Wisconsin Supreme Court Holds that Subrogation Waiver Does Not Violate Statute Prohibiting Limitation on Tort Liability in Construction Contracts
October 21, 2019 —
Gus Sara - The Subrogation StrategistIn Rural Mut. Ins. Co. v. Lester Bldgs., LLC 2019 WI 70, 2019 Wisc. LEXIS 272, the Supreme Court of Wisconsin considered whether a subrogation waiver clause in a construction contract between the defendant and the plaintiff’s insured violated Wisconsin statute § 895.447, which prohibits limitations of tort liability in construction contracts. The Supreme Court affirmed the lower court’s decision that the waiver clause did not violate the statute because it merely shifted the responsibility for the payment of damages to the defendant’s insurance company. The waiver clause did not limit or eliminate the defendant’s tort liability. This case establishes that while
§ 895.447 prohibits construction contracts from limiting tort liability, a subrogation waiver clause that merely shifts responsibility for the payment of damages from a tortfeasor to an insurer does not violate the statute and, thus, is enforceable.
In Rural Mutual, the plaintiff’s insured, Jim Herman, Inc. (Herman), entered into a contract with Lester Buildings, LLC (Lester) to design and construct a barn on Herman’s property. The contract included a provision that stated the following:
Both parties waive all rights against each other and any of their respective contractors, subcontractors and suppliers of any tier and any design professional engaged with respect to the Project, for recovery of any damages caused by casualty of other perils to the extent covered by property insurance applicable to the Work or the Project, except such rights as they have to the proceeds of such property insurance and to the extent necessary to recover amounts relating to deductibles of self-insured retentions applicable to insured losses. . . . This waiver of subrogation shall be effective notwithstanding allegations of fault, negligence, or indemnity obligation of any party seeking the benefit or production [sic] of such waiver.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
An Expert’s Qualifications are Important
January 28, 2019 —
David Adelstein - Florida Construction Legal UpdatesAn expert’s qualifications are important. Please remember this the next time you retain an expert to analyze documents or data and render an opinion based on that information. An expert must be qualified to render an opinion. Otherwise the expert will not be allowed to render the opinion you may be looking for or need for purposes of trial, as discussed below.
A recent personal injury case, White v. Ring Power Corp., 43 Fla.L.Weekly D2729a (Fla. 3d 2018), involved a crane operator that became severely injured when operating a leased crane. The case proceeded to trial against only the equipment lessor of the crane based on the plaintiff’s contention that there were deficiencies with the crane. The plaintiff intended on using expert witnesses to interpret the crane’s load movement indicator (referred to as LMI) and render opinions that the LMI data showed prior overloads of the crane which resulted in the injury to the operator of the crane.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
No Coverage for Additional Insured for Construction Defect Claim
July 02, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe Seventh Circuit affirmed the district court's grant of summary judgment to the insurers, finding there was no coverage for the additional insured on a construction defect claim. St. Paul Guardian Ins. Co. v. Walsh Construction. Co., 2024 U.S. App. LEXIS 10285 (7th Cir. April 29, 2024).
The City of Chicago hired Walsh Construction Company as general contractor for the Facade and Circulation Enhancement (FACE) project at O'Hare International Airport. The FACE project involved building and installing a new canopy for Terminals 1, 2 and 3. The project also called for the construction of a steel and glass curtain wall that would be integrated with the curtain wall at Terminals 2 and 3. Walsh contracted with Carlo Steel Corporation to manufacture the steel and curtain wall. Carlo, in turn, subcontracted with LB Steel, LLC to manufacture and install the steel elements of the wall, which included steel columns, hammer heads and box girders. The subcontract between Carlo and LB Steel included an indemnity provision that required LB Steel to indemnify Carlo and Walsh for any property damage resulting from LB Steel's negligent performance.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Efficient Proximate Cause Applies to Policy's Collapse Provisions
February 23, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe court applied the efficient proximate cause doctrine to find coverage under a property policy for a building's collapse. Vardanyan v. Amco Ins. Co., 2015 Cal. App. LEXIS 1181 (Cal. Ct. App. Dec. 11, 2015).
The insured submitted a claim to Amco for damage to the flooring of the house and for mold. Amco's adjustor reported that the house seemed to be settling, possibly due to a water leak. A structural engineer then inspected and found multiple potential leaks in the roof, gutters in disrepair, downspouts that deposited water at the base of the walls of the house, and evidence that a faucet had been spraying the wall in one area. Water damage was noticed in these areas. Further, the kitchen was water damaged and had past termite infestation.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Connecticut Supreme Court Rules Matching of Materials Decided by Appraisers
March 28, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe Connecticut Supreme Court determined that an appraisal panel could resolve whether the insurer must replace undamaged materials so that they match the damaged materials. Klass v. Liberty Mut. Ins. Co., 2022 Conn. LEXIS 2 (Conn. Jan. 11, 2022).
The insured reported damage to the roof of his home to Liberty Mutual. A representative from Liberty Mutual inspected and noticed a few shingles missing from the rear slope of the roof. The representative agreed that the damage was caused by wind damage, a covered loss under the policy. Liberty Mutual accepted coverage and issued an estimate to replace the rear slope of the roof. The insured's contractor inspected the roof and provided an estimate that contemplated replacement of the entire roof at nearly double the cost of Liberty Mutual's estimate.
The insured requested an appraisal. Liberty Mutual responded that the insured could not invoke the appraisal process in the absence of a "competing" estimate (i.e., one that addressed the claim for which coverage was accepted). Any dispute regarding the matching of the front and rear roof slope was a question of coverage, not an issue for appraisal.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
2015 California Construction Law Update
December 31, 2014 —
Garret Murai – California Construction Law BlogOver 2,200 bills were introduced during the second and final year of the 2013-2014 legislative session of which 931 were signed into law. For the design and construction industry, the end of the second session, like the end of the first session, saw a number of new prevailing wage bills signed into law, which again reflected the strong Democratic majorities in both the Assembly and Senate. The end of the second session also saw the enactment of laws consolidating several existing design-build authorization sections and extending the 5% cap on retention for public works projects.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Delaware District Court Finds CGL Insurer Owes Condo Builder a Duty to Defend Faulty Workmanship Claims — Based on the Subcontractor Exception to the Your Work Exclusion
October 04, 2021 —
Anthony L. Miscioscia & Laura Rossi - White and WilliamsOn September 7, 2021, in one of the few decisions addressing the scope of coverage for faulty workmanship under Delaware law, the Delaware District Court denied an insurer’s motion seeking a declaration that it neither needed to defend nor indemnify an insured-builder under a commercial general liability policy.
In this declaratory judgment action, Pennsylvania National Mutual Casualty Insurance Company v. Zonko Builders, the insurer argued that the ongoing underlying action failed to properly plead an “occurrence” in a case alleging damages to a condominium caused by faulty workmanship involving subcontractors.* Zonko Builders (Zonko) served as the general contractor, supervising subcontractors. The Condominium Association sued Zonko for damages allegedly resulting from design and construction deficiencies. The motion was opposed by the Condominium Association, which cross-moved for partial judgment on the pleadings.
In AE-Newark Associates, L.P. v. CNA Insurance Companies, 2001 Del. Super. LEXIS 370 (Del. Super. Ct. Oct. 2, 2001), the Delaware Superior Court found that an insured was entitled to coverage for damages arising from a faulty roof system installed by a subcontractor on behalf of the insured general contractor.
Reprinted courtesy of
Anthony L. Miscioscia, White and Williams and
Laura Rossi, White and Williams
Mr. Miscioscia may be contacted at misciosciaa@whiteandwilliams.com
Ms. Rossi may be contacted at rossil@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Detroit Showed What ‘Build Back Better’ Can Look Like
May 10, 2021 —
Rip Rapson - BloombergAmerican cities stand at a precipice. Burdened by an overwhelming public health crisis, drained of resources by economic stagnation and torn apart by racial injustice and unrest, cities are confronting the reality that conventional formulas of municipal finance and practices of working cannot sustain our urban places.
The significance of this moment was not lost on the Biden-Harris administration, which quickly advanced an ambitious mandate commensurate with the challenge: a domestic Marshall Plan called Build Back Better. Already, the first prong — the $1.9 trillion American Rescue Plan — has helped shore up city budgets, restore desperately needed funding for public transportation and keep businesses open and families in homes. The second leg, the $2 trillion American Jobs Plan, represents a bold shift from short-term recovery to long-term transformation.
Read the court decisionRead the full story...Reprinted courtesy of
Rip Rapson, Bloomberg