Think Twice Before Hedging A Position Or Defense On A Speculative Event Or Occurrence
July 13, 2020 —
David Adelstein - Florida Construction Legal UpdatesSometimes, hedging a position on a potential occurrence is not prudent. Stated differently, hedging a position on a contingent event is not the right course of action. The reason being is that a potential occurrence or contingent event is SPECULATIVE. The occurrence or event may not take place and, even if it does take place, the impact is unknown.
An example of hedging a defense on such a potential occurrence or contingent event can be found in a construction dispute involving a federal project out of the Eastern District of Virginia, U.S. f/u/b/o Champco, Inc. v. Arch Insurance Co., 2020 WL 1644565 (E.D.Va. 2020). In this case, the prime contractor hired a subcontractor to perform electrical work, under one subcontract, and install a security system, under a separate subcontract. The subcontractor claimed it was owed money under the two subcontracts and instituted a lawsuit against the prime contractor’s Miller Act payment bond. The prime contractor had issued the subcontractor an approximate $71,000 back-charge for delays. While the subcontractor did not accept the back-charge, it moved for summary judgment claiming that the liability for the back-charge can be resolved at trial as there is still over $300,000 in contract balance that should be paid to it. The prime contractor countered that the delays caused by the subcontractor could be greater than $71,000 based on a negative evaluation in the Contractor Performance Assessment Reporting System (“CPARS”). A negative CPARS rating by the federal government due to the delays caused by the subcontractor would result in a (potential) loss of business with the federal government (i.e., lost profit) to the prime contractor. The main problem for the prime contractor: a negative CPARs rating was entirely speculative as there had not been a negative CPARs rating and, even if there was, the impact a negative rating would have on the prime contractor’s future business with the federal government was unknown. To this point, the district court stated:
In this case, [prime contractor’s] claim for damages is wholly speculative. [Prime contractor] has not produced any evidence that its stated condition precedent—a negative CPARS rating—will actually occur and will have a negative impact on its future federal contracting endeavors. Specifically, [prime contractor] has not identified any facts that indicate that it will be subject to a negative CPARS rating or any indication of the Navy’s dissatisfaction with its work as the prime contractor on the Project… Further, a CPARS rating is only one aspect taken into consideration when federal contracts are awarded. In sum, there is no evidence of the following: (1) a negative CPARS rating issued to [prime contractor]; (2) [prime contractor’s] hypothetical negative rating will be the result of the delay [prime contractor] alleges was caused by [subcontractor]; or (3) [prime contractor’s] hypothetical negative CPARS rating will result in future lost profits.
U.S. f/u/b/o Champco, Inc., supra, at *2 (internal citation omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Definitions Matter in Illinois: Tenant Held Liable Only for Damage to Apartment Unit
September 09, 2024 —
Gus Sara - The Subrogation StrategistIn Phila. Indem. Ins. Co. v. Gonzalez, No. 1-23-0833, 2024 Ill. App. Unpub. LEXIS 1372, the Appellate Court of Illinois considered whether the terms of a lease agreement limited a tenant’s liability for fire damages, a fire caused by her negligence, to her apartment unit only. The plaintiff insured the subject apartment building, which incurred damage to several units as result of a fire in the tenant’s unit. The lease defined “Premises” as the specific apartment unit occupied by the tenant and held the tenant responsible for damage caused to the Premises. While the court found that the lease permitted the plaintiff to subrogate against the tenant, it held that the lease terms limited the damages to the tenant’s apartment unit only.
In Gonzalez, the plaintiff’s insured owned a multi-unit apartment building in Chicago. In September 2019, the building owner entered into a lease agreement with the defendant for apartment Unit 601. The lease stated that Unit 601 was the “Leased Address (Premises).” Another provision stated that building owner “hereby leases to Tenant(s) and Tenant(s) hereby leases from Landlord(s) for use as a private dwelling only, the Premises, together with the fixtures and appliances (if any) in the premises…” The lease also stated that “Tenant shall be liable for any damage done to the premises as a result of Tenant’s or Tenant’s invitees, guests or others authorized to reside in the Premises [sic] direct action, negligence, or failure to inform Landlord of repairs necessary to prevent damage to the Premises.”
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
Recent Developments with California’s Right to Repair Act
June 11, 2014 —
Beverley BevenFlorez-CDJ STAFFIn Lexology, Amy Kuo Alexander of Gordon Rees Scully Mansukhani, LLP analyzed recent decisions involving California’s Right to Repair Act, SB 800. According to Alexander, “SB 800, applies to all new residential construction sold after January 1, 2003” and “[i]t establishes a process to resolve certain construction defect claims prior to the filing of any lawsuit by a homeowner of new residential construction.”
Alexander’s three main discussion points include “SB 800 is Not the Exclusive Remedy,” “Notice Requirements to Builder Under SB 800,” and “Parties Can Opt Out of SB 800 to Adopt Their Own Prelitigation Procedure So Long as the Terms Are Not Unconscionable.”
Read the court decisionRead the full story...Reprinted courtesy of
A Property Tax Exemption, Misapplied, in Texas
June 18, 2019 —
Anthony B. Cavender - Gravel2GavelIn an important ruling for Texas businesses, the Texas Supreme Court has unanimously ruled that the TCEQ misapplied the Texas property tax’s exemption for specified pollution control equipment.
Since 1993, the Texas Constitution has included a provision which authorizes the Texas Legislature to exempt from ad valorem taxation “all or part of real and personal property used … wholly or partly … for the control or reduction of air, water or land pollution.” This provision is implemented by Section 11.31 of the Texas Tax Code, which is administered by the Texas Commission on Environmental Quality. (See the rules at Title 30, Chapter 17 of the Texas Administrative Code.) If the Executive Director of the TCEQ determines that the equipment is used wholly or partly for pollution control, he issues a “positive use determination”; in the event it does not, the Executive Director issues a “negative use determination and rejects the application for the exemption. In 2007, Section 11.31 was amended at 11.31 (k) to list several items of equipment that are presumed to be pollution-control equipment, including “heat recovery steam generators” or HRSGs. This equipment is used by powerplants to reduce nitrogen oxide emissions that are the product of generation of electricity. Several applications were submitted to the TCEQ by the Brazos Electric Power Cooperative, seeking a tax exemption for its HRSG units. In July 2012, the TCEQ denied these applications, with the flat declaration that HRSGs are not pollution-control equipment—“they are used solely for production.” The Brazos Cooperative sued the Commission, and on May 3, 2019, in the case of Brazos Electric Power Cooperative, Inc. v. TCEQ, the Texas Supreme Court issued a unanimous opinion reversing the Commission, and the lower court (the Eight Court of Appeals, sitting in El Paso) that affirmed the Commission’s action.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Insured's Jury Verdict Reversed After Improper Trial Tactics
October 09, 2018 —
Tred R. Eyerly - Insurance Law HawaiiThe appellate court reversed a jury verdict for the insured due to improper trial tactics by his attorney. Homeowners Choice Property and Cas. Ins. Co., Inc. v. Kuwas, 2018 Fla. Ct. App. LEXIS 9500 (Fla. Ct. App. July 5, 2018).
The insured sued Homeowners Choice (HCI) alleging breach of contract due to a denial of coverage for property damage as a result of water loss. During the trial, HCI raised objections to various questions posed by the insured's counsel during the testimony of HCI's litigation manager, as well as various closing arguments made by the insured. The jury entered a verdict for the insured for a substantial sum. HCI appealed.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
London Shard Developer Wins Approval for Tower Nearby
November 05, 2014 —
Neil Callanan - BloombergSellar Property Group, developer of the Shard in London, won local government approval to build a 26-story residential tower close to the skyscraper on the south bank of the River Thames.
The council for the Southwark borough voted in favor of the 148-apartment project, which also includes a 16-story tower, at a meeting yesterday, Sellar spokesman Baron Phillips said by e-mail. The project, like the Shard, will be developed in a partnership with the state of Qatar.
Developers plan to construct more than 25,000 luxury properties in London worth more than 60 billion pounds ($96 billion) over the next decade, EC Harris said in an Oct. 7 report. The homes approved yesterday at the Fielden House site are expected to sell for about 800,000 pounds each, according to a filing by the borough.
Read the court decisionRead the full story...Reprinted courtesy of
Neil Callanan, BloombergMr. Callanan may be contacted at
ncallanan@bloomberg.net
The Anatomy of a Construction Dispute- The Claim
December 02, 2015 —
Christopher G. Hill – Construction Law MusingsA new year brings with it promise and challenges. The promise is a relatively clean slate and the thought that 2015 will be a great year for construction professionals and those that assist them. The challenges come from the almost inevitable issues that can arise on a construction site with its many moving parts and enough potential pitfalls to make even the most optimistic construction attorney, contractor, subcontractor or supplier think that Murphy was an optimist.
In order to assist with the potential challenges, this post will be the first in a series of “musings” on the best way to handle a payment dispute arising from a construction contract. This week’s post will discuss what the first steps should be once a payment dispute or claim arises. We’ll assume that you, as a construction contractor, have taken early advantage of the services of a construction lawyer and have carefully reviewed your contract for issues before signing that contract.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
House Passes $25B Water Resources Development Bill
June 27, 2022 —
Tom Ichniowski - Engineering News-RecordA key federal infrastructure bill advanced with approval in the House of a measure providing $25.3 billion to help finance 22 Army Corps of Engineers storm and flood protection, ecological restoration, harbor dredging and other projects around the country.
Reprinted courtesy of
Tom Ichniowski, Engineering News-Record
Mr. Ichniowski may be contacted at ichniowskit@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of