Nonparty Discovery in California Arbitration: How to Get What You Want
January 08, 2019 —
Leilani L. Jones - Payne & FearsOpting for arbitration requires attorneys to balance efficiency and procedural protections. The implications of arbitration are something clients certainly have to carefully consider both when drafting arbitration provisions, and after initiating a demand. While arbitration can in many respects streamline the civil discovery process, one of the largest roadblocks for cases in California arbitrations is “streamlining” discovery from nonparties. This article explores the challenges presented by third party discovery in arbitration, and proposes strategies for obtaining such discovery efficiently and expeditiously.
Read the court decisionRead the full story...Reprinted courtesy of
Leilani L. Jones, Payne & FearsMs. Jones may be contacted at
llj@paynefears.com
Hard to Believe It, Construction Law Musings is 16
January 07, 2025 —
Christopher G. Hill - Construction Law MusingsOn this date back in 2008 (wow, that seems so long ago), I began Construction Law Musings on the Blogger platform with a brief announcement. Little did I know that this corner of the internet (or is it Blawgosphere?) would still be around in 2024!
In the time since I made that short entry 16 years ago (I know, I can’t believe it either), I’ve met several construction lawyers here in Virginia who refer to me as the “blog guy.” To be recognized for the work I do here at Construction Law Musings, something that benefits me (and I hope the readers), and which I do for the fun of it, is an honor.
The blog has since taken on a life of its own in many respects, allowing me to meet some of the great construction pros who have provided a guest post or two for Musings and added their different perspectives. Musings also kept me up on at least most of the trends in Virginia construction law by making me post consistently (though sometimes less consistently than others). Now, around 975 posts and 16 years later, I find it hard to believe that so much time has passed and effort has been put into what started on a whim and the plan that I’d post thoughts on the legal landscape and construction from the perspective of a Virginia construction lawyer.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
NLRB Broadens the Joint Employer Standard
September 17, 2015 —
Craig Martin – Construction Contractor AdvisorPerhaps in anticipation of Labor Day, the National Labor Relations Board issued its ruling in Browning-Ferris Indus. of Cal. d/b/a BFI Newby Island Recyclery, establishing an easier standard for unions to prove that a joint employer relationship exists. This will make it easier for unions to make the upstream company, like a parent company, liable for unfair labor practices, even if the upstream company had no direct involvement.
Some Background
BFI runs a recycling plant and contracts with Leadpoint to provide workers to sort garbage in the recycling plant. The staffing agreement specifically stated that Leadpoint was the sole employer of the personnel it supplied and Leadpoint handled supervision of the employees, not BFI.
Leadpoint’s employees sought to unionize and an election was held. The union filed a petition seeking a determination that Leadpoint and BFI were a joint employers.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Will a Notice of Non-Responsibility Prevent Enforcement of a California Mechanics Lien?
March 05, 2015 —
William L. Porter – Porter Law Group, Inc.The “Notice of Non-Responsibility” is one of the most misunderstood and ineffectively used of all the legal tools available to property owners in California construction law. As a result, in most cases the answer to the above question is “No”, the posting and recording of a Notice of Completion will not prevent enforcement of a California Mechanics Lien.
The mechanics lien is a tool used by a claimant who has not been paid for performing work or supplying materials to a construction project. It provides the claimant the right to encumber the property where the work was performed and thereafter sell the property in order to obtain payment for the work or materials, even though the claimant had no contract directly with the property owner. When properly used, a Notice of Non-Responsibility will render a mechanics lien unenforceable against the property where the construction work was performed. By derailing the mechanics lien the owner protects his property from a mechanics lien foreclosure sale. Unfortunately, owners often misunderstand when they can and cannot effectively use a Notice of Non-Responsibility. As a result, the Notice of Non-Responsibility is usually ineffective in protecting the owner and his property.
The rules for the use of the Notice of Non-Responsibility are found in California Civil Code section 8444. Deceptively simple, the rules essentially state that an owner “that did not contract for the work of improvement”, within 10 days after the owner first “has knowledge of the work of improvement”, may fill out the necessary legal form for a Notice of Non-Responsibility and post that form at the worksite and record it with the local County Recorder in order to prevent enforcement of a later mechanics lien on the property.
What commonly occurs however is that early in the process the owner authorizes or even requires its tenant to perform beneficial tenant improvements on the property. This authorization is often set forth in a tenant lease or other written document. The dispositive factor for determining whether the Notice of Non-Responsibility will be enforceable though is that the owner knows that these improvements will be made to the property and intends that they be made, usually long before the work begins. Indeed, the owner has usually negotiated these very terms into the lease contract. The owner then mistakenly believes that once work on the property commences it has 10 days to post and record a Notice of Non-Responsibility and thereby protect itself from a mechanics lien.
The usual error is two-fold. First, the statute states that the Notice is available when the owner “did not contract for the work of improvement”. The fact though is that the owner did contract for the work of improvement. It did so through the lease contract. This is true even though the owner’s contract was not with the contractor or supplier directly. Secondly, the 10 day period to post and record the Notice begins when the owner first “has knowledge” of the work of improvement. This knowledge was of course gained when the lease was negotiated and signed, providing knowledge typically many days before the work has begun. Thus, the 10 day period can also seldom be met. The Notice of Non-Responsibility will therefore fail both rules because the owner has in fact contracted for the improvement and because he does not act within 10 days of gaining this knowledge.
The next event in the typical scenario occurs when the tenant does not pay its contractor. The contractor then has nothing to pay its subcontractors. Material suppliers also go unpaid. Mechanics liens are then recorded by the unpaid claimants, followed by foreclosure actions within ninety days thereafter. Owners will typically point to the Notice of Non-Responsibility they posted and recorded, claiming its protection. Claimants then in turn point to the lease or other evidence that the owner knew of the pending improvements and contracted in some way that the improvements be performed, often also more than 10 days before they posted the Notice. Judges generally agree with the unpaid mechanics lien claimants and the Notice of Non-Responsibility is deemed ineffective.
The fact that the Court does not enforce the Notice of Non-Responsibility under these circumstances is not an unfair result. Since the owner authorized the work to be performed and it received a substantial benefit in the form of those improvements, it is not unfair that the owner should pay for those benefits. It would be inequitable for the owner to obtain the benefit of the improvements which it authorized but for which it did not pay, while allowing those who provided the benefit to go unpaid. Moreover, without such a system in place the door would be open to owners setting up sham “tenants” who would enter into contracts to have work performed, only to disappear when the work is completed, leaving the contractor without a source of payment. The system in place as described above prevents such duplicity. Owners would do well to arm themselves with proper knowledge of when the Notice of Non-Responsibility will and will not protect them and then responsibly use the Notice of Non-Responsibility.
For the legal eagles among you, the following cases illustrate the view of the courts, consistent with the above: Baker v. Hubbard (1980) 101 Cal.App.3d 226; Ott Hardware v. Yost (1945) 69 Cal. App.2d 593 (lease terms); Los Banos Gravel Co. v. Freeman (1976) 58 Cal.App.3d 785 (common interest); Howard S. Wright Construction Co. v. Superior Court (2003); 106 Cal.App.4th 314 (participating owner).
William L. Porter of
Porter Law Group, Inc. located in Sacramento, California may be contacted at (916) 381-7868 or bporter@porterlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
COVID-19 Response: Key Legal Considerations for Event Cancellations
March 30, 2020 —
Michael G. Platner, Solomon B. Zoberman, & Jane C. Luxton - Lewis BrisboisEvery passing day brings stark new reports of novel coronavirus (COVID-19) cases and increasing numbers of cancelled conventions, concerts, and other major events. Both the hospitality and travel industry on the one hand, and organizations that are canceling events on the other, are scrambling to understand the legal consequences of these costly terminations. Cancellation fees can be breathtaking, and affected parties are quickly learning that there are no simple answers as to whether a disease outbreak of this scope and scale falls within force majeure (or Act of God) clauses that either do not explicitly list, or arguably may never have contemplated, circumstances of this type.
Generally, force majeure clauses excuse parties’ performance under a contract when circumstances that are beyond their control arise and prevent them from fulfilling their obligations. The party electing to enforce its rights under the force majeure clause must show that the triggering event qualifies as a force majeure event, and that the event has rendered the party’s performance impossible or impracticable.
Reprinted courtesy of Lewis Brisbois attorneys
Michael G. Platner,
Solomon B. Zoberman and
Jane C. Luxton
Mr. Platner may be contacted at Michael.Platner@lewisbrisbois.com
Mr. Zoberman may be contacted at Solomon.Zoberman@lewisbrisbois.com
Ms. Luxton may be contacted at Jane.Luxton@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Real Estate & Construction News Round-Up 04/06/22
April 11, 2022 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogA growing proptech startup aims to pre-emptively identify needed home repairs, 3D-printed homes could become a workable solution to the housing shortage, and more.
- Concerns about a housing-market crash are growing as the Fed begins to hike interest rates, leaving industry experts to speculate on what’s next for the U.S. housing bubble. (William Edwards, Insider)
- Real-estate sales in Manhattan topped $7 billion in the first quarter of 2022, with the average price of apartments jumping 19% over the previous year. (Robert Frank, CNBC)
- Proptech startup DwellWell claims to have produced the first “check engine light” that can pre-emptively diagnose needed home repairs. (T.P. Yeatts, The Real Deal)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Heathrow Tempts Runway Opponents With $1,200 Christmas Sweetener
December 15, 2016 —
Christopher Jasper – BloombergHeathrow Airport Ltd. will offer hundreds of homeowners a 1,000-pound ($1,200) festive sweetener to participate in environmental studies vital to expediting planning for its controversial 16 billion-pound third runway.
The owners of houses and farmland on which the new landing strip is due to be built will qualify for the payment in return for agreeing to a handful of visits over about two years, Heathrow Chief Executive Officer John Holland-Kaye said in an interview. The surveys are required to establish the site’s wildlife value.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher Jasper, Bloomberg
Contractors: Beware the Subordination Clause
October 15, 2014 —
Garret Murai – California Construction Law BlogA bit of mechanics lien trivia.
What is the only state in the United States in which mechanics liens are a constitutional right?
If you answered California, ding, ding.
Article XIV of the California Constitution states:
Mechanics, persons furnishing materials, artisans, and laborers of every class, shall have a lien upon the property upon which they have bestowed labor or furnished material for the value of such labor done and materials furnished; and the Legislature shall provide, by law, for the speedy and efficient enforcement of such liens.
But how does that constitutional right stand up against contractual rights? Not so well it seems.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Kronick Moskovitz Tiedemann & GirardMr. Murai may be contacted at
gmurai@kmtg.com