Construction Wall Falls, Hurts Three
November 06, 2013 —
CDJ STAFFA construction wall collapsed on November 1 during heavy rainfall in New York City. Two women were briefly trapped under the rubble, while other bystanders worked to free them. Einstein Construction Group, a contractor based in Texas, was remodeling the first floor for a new tenant, a Japanese restaurant. The company, which disclaims responsibility for the occurrence, were cited for violations and a stop work order was issued.
Just prior to the incident, high winds whipped through the area. The construction wall allegedly had not been securely attached to the building.
Read the court decisionRead the full story...Reprinted courtesy of
Killer Subcontract Provisions
January 20, 2020 —
Patrick McNamara - Porter Law GroupWe are frequently requested by subcontractor clients to review the subcontract that has been prepared by the prime contractor, before our client signs it. While no two agreements are identical, there are a number of problematic contract provisions that appear in many agreements. Here is a list of ten such provisions (and their variations) that are potential “deal breakers”:
- PAY IF/WHEN PAID (e.g. “Contractor shall have the right to exhaust all legal remedies, including appeals, prior to having an obligation to pay Subcontractor.”) “Pay-if-paid” provisions (“Receipt of payment from Owner shall be a condition precedent to Contractor’s duty to pay Subcontractor”) are illegal in California. However, the only legal limit on “Pay-When-Paid” provisions is that payment must be made “within a reasonable time.” The example above, as written, essentially affords the prime contractor a period of several years following completion of the project before that contractor has an independent duty to pay its subcontractors – not a “reasonable” amount of time, to those waiting to be paid. A compromise is to provide a time limit, such as 6 months or one year following substantial completion of the project.
- CROSS-PROJECT SET-OFF (e.g. “In the event of disputes or default by Subcontractor, Contractor shall have the right to withhold sums due Subcontractor on this Project and on any other project on which Subcontractor is performing work for Contractor.”) Such provisions are problematic and likely unenforceable, as they potentially bar subcontractors’ lien rights. Such provisions should be deleted.
- CONTRACTOR/SUBCONTRACTOR RESPONSIBILITY FOR DESIGN QUALITY (e.g. “Subcontractor warrants that the Work shall comply with all applicable laws, codes, statutes, standards, and ordinances.”) Unless a subcontractor’s scope of work expressly includes design work, this provision should either be deleted or modified, with the addition of the following phrase: “Subcontractor shall not be responsible for conformance of the design of its work to applicable laws, codes, statutes, standards, and ordinances.”
Read the court decisionRead the full story...Reprinted courtesy of
Patrick McNamara, Porter Law GroupMr. McNamara may be contacted at
pmcnamara@porterlaw.com
Fannie-Freddie Elimination Model in Apartments: Mortgages
April 08, 2014 —
Sarah Mulholland – BloombergThe apartment-lending units of Fannie Mae (FNMA) and Freddie Mac were among their few money makers after the U.S. housing collapse. Now they should help transform the U.S. mortgage industry.
Lawmakers seeking to eliminate the two government lenders, which were seized by regulators during the 2008 credit crisis, see an antidote to the reckless lending that blew up the U.S. housing market in the structure of the firms’ multifamily operations, which share risks with lenders.
Senate Banking Committee Chairman Tim Johnson and Republican Mike Crapo are proposing legislation to create a new government-backed reinsurer of mortgage bonds that would require private investors to bear losses on the first 10 percent of capital. The model for the provision mirrors Fannie Mae and Freddie Mac (FMCC)’s multifamily lending operations, requiring lenders to shoulder some of the risk on loans they originate.
Read the court decisionRead the full story...Reprinted courtesy of
Sarah Mulholland, BloombergMs. Mulholland may be contacted at
smulholland3@bloomberg.net
Antidiscrimination Clause Required in Public Works and Goods and Services Contracts –Effective January 1, 2024
January 22, 2024 —
Travis Colburn - Ahlers Cressman & SleightIn July 2023, the Washington legislature passed Senate Bill 5186, which mandates inclusion of select antidiscrimination clauses in every state contract and subcontract for public works, goods, or services executed after January 1, 2024.
[i] RCW 49.60.530(3) codifies the now-required antidiscrimination clauses, which prohibit four categories of discrimination against any person because of age, sex, marital status, sexual orientation, gender identity, race, creed, color, national origin, citizenship or immigration status, honorably discharged veteran or military status, the presence of any sensory, mental, or physical disability, or the use of a trained dog guide or service animal by a person with a disability (the “Protected Class”).
Under the new law, public contractors and subcontractors (“Public Contractor”) may not refuse to hire a person because that person is a member of the Protected Class, unless that refusal is based upon a bona fide occupational qualification or if a person with a particular disability would be prevented from properly performing the particular work involved.
[ii] Similarly, Public Contractors may not discharge or bar a person from employment or discriminate against any person – either in terms of compensation or other terms and conditions of employment – because that person is a member of the Protected Class.
[iii] Last, Public Contractors may not print or circulate (or cause to be printed or circulated) any statement, advertisement, publication, form of application for employment, or make inquiry in connection with prospective employment, which expresses any limitation, specification, or discrimination as to the Protected Class.
[iv] Read the court decisionRead the full story...Reprinted courtesy of
Travis Colburn, Ahlers Cressman & SleightMr. Colburn may be contacted at
travis.colburn@acslawyers.com
No Coverage for Homeowner Named as Borrower in Policy but Not as Insured
July 08, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe magistrate judge recommended that the homeowner's complaint seeking coverage for damage caused by Hurricanes Laura and Delta be denied because the homeowner was only named as the borrower under the policy. LeDay v. Integon Nat'l Ins. Co., 2024 U,S. Dist. LEXIS 87369 (W.D. La. April 15, 2024).
When the homeowner sought coverage for hurricane damage, it was denied. The homeowner then sued and Integon moved to dismiss. Integon argued it did not issue a policy to the homeowner, but the policy was issued to Midland Mortgage. The pro se homeowner did not respond to the motion.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
No Concrete Answers on Whether Construction Defects Are Occurrences
February 14, 2013 —
CDJ STAFFAaron Mandel and Stevi Raab of Sedgwick Law write Construction Defect Coverage Quarterly addressing the question of “whether defective construction constitutes an ‘occurrence’ (and therefore may be covered) under liability insurance policies.” They note that some courts have held that construction defects are not an occurrence but instead are the “natural consequence of performing substandard work.” Other courts conclude that while construction defects are not occurrences, “the resulting damage may be covered because it was fortuitous and unintended.” And, finally, other courts have concluded that “defective construction work itself is accidental and the inured rarely expects construction defects.” Mandel and Raab put forth that “these decisions essentially provide insured with huge, unintended and unfair windfalls – performance bonds for basically no premium.”
Legislatures have also looked at this issue, passing laws that mandate that construction defects are occurrences. These are all fairly recent and the courts have yet to address these laws, and Mandel and Raab note that “it is unclear what their ultimate effect on the ‘occurrence’ issue will be.” They do not expect the laws to end litigation over whether construction defects are occurrences.
Finally, they discuss what the ultimate results of these court decisions and laws will be. Insurers might write more policy exclusions, or increase premiums, or even cease insuring construction.
Read the court decisionRead the full story...Reprinted courtesy of
No Coverage for Alleged Misrepresentation Claim
January 23, 2023 —
Tred R. Eyerly - Insurance Law HawaiiThe court found there was no coverage for a misrepresentation claim against the insured sellers of a residence. Am. Family Mut. Ins. Co. v. Coyne, 2022 U.S. Dist. LEXIS 186417 (E.D. Mo. Oct. 12, 2022).
Aaron and Tobi Beckman purchased a home from Denise Coyne. The Bockmans alleged in the underlying suit that Coyne represented that the property had a "2-car garage." A disclosure statement signed by Coyne stated she had disclosed all conditions which might lower the value of the property or adversely affect the Bockman's decision to buy the property. After purchasing the property, the Bockmans learned that they could not fit their two vehicles in the attached garage. The Bockmans alleged that substantial remediation was necessary to expand the depth of the garage to fit two cars within it.
The underlying suit alleged that Coyne had was engaged in fraud, misrepresentation and concealment by omitting material facts in connection with the sale of the home. Coyne allegedly engaged in negligent misrepresentation by failing to inform the Bockmans of the depth of the attached garage.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Update: Lawyers Can Be Bound to Confidentiality Provision in Settlement Agreement
January 13, 2020 —
Danielle Ward, Esq. - Balestreri Potocki & HolmesIn July 2019, the California Supreme Court ruled that an attorney’s signature under the often-used phrase “approved as to form and content” does not preclude a finding that the attorney could be bound to the terms of a settlement agreement. (Monster Energy Co. v. Schechter (2019) 7 Cal.5th 781.) This decision marks a reversal of the Fourth District Court of Appeal’s 2018 ruling that approval of a contract is not tantamount to an agreement to be bound by that contract.
The underlying action stemmed out of a wrongful death suit by Wendy Crossland and Richard Fournier, parents of the decedent, against Monster Energy Company. The parties negotiated a settlement, a critical of element of which was a confidentiality provision aimed at keeping the the settlement secret.
The confidentiality provision prohibited plaintiffs and their counsel of record from disclosing both the existence of the settlement, or the terms thereof, to any person, entity, or publication, including the legal website Lawyers & Settlements. The attorneys signed the agreement under the phrase “approved as to form and content.”
Shortly after the settlement agreement was executed, the Plaintiffs’ attorney Bruce Schechter disclosed his clients’ settlement with Monster in an interview with Lawyers & Settlements. Monster filed suit against Mr. Schechter for breach of contract, among other causes of action. Mr. Schechter challenged the lawsuit with a SLAPP motion, essentially arguing that the lawsuit was meritless and merely an attempt to thwart freedom of speech.
The trial court denied Mr. Schechter’s motion as to the breach of contract cause of action finding that the settlement clearly contemplated that the attorneys were subjected to the terms of the agreement, and Schechter’s claim that he was not a party because he merely approved as to form and content was “beyond reason.”
The Fourth District Court of Appeal reversed, concluding that Mr. Schechter was not a party to the agreement by virtue of his signature approving the form and content, and the Plaintiffs had no authority to bind their attorney to the terms of the agreement. The Court of Appeal found that by affixing his signature to the agreement Mr. Schechter was merely manifesting his “professional thumbs up” in line with legal industry’s customary understanding.
In its reversal, the California Supreme Court did not disturb the legal community’s understanding of the phrase “approved as to form and content.” Rather, the Court concluded that an attorney’s signature under that often-used phrase does not preclude as a matter of law that the attorney intended to be bound by the agreement. The entire agreement, including the substantive provisions, need to be examined to determine the attorney’s intent in affixing his/her signature to the agreement.
Turning to the Crossland/Fournier Monster settlement agreement, the Court was unpersuaded by Mr. Schechter’s argument that he was not bound to the agreement because counsel was not included in the definition of “party”. The Court stated that it’s the substance of the agreement that determines whether counsel is a party to the contract, as opposed to a party to the lawsuit.
The Court was persuaded, in part, by the important role that confidentiality plays in brokering settlements. It noted that public disclosure of private settlements would serve to “chill” parties’ ability to resolve matters short of trial, and there was little doubt that confidentiality was an important term of the Crossland/Fournier Monster settlement. In concluding that Monster had met its burden to defeat an anti-SLAPP motion, the Court pointed to the numerous references to counsel in the substantive provisions of the agreement which a trier of fact could conclude bound Mr. Schechter to the confidentiality terms.
Danielle Ward has concentrated her law practice on defending developer, general contractor, and subcontractor clients in a variety of construction matters. She has been an attorney with Balestreri Potocki & Holmes since 2010 and can be reached at dward@bph-law.com.
Read the court decisionRead the full story...Reprinted courtesy of