The Value of Photographic Evidence in Construction Litigation
April 26, 2021 —
Marie Mueller - Construction ExecutiveIf a picture is worth a thousand words, can it be worth a thousand dollars? Ten thousand? Maybe, if it provides key evidence in a construction dispute. Litigating a construction case involves each side telling their story. Details and visual context make a story compelling. Evidence and corroboration make a story persuasive. Photographs can help on both of these fronts.
The Value of Photographic Evidence in Construction Litigation
Consider the following examples:
- A dispute relates to the timeliness of particular work. An employee has a memory of a load of materials arriving to the site later than it should have, but the records are incomplete or ambiguous about when it actually occurred. If the employee also took a photo of the materials, on the day they arrived, they could match up the date of the photo to their memory and build a clear timeline.
- A dispute relates to the presence or absence of obstructions in drilled shafts. There are no available photographs or videos of the work due to site restrictions. Presentation of this type of case may be severely limited by not being able to show photos depicting the size, shape and type of material removed from the shafts, and by the lack of video depicting the work.
Reprinted courtesy of
Marie Mueller, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Ms. Mueller may be contacted at
mmueller@verrill-law.com
Insurer Wrongfully Denies Coverage When Household Member Fails to Submit to EUO
May 06, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe court determined that coverage for a loss by fire could not be denied when the insured's son failed to appear for a examination under oath (EUO). Adekola v. Allstate Vehicle & Prop. Ins. Co., 2024 U.S. Dist. LEXIS 27125 (E.D. Pa. Feb. 16, 2024).
Plaintiff had a homeowners policy with Allstate. Plaintiff - Michele Adekola - was the named insured under the policy. After the fire, Allstate provided payments for temporary housing. Allstate requested examinations under oath of Plaintiff and her son, Nico. Plaintiff and her son were examined by Zoom. Allstate then sought to examine Plaintiff's other son, Lemmeco, but these efforts were unsuccessful.
Allstate then stopped paying for Plaintiff's temporary housing and informed Plaintiff that Lemmeco's failure to participate in an EUO was a material breach of duties under the policy and the breach was prejudicial to Allstate. Allstate further contended that Lemmeco had a duty to submit to an EUO.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Construction Mezzanine Financing
March 29, 2017 —
Tim Davis & Steven Coury - White and Williams LLPConstruction mezzanine lending is on the rise and more development deals are getting done with a capital stack that includes mezzanine debt in addition to the traditional components of sponsor equity and senior mortgage debt. Below are important issues and concepts to bear in mind when structuring the financing of a construction project that includes a mezzanine debt component.
Funding Sequence
Funding Sequence
When will the proceeds of the mezzanine loan be advanced? In some instances, the mezzanine loan proceeds will be advanced only after all of the borrower’s equity has been contributed to the construction of the project. In other instances, the borrower’s equity and the mezzanine loan proceeds go in either pari passu or simultaneously at another ratio. If the equity is not entirely contributed in advance, the mezzanine lender may require that the uncontributed equity be held by the mezzanine lender or held in a pledged account. The mezzanine lender may also further mitigate the risk of non-funding of the equity by requiring an equity funding guaranty (as discussed below).
Additionally, when will the mezzanine loan proceeds be advanced in relation to the senior mortgage loan proceeds? Will the entire mezzanine loan be advanced prior to any senior mortgage loan advance or will they be advanced pari passu? Depending on the business deal, the mezzanine loan agreement will need to reflect how and when the equity, the mezzanine debt, and the mortgage debt will be advanced.
Reprinted courtesy of
Tim Davis, White and Williams LLP and
Steven Coury, White and Williams LLP
Mr. Davis may be contacted at davist@whiteandwilliams.com
Mr. Coury may be contacted at courys@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Property Damage to Insured's Own Work is Not Covered
May 27, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe Michigan Court of Appeals found there was no coverage for a lawsuit filed against the insureds for faulty workmanship. Skanska United States Bldg. v M.A.P. Mech. Contrs., 2019 Mich App. LEXIS 529 (Mich. Ct. App. March 19, 2019).
Contractor Skanska United States Building was the construction manager on a renovation project for the medical center. The heating and cooling portion of the project was subcontracted to M.A.P. Mechanical Contractors (MAP). MAP had a CGL policy from Amerisure Insurance Company. Skanska and the medical center were named as additional insureds on the policy.
After installation of the steam boiler and related piping, it was discovered that the heating system did not function property. Skanska discovered that MAP had installed some of the expansion joints backward, causing damage to concrete, steel, and heating system. The medical center sent a demand to MAP. Skanska performed the repairs and replaced the damaged property. Skanska then submitted a claim to Amerisure, which was denied.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Update Regarding McMillin Albany LLC v. Super Ct.
April 28, 2016 —
Richard H. Glucksman and David A. Napper – Chapman Glucksman Dean Roeb & Barger In FocusThe construction industry continues to await the California Supreme Court's highly anticipated decision regarding McMillin Albany LLC v. Super Ct. 2015 F069370 (Cal.App.5 Dist.). The Supreme Court will attempt to resolve the conflict presented by the Fourth Appellate District Court's holding in Liberty Mut. Ins. Co. v. Brookfield Crystal Cove LLC (2013) 219 Cal.App.4th 98 and rejection of the same by the Fifth Appellate District Court in McMillin Albany. The issue is whether the Right to Repair Act (SB800) is the exclusive remedy for all defect claims arising out of new residential construction sold on or after January 1, 2013. CGDRB has been closely monitoring the progress of the case and understands that the real parties in interest have submitted their opening brief on the merits. The Court granted Petitioners a further and final extension to file the answer brief on the merits. The answer deadline is Monday April 25, 2016. Stay tuned.
Reprinted courtesy of
Richard H. Glucksman, Chapman Glucksman Dean Roeb & Barger and
David A. Napper, Chapman Glucksman Dean Roeb & Barger
Mr. Glucksman may be contacted at rglucksman@cgdrblaw.com
Mr. Napper may be contacted at dnapper@cgdrblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Homeowner Alleges Pool Construction Is Defective
November 13, 2013 —
CDJ STAFFA Texas man is suing the contractor who built his pool alleging that within months of construction, the pool began to crack and leak water. According to the lawsuit from Larry Merendino, when the concrete contractor, PC Construction, removed some concrete, they found PVC joints that were not glued properly and were leaking.
Mr. Merendino is suing the company and five other firms, claiming that the construction of his pool was negligent and that the companies operated by deceptive trade practices.
Read the court decisionRead the full story...Reprinted courtesy of
Georgia Federal Court Holds That Pollution Exclusion Bars Coverage Under Liability Policy for Claims Arising From Discharge of PFAS Into Waterways
December 18, 2022 —
Paul Briganti - White and WilliamsOn December 5, 2022, the U.S. District Court for the District of Georgia held that a total pollution exclusion (TPE) in a CGL policy relieved the insurer of any obligation to defend or indemnify a recycling company in a putative class action alleging PFAS contamination of Georgia waterways. See Grange Ins. Co. v. Cycle-Tex Inc., et al., Order, Civ. A. No. 4:21-cv-00147-AT (N.D. Ga. Dec. 5, 2022). The decision adds to a slowly-developing body of case law addressing coverage issues arising out of PFAS-related claims.
In Grange, the insured, Cycle-Tex, Inc., was the operator of a thermoplastics recycling facility in Dalton, Georgia. Cycle-Tex and other defendants – which included chemical suppliers, carpet manufacturers, intermediaries, the City of Dalton and the Dalton-Whitfield Solid Waste Authority – were named in a putative class action complaint alleging that residents of Dalton had been injured as a result of the defendants’ discharge of PFAS into local waterways. The complaint sought damages for: (1) alleged harm to the residents’ health by virtue of ingesting contaminated water; (2) alleged property damage resulting from the contamination of the public water supply; and (3) the payment of surcharges and heightened water rates as a result of the alleged contamination.
Read the court decisionRead the full story...Reprinted courtesy of
Paul Briganti, White and WilliamsMr. Briganti may be contacted at
brigantip@whiteandwilliams.com
Blackstone Suffers Court Setback in Irish Real Estate Drama
August 20, 2014 —
Donal Griffin and Dara Doyle – BloombergAt 11:15 a.m. on July 29, Irish property developer Michael O’Flynn realized that Blackstone Group LP (BX) was trying to gain control of his real estate empire, which includes the country’s tallest residential tower.
Ten weeks earlier, the private equity firm had bought 1.8 billion euros ($2.4 billion) of loans to O’Flynn’s companies and the developer personally. Coming out of a meeting, he learned Blackstone was demanding the immediate repayment of 16 million euros of personal loans secured on his shareholdings -- even though he wasn’t in default. By the end of the day he had lost control of the business he’d spent more than 30 years building.
“I was shocked that they’d made this demand,” O’Flynn, 57, said in an interview. “It took time to understand the gravity of it because I’ve never been served with a demand in my 36 years of business. I was very recently transferred to Blackstone and I was doing my damnedest to work with them.”
Mr. Doyle may be contacted at ddoyle1@bloomberg.net; Mr. Griffin may be contacted at dgriffin10@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Donal Griffin and Dara Doyle, Bloomberg