Committeewoman Requests Refund on Attorney Fees after Failed Legal Efforts
February 10, 2014 —
Beverley BevenFlorez-CDJ STAFFWest Deptford, New Jersey township redevelopment counsel Mark Cimino had spent a year arguing that the city should receive a $4 million reduction in construction costs due to “inadequate documentation provided by the bank, as well as receipts showing disbursement had ‘improperly’ been made toward uses other than construction,” according to a December 30th 2013 article in the South Jersey Times. However, a state appellate court upheld the ruling that “the township had no basis” to request the reduction.
Now, Committeewoman Denice DiCarlo is “seeking a $10,000 refund on the attorney fees paid” to Cimino, the South Jersey Times reported on February 6th. “This entire matter has been a monumental waste of tax dollars, and I am angry that the entire township committee was misled by Mr. Cimino and induced to believe we had any reasonable chance of recovering loan proceeds from this lawsuit,” DiCarlo stated in a letter to Mayor Raymond Chintall.
Not all committee members agree with DiCarlo. Committeeman Sam Cianfarini told South Jersey Times that “he still believed Fulton Bank owed it to West Deptford to answer for any funds put toward anything other than construction.”
Cimino declared “that both the lawsuit and appeal were valid,” according to the February 6th article. He “accused DiCarlo of ‘playing politics.’”
Read the full story, December 30th Article...
Read the full story, February 6th Article... Read the court decisionRead the full story...Reprinted courtesy of
2018 Super Lawyers and Rising Stars!
July 18, 2018 —
Wilke, Fleury, Hoffelt, Gould & Birney, LLPWilke Fleury is thrilled to announce our 2018 Super Lawyers and Rising Stars! Twelve of our talented attorneys have been honored with the Super Lawyers and Rising Stars distinctions.
Super Lawyers® is a service of the Thomson Reuters, Legal Division. Each year, the research team at Super Lawyers® undertakes a rigorous multi-phase selection process that includes a statewide survey of lawyers, independent evaluation of candidates by the attorney-led research staff, a peer review of candidates by practice area and a good-standing and disciplinary check. The Super Lawyers list represents only five percent of lawyers in California and Rising Stars reflects 2.5% of the state’s up-and-coming lawyers.
Congratulations to Wilke Fleury’s 2018 Super Lawyers and Rising Stars!
Read the court decisionRead the full story...Reprinted courtesy of
Wilke, Fleury, Hoffelt, Gould & Birney, LLP
25 Days After Explosion, Another Utility Shuts Off Gas in Boston Area
October 30, 2018 —
Johanna Knapschaefer - Engineering News-RecordThree hundred thirty-nine homes in Woburn, Mass., were without power on Oct. 8 after National Grid shut off gas meters following the inadvertent over-pressurization of the natural gas line on Oct. 8, according to the Woburn Fire Dept.
Read the court decisionRead the full story...Reprinted courtesy of
Johanna Knapschaefer, ENRENR may be contacted at
ENR.com@bnpmedia.com
Settlement Payment May Preclude Finding of Policy Exhaustion: Scottsdale v. National Union
December 11, 2013 —
Heather Anderson — Higgins, Hopkins, McLain & Roswell, LLC.In the last year, the U.S. District Court for the District of Colorado found that a settlement payment from an excess insurance carrier to another primary insurance carrier precluded a finding of vertical exhaustion sufficient to trigger the primary carrier’s duty to indemnify. See Scottsdale Ins. Co. v. National Union Fire Ins. Co. of Pittsburgh, 2012 WL 6004087 (D. Colo. 2012). The Scottsdale case arose out of the construction of a 507-unit apartment complex in Arapahoe County, Colorado in which a number of defects became apparent during construction. As a result, the owner of the project sued the general contractor and/or the construction manager, seeking to recover more than $22 million for various construction deficiencies. Id. at *1.
The general contractor was insured under policies issued by several carriers. Scottsdale Insurance Co. (“Scottsdale”) and National Union Fire Ins. Co. (“National Union) provided umbrella coverage, and CNA and American Zurich Ins. Co. (“Zurich”) provided primary insurance under commercial general liability policies. About five years later, the construction defect case settled for $8.5 million dollars.
Read the court decisionRead the full story...Reprinted courtesy of
Heather AndersonHeather Anderson can be contacted at
anderson@hhmrlaw.com
Just Because You Record a Mechanic’s Lien Doesn’t Mean You Get Notice of Foreclosure
September 15, 2016 —
Christopher G. Hill – Construction Law MusingsAs longtime (or new readers for that matter) know, mechanic’s liens are near and dear to my heart here at Construction Law Musings. These powerful tools to collect for your hard work on a construction project are great when prepared and recorded in the very specific fashion required by the Virginia legislature and courts. In most situations, if done properly, a mechanic’s lien gives you some security and priority for your construction claim that you would not have with a simple judgment lien.
Despite the power of a properly perfected and enforced mechanic’s lien (and the fact that the end result of a full mechanic’s lien suit that remains unsettled is in fact a foreclosure), a recent case in the Eastern District of Virginia, Weinberg v. J.P. Morgan Chase, et. al., (thanks for the head’s up on this case to the folks at the Construction Payment Blog) held that under Virginia statute mechanic’s lien holders are not entitled to notice of foreclosure. In the Weinberg case, the plaintiff, a pro se lien claimant that recorded two different liens, one pre-foreclosure and one post-foreclosure, and who had not received notice of the intervening foreclosure, argued, among other things, that he should have been given notice of the foreclosure on the deed of trust on the property by J. P. Morgan Chase.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Lump Sum Subcontract? Perhaps Not.
August 20, 2019 —
David Adelstein - Florida Construction Legal UpdatesLump sum subcontract? Perhaps not due to a recent ruling where the trial court said “No!” based on the language in the subcontract and contract documents generally incorporated into the subcontract.
This is a ruling on an interpretation of a subcontract and contract documents incorporated into the subcontract that I do not agree with and struggle to fully comprehend. The issue was whether the subcontract amount was a lump sum or subject to an audit, adjustment, and definitization based on actual costs incurred. Of course, the subcontractor (or any person in any business) is not just interested in recouping actual costs, but there needs to be a margin to cover profit and home office overhead that does not get factored into field general conditions.
In United States v. Travelers Casualty and Surety Company, 2018 WL 6571234 (M.D.Fla. 2018), a prime contractor was hired to perform work on a federal project. During the work, the Government issued the prime contractor a Modification that had a not-to-exceed value and required the prime contractor to track its costs for this Modification separate from other contract costs. In other words, based on this Modification, the prime contractor was paid its costs up to a maximum amount and the prime contractor would separately cost-code and track the costs for this work differently than other work it was performing under the prime contract.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
2023’s Bank Failures: What Contractors, Material Suppliers and Equipment Lessors Can Do to Protect Themselves
May 15, 2023 —
Garret Murai - California Construction Law BlogIt has been a tumultuous year for the banking industry. Since the beginning of this year the industry has seen the collapse of Silicon Valley Bank and Signature Bank, the shotgun marriage between failing Credit Suisse and USB, and, most recently, the collapse of First Republic Bank this past week and its purchase by JP Morgan Chase. Indeed, according to the New York Times, these three bank failures cum bailouts alone were bigger than the 25 banks that collapsed during the financial crises of 2008 and some are concerned that it is just the beginning.
This, of course, has impacted the stock market, with Forbes reporting that the banking industry lost more than $300 billion in market value as of the end of March. However, it also raises concerns regarding liquidity on construction projects.
While the failing banks have either been bought out by other banks or shored up by the federal government, which, in the case of Silicon Valley Bank and Signature Bank, involved the Federal Deposit Insurance Corporation (FDIC), the Treasury Department and the Federal Reserve stepping into to protect depositors by
guaranteeing deposits in excess of the current FDIC limit of $250,000, there continues to be concerns over access to cash. This can impact construction projects in several ways.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Insurer Must Pay Portions of Arbitration Award Related to Faulty Workmanship
October 21, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe court determined that portions of an arbitration award against the insured contractor based upon faulty workmanship were covered by the policy. Wallace v. Nautilus Ins. Co., 2019 U.S. Dist. LEXIS 122219 (D. N. H. July 23, 2010).
Plaintiffs, owners of adjoining homes, hired McPhail Roofing, LLC to replace the roofs of their houses. After installation, the plaintiffs found several problems with their roofs and withheld roughly a third of the agreed-upon contract price from final payments due to McPhail. A roofing consultant found evidence of water leaking through both roofs during rainstorms. Improper installation of the shakes on the roofs allowed rain to seep through to the roof decks (the plywood underneath the roofs) and eventually into the houses. The only way to cure the installation defects was to remove and replace the roofs entirely.
Plaintiffs and McPhail went to arbitration. Plaintiffs sought compensation for the damage caused by the leaking and for the replacement costs of the roofs. McPhail sought the remaining payment under the contracts. Nautilus defended McPhail under this CGL policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at