Contractual Indemnification Limitation on Florida Public Projects
July 28, 2016 —
David Adelstein – Florida Construction Legal UpdatesConstruction contract indemnification provisions are governed under Florida Statute s. 725.06. This is a very important statute to know if you are drafting indemnification provisions for any type of construction contract. (There is also Florida Statute s. 725.08 that discusses indemnification provisions applicable to design professionals that is also worth knowing.)
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Paycheck Protection Flexibility Act Of 2020: What You Need to Know
July 20, 2020 —
Amy R. Patton & Rana Ayazi - Payne & FearsOn June 5, 2020, President Trump signed into legislation the bipartisan bill titled the Paycheck Protection Program Flexibility Act of 2020 (PPPFA). The PPPFA modifies the Paycheck Protection Program, which was first introduced under the Coronavirus Aid, Relief, and Economic Security Act (CARES Act). The modifications provide borrowers more control over the use of funds and make it easier to obtain forgiveness. The following is a summary of the key changes.
1. Extended Maturity Date From 2 Years to 5 Years
Under the CARES Act, the minimum maturity date for loan amounts after the forgiveness period was not defined. The Small Business Administration (SBA) then released an Interim Final Rule clarifying that the minimum maturity date was two years. The PPPFA has extended the term to five years: “The covered loan shall have a minimum maturity of 5 years and a maximum maturity of 10 years from the date on which the borrower applies for loan forgiveness under that section.”
2. Extension of Covered Period From Eight Weeks to a Maximum of 24 Weeks
Under the CARES Act, the covered period of the loan (i.e., the time period in which you may spend the loan funds) was February 15, 2020 to June 30, 2020, an eight-week period. The PPPFA extended the covered period to 24 weeks from the origination date of the loan, or December 31, 2020, whichever is earlier.
Reprinted courtesy of
Amy R. Patton, Payne & Fears and
Rana Ayazi, Payne & Fears
Ms. Patton may be contacted at arp@paynefears.com
Ms. Ayazi may be contacted at ra@paynefears.com
Read the court decisionRead the full story...Reprinted courtesy of
The Heat Is On
June 13, 2022 —
Christopher Durso - Construction ExecutiveEvery year, NASA and the National Oceanic and Atmospheric Administration (NOAA) team up to assess global temperatures and climate trends. (Yes, that NASA. A big part of the space agency’s mission is focused on Earth science, with the goal of better understanding the planet’s interconnected systems.) The two groups released their findings for 2021 this past January, with several predictably alarming highlights:
- 2021 was the sixth-warmest year on record, with the average global surface temperature about 1.5°F over the 20th-century baseline periods that the agencies use for comparison and nearly 2°F higher than in the late-19th century.
- The surface temperature in the Northern Hemisphere was also the sixth-highest on record, at nearly 2°F over baseline, with the land temperature exceeding the baseline by 2.8°F.
- Extreme climate events included an above-average Atlantic hurricane season, with 21 storms, and a severe heat wave in the northwestern United States and western Canada in June during which Canada recorded its highest temperature ever, at 121°F.
Reprinted courtesy of
Christopher Durso, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
PSA: Performing Construction Work in Virginia Requires a Contractor’s License
March 04, 2019 —
Christopher G. Hill - Construction Law MusingsAs a Virginia construction attorney, I often get calls for assistance in dealing with payment disputes. Frequently, these calls come from out of state contractors and subcontractors that have performed work in Virginia.
One of the first questions that I ask is whether these contractors and subcontractors hold a contractor license from the Commonwealth of Virginia. While most do, some do not, likely because they are unaware of the requirement in Virginia that all contractors be licensed when performing work in the Commonwealth. While I haven’t done an exhaustive survey of the statutes and regulations of every state of the union on this point, the confused silence leads me to believe that such is not a requirement in every state. The most common reaction after “I had no idea I needed one” is that the general contractor holds a license so they did not think they needed to hold one. As I stated above, this is incorrect.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Julie Firestone & Francois Ecclesiaste Recognized as 2023 MSBA North Star Lawyers
July 15, 2024 —
Lewis Brisbois NewsroomMinneapolis, Minn. (June 11, 2024) - Minneapolis Partners Julie Firestone and Francois Ecclesiaste were recently named to the Minnesota State Bar Association (MSBA) 2023 North Star Lawyers list, which recognizes attorneys who provide pro bono service to people of low income at no fee.
All attorneys who were recognized by MSBA provided 50 hours or more of pro bono service to low-income Minnesotans last year. MSBA has a long-standing dedication to advancing the Bars’ pro bono efforts through training, recruiting, and sharing pro bono stories in the community.
“Lewis Brisbois has a long-standing commitment to serving our local communities, including through our pro bono practice, and we are proud of our partners who exemplify this core value of our Firm,” expressed Michelle Gilboe, Managing Partner of the Minneapolis office.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
Private Mediations Do Not Toll The Five-Year Prosecution Statute
April 28, 2016 —
Zachary P. Marks – Chapman Glucksman Dean Roeb & Barger In FocusIf you thought private mediation could toll the five-year period for case prosecution – think again. In a recent decision handed down by the Second District Court of Appeal, the court unequivocally held that voluntary, private mediations do not toll the five-year period before dismissal for failure to bring an action to trial.
California Code of Civil Procedure section 583.310 sets forth the applicable rule: “[a]n action shall be brought to trial within five years after the action is commenced against the defendant.” Section 1775.7(b) clarifies this rule, stating that the five-year period can be tolled if it is “submitted to mediation” within the final six months of the five-year period. However, the Code is silent with respect to the effect of tolling on public versus private mediations.
The Court of Appeal addressed this issue in its recent decision entitled Castillo v. DHL Express (USA) (2015) 243 Cal.App.4th 1186. Castillo was an employment class action brought by truck drivers against their employers. Plaintiffs argued that the case was “submitted to mediation” within the meaning of Section 1775.7(b) because the court’s Case Management Order reflected the fact that the parties agreed to pursue mediation. Conversely, defendants argued that the Case Management Statement clearly stated that the parties voluntarily agreed to a private mediation, not a court-ordered mediation.
Read the court decisionRead the full story...Reprinted courtesy of
Zachary P. Marks, Chapman Glucksman Dean Roeb & Barger In FocusMr. Marks may be contacted at
zmarks@cgdrblaw.com
2019 Legislative Changes Affecting the Construction Industry
July 09, 2019 —
Melinda S. Gentile & Cadian T. Baker - Peckar & Abramson, P.C.The 2019 Florida Legislative Session recently concluded and a number of important construction-related House Bills (HB) and Senate Bills (SB) were presented during the Session. Below is a summary of those construction-related bills set to become law in 2019.
Bills Becoming Law in 2019
HB 1247: Relating to Construction Bonds. This bill passed both the House and the Senate and is awaiting the Governor’s signature. Once the Governor has approved the bill it becomes effective as of October 1, 2019.
This bill addresses how to properly perfect a claim against a contractor’s payment bond.
(1) The Notice of Nonpayment that must be served on the contractor and the surety, must be made under oath and include the following provisions:
The nature of the labor or services performed or to be performed;
The materials furnished or to be furnished;
The amount paid on the account; and if known, the amount owed and the amount to become due.
A Notice of Nonpayment that includes the sums for retainage must specify the portion of the amount claimed for retainage.
(2) A subcontractor, laborer, or material supplier (claimant) who files a fraudulent Notice of Nonpayment loses their rights under the bond. The filing of a fraudulent notice is a complete defense to claimant’s claim against the bond. A notice is fraudulent if the claimant willfully exaggerated the amount due, willfully included a claim for work not performed or materials not furnished or prepared the notice with willful and gross negligence, which resulted in willful exaggeration. However, a minor mistake in the notice, or a good faith dispute as to the amount due, is not considered fraudulent. Please note that this provision mirrors the existing statute relative to a fraudulent lien.
Read the court decisionRead the full story...Reprinted courtesy of
Melinda S. Gentile, Peckar & Abramson, P.C.Ms. Gentile may be contacted at
mgentile@pecklaw.com
Bad Faith and a Partial Summary Judgment in Seattle Construction Defect Case
February 10, 2012 —
CDJ STAFFThe US District Court of Washington has issued a ruling in the case of Ledcor Industries v. Virginia Surety Company, Inc. Ledcor was the builder of a mixed-use real estate project in Seattle called the Adelaide Project. Ledcor purchased an insurance policy from Virginia Surety covering the project. After the completion of the project, Ledcor received complaints of construction defects from the homeowners, which they forwarded to Virginia Surety.
Virginia Surety denied coverage on several grounds. Absent any lawsuit, Virginia claimed that there was “not yet any duty to defend or indemnify.” Further, as the policy commenced ten days after work on the project was substantially completed, Virginia cited a provision in the policy that excluded coverage for damage that occurred before the policy began. As problems included water intrusion, Virginia noted an exclusion for fungal damage. Finally, Virginia noted that it was not clear whether damage was due to Ledcor’s own actions.
The homeowners sued over the construction defects. Ledcor settled these suits before trial. In this, they were defended by, and settlements were paid by American Home, another of Ledcor’s insurers. Ledcor claims that Virginia Surety acted in bad faith by denying coverage and by its failure to investigate the ongoing nature of the work at the project.
The judge determined that Virginia Surety acted in bad faith when it invoked the fungus exclusion. Virginia noted that fungal damage “‘would have been’ referenced in the list of construction defects,” however, the HOAs claimed only “water stains” and “water damage,” and made no mention of mold or fungus. The court found that Virginia Surety “was not entitled to deny coverage simply because it may have suspected that mold or fungus damage existed.” The court noted that further proceedings would be needed to determine what portion of the settlement Virginia is obligated to pay.
The court found that there were matters of fact to be determined on the further issues in the case. The judge wrote that although Virginia acted in bad faith in invoking the fungus exclusion, it still had to be determined if they were in breach of contract by failing to defend Ledcor. Ledcor still needs to show that the damages claimed by the HOA were due to work actually covered by Virginia Surety.
Ledcor made an additional claim that Virginia Surety violated Washington’s laws concerning the insurance industry. Here, the court noted that the improper exclusion for fungus issues “constitutes a per se unfair trade practice.” Six other claims were made under this law. The court found that Virginia Surety did not misrepresent “pertinent facts or insurance policy provisions.” It also issued its denial letter promptly, satisfying the fifth provision. However, Virginia Surety did violate the second provision, in that it failed “to acknowledge and act reasonably promptly upon communications with respect to claims.” Two other issues could not be determined.
Judge Martinez’s decision granted a summary judgment to Ledcor on the issue of bad faith. An additional summary judgment was granted that Virginia Surety violated Washington’s Insurance Fair Conduct Act. Judge Martinez did not grant summary judgment on any of the other issues Ledcor raised.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of