removal.
The Torres filed suit and cross-motions for summary judgment were filed. The district court denied the Torres' motion and granted Liberty's motion.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
California Case That Reads Like Russian Novel Results in Less Than Satisfying Result for Both Project Owner and Contractors
May 01, 2019 —
Garret Murai - California Construction Law BlogSometimes you can see a train wreck coming a mile away. The next case, Design Built Systems v. Sorokine, Court of Appeal for the First District, Case Nos. A151264 and A152059 (February 26, 2019), is one of those cases. It also happens to read like a Tolstoy novel.
The Beginning of the Train Wreck
Alexei Sorokine and Elena Koudriavtseva, husband and wife, owned a single family home in San Rafael, California. Sorokine had acquired the house prior to his marriage to Koudriavtseva. In 2010, he traveled to Russia and, for reasons unexplained, has not been able to return.
Following a landslide on the property in 2006, Sorokine entered into a construction contract with Design Built Systems to design and build a series of retaining walls. DBS was also retained to remedy a stop work notice issued by the City of San Rafael following work performed by others.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel RosenMr. Murai may be contacted at
gmurai@wendel.com
Floating Cities May Be One Answer to Rising Sea Levels
August 07, 2022 —
Adam Minter - BloombergThanks to climate change, sea levels are lapping up against coastal cities and communities. In an ideal world, efforts would have already been made to slow or stop the impact. The reality is that climate mitigation remains difficult, and the 40% of humanity living within 60 miles of a coast will eventually need to adapt.
One option is to move inland. A less obvious option is to move offshore, onto a floating city.
It sounds like a fantasy, but it could real, later if not sooner. Last year, Busan, South Korea's second-largest city, signed on to host a prototype for the world's first floating city. In April, Oceanix Inc., the company leading the project, unveiled a blueprint.
Representatives of SAMOO Architects & Engineers Co., one of the floating city's designers and a subsidiary of the gigantic Samsung Electronics Co., estimate that construction could start in a "year or two," though they concede the schedule might be aggressive. “It's inevitable,” Itai Madamombe, co-founder of Oceanix, told me over tea in Busan. “We will get to a point one day where a lot of people are living on water.”
Read the court decisionRead the full story...Reprinted courtesy of
Adam Minter, Bloomberg
Owner’s Slander of Title Claim Against Contractor Recording Four Separate Mechanics Liens Fails Under the Anti-SLAPP Statute
February 01, 2021 —
Garret Murai - California Construction Law BlogMost mechanics lien actions follow a pretty standard process:
- A mechanics lien claimant, either a contractor subcontractor, material supplier, or laborer, performs work but is not paid;
- Mechanics lien claimant records a mechanics lien on the property in which work was performed; and
- Within 90 days thereafter files suit to foreclose on the mechanics lien.
Sometimes, either before or after a mechanics lien claimant files suit, the owner will record a mechanics lien release bond, in which case mechanics lien claimant files suit against the release bond.
But what if a mechanics lien claimant records a mechanics lien, the owner records a mechanics lien release bond, and the mechanics lien claimant records three different but identical mechanics liens thereafter? Is this even legal?
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
General Contractors: Consider Importance of "Primary Noncontributory" Language
February 16, 2017 —
David Adelstein – Florida Construction Legal UpdatesIn prior articles, I reinforced the importance of general contractors including “primary and noncontributory” language in subcontracts and requiring the subcontractor to provide an analogous “primary and noncontributory” endorsement. As a general contractor this is important, particularly since you are going to require the subcontractor to (i) indemnify you for claims relating to personal injury, property damage, or death, and (ii) identify you as an additional insured under its commercial general liability (CGL) policy for claims arising out of the subcontractor’s scope of work. The “primary and noncontributory” language in your subcontracts allows you to maximize the value of your additional insured status.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at