Texas Walks the Line on When the Duty to Preserve Evidence at a Fire Scene Arises
October 14, 2019 —
Lian Skaf - The Subrogation StrategistThe extent to which a loss scene can be altered before adversaries can legitimately cry spoliation has long been a mysterious battleground in the world of subrogation. In the case of In re Xterra Constr., LLC, No. 10-16-00420-CV, 2019 Tex. App. LEXIS 3927 (Tex. App. – Waco, May 15, 2019), the Court of Appeals of Texas, Tenth District, addressed the question of when a party has a duty to preserve evidence. The court found that the trial court abused its discretion in imposing sanctions on the defendants for the spoliation of evidence as the evidence at issue was already gone by the time the defendants knew or reasonably should have known there was a substantial chance a claim would be filed against them.
In this matter, Xterra Construction, LLC, Venturi Capital, Inc. d/b/a Artisan Cabinets and Keith D. Richbourg (collectively, Xterra) leased a commercial space from building owners Daniel Hull and William H. Beazley, Jr. (collectively, Hull) to be used as a woodworking and cabinet making warehouse. On October 18, 2014, there was a fire at the warehouse. By October 20, 2014, Xterra informed its insurance carrier, Cincinnati Insurances Companies (“Cincinnati”) of the loss and Cincinnati’s adjuster, Leann Williams (Williams), met with Keith D. Richbourg (Richbourg) at the site. Williams also hired expert Jim Reil (Reil) to inspect the fire scene to perform a cause and origin investigation. The next day, Williams informed Hull’s attorney that Reil would inspect the scene on October 23, 2014. Hulls attorney, however, did not send anyone to the scene to participate in the inspection.
Read the court decisionRead the full story...Reprinted courtesy of
Lian Skaf, White and Williams LLPMr. Skaf may be contacted at
skafl@whiteandwilliams.com
Safety, Technology Combine to Change the Construction Conversation
September 30, 2019 —
Neil Riddle & Brent Burger - Construction ExecutiveNew technologies are redefining how to plan, build and deliver the full spectrum of construction projects. Automation, software and new processes are changing the construction industry in unprecedented ways, and construction management is evolving along with it. Construction companies are adapting—using innovative tools and resources, joined by more aggressive risk management and decision-making methods. All the while, safety remains at the heart of every successful new build.
Envisioning the Modern Job Site
Productivity has increased by leaps and bounds as processes have gotten faster and cheaper. Twenty years ago, the industry looked completely different— a $500 million project would have taken four years to deliver; today, it can be done in 29 months.
These new projects are becoming incredibly complex as new technologies change the size and scope, giving rise to more specialization and fragmentation. Building projects faster with fewer people requires a whole new level of preparation. This is where advanced planning and advanced work packaging can play a big role—by informing exactly how the material is going to arrive, how it will be staged, how it will be fabricated and how the area can be best managed to deliver the work.
Reprinted courtesy of
Neil Riddle & Brent Burger, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Riddle may be contacted at RiddleRN@bv.com
Mr. Burger may be contacted at BurgerBB@bv.com
Read the court decisionRead the full story...Reprinted courtesy of
Why a Challenge to Philadelphia’s Project Labor Agreement Would Be Successful
February 22, 2018 —
Wally Zimolong – Supplemental ConditionsThere is a common misconception that all Philadelphia Public Works projects must be performed pursuant to a project labor agreement with various members of the Building and Construction Trades Council. This common misconception is even shared by the current Mayoral administration, who I saw in a recent court filing testified under oath that “project labor agreements are required for all construction projects in Philadelphia with a value of at least five million dollars.” (As is discussed below this is flat out false.)
No one has yet to step forward to challenge Philadelphia’s project labor agreement scheme. However, if someone did, I think the challenge would be successful for three reasons. First, contrary to the Mayor’s representative’s statement, there is no requirement that all projects in excess of $5 million be subject to a project labor agreement. Second, Philadelphia’s project labor agreement excludes signatories to collective bargaining agreements with the United Steel Workers (USW) from participating, which violates public bid laws. Third, the exclusion of the USW, also gives rise to a challenge that federal labor law preempts the project labor agreement.
A. Background on the Philadelphia PLA.
Under a project labor agreement (PLA), a contractor wishing to perform work on a project agrees to be bound by the terms and conditions of employment established by the public owner and certain construction unions. Each PLA varies, but typically PLA’s will require a contractor’s employees to become members of a union – if they are already not members – in order to work on a project or will require a contractor to hire labor from a union hiring hall. PLA’s are controversial because they exclude non-union contractors from performing work on a project subject to a PLA, unless of course that contractor agrees to become “union” for purposes of that project. For reasons beyond this blog post, a merit shop contractor would be crazy to do that.
The “Philadelphia PLA” that Mayor Kenney believes is required for all public projects over $5 million was instituted by Mayor Nutter through a
2011 Executive Order(Executive Order No. 15-11, Public Works Project Labor Agreements).
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
Trial Court's Award of Contractual Fees to Public Adjuster Overturned
June 03, 2019 —
Tred R. Eyerly - Insurance Law HawaiiA judgment awarding the public adjuster his compensation for work performed under contract was remanded for further proceedings by the Hawaii Intermediate Court of Appeals. Joslin v Ota Camp-Makibaka Ass'n, 2019 Haw. App. LEXIS 155 (Haw. Ct. App. April 5, 2019).
A fire destroyed the homeowners' residence on September 19, 2013. The property was subject to the bylaws of the Association of Apartment Owners of Ota Camp. The Association had a policy with Alterra Excess & Surplus Insurance Company and submitted a claim for all units damaged in the fire. The Association's adjuster came the following day to inspect the site.
Separately, Robert Joslin, public adjuster, entered a contract with the homeowners to adjust their claim in exchange for twelve-percent of any insurance proceeds obtained. Over the next several months Joslin pursued insurance proceeds from Alterra on behalf of the homeowners. On December 18, 2013, Joslin filed a complaint with the Insurance Division arguing that Alterra had failed to timely make payments on the claim.
On February 10, 2014, Alterra's third party administrator, Engle Martin & Associates, sent a check to Joslin for $231,940 made out to the Association, the homeowners and Joslin.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Construction Defect Risks Shifted to Insurers in 2013
December 11, 2013 —
CDJ STAFFRecent court decisions have tended to view construction defects as covered under insurance policies, “allowing construction companies to shift the costs of their faulty workmanship to their insurers, thereby reversing the previous public policy trend against coverage for such claims.” John Husmann and Adam Fleischer of Bates Carey Nicolaides review some of the 2013 decisions that reversed “the previous public policy trend against coverage for such claims.”
They note that “for some time, courts have recognized that there is a public policy against allowing construction companies to get paid to perform faulty workmanship, and then force their insurers to be the financers for the repair and replacement costs.” But in 2013, the courts “strayed from those public policy considerations upon which previous decisions relied.”
With reference to specific cases and decisions, they discuss three ways in which the courts have change course. The first is whether faulty workmanship is an “occurrence.” The next is if faulty workmanship is covered when it damages non-faulty work of the same project. And finally, whether exclusions for particular parts of the property extend to the work done in that area.
Read the court decisionRead the full story...Reprinted courtesy of
Singer Akon’s Multibillion-Dollar Futuristic City in Africa Gets Final Notice
September 02, 2024 —
Katarina Hoije & Fred Ojambo - BloombergA single arched concrete block juts out of a field in Senegal where R&B singer Akon first laid the foundation stone for his $6 billion metropolis four years ago.
The West African nation granted the artist 136 acres of land on its Atlantic Coast in 2020 to build his Akon City — envisioned as a real-life Wakanda, the fictional country from Marvel Studios’ Black Panther films.
Complete with condominiums, amusement parks and a seaside resort in gravity-defying skyscrapers rising above the rural landscape, Akon City would run on solar power and his Akoin cryptocurrency, the American-Senegalese singer said during a flashy presentation in Senegal’s capital, Dakar.
Today, goats and cows graze the deserted pasture 60 miles south of Dakar, and authorities are growing increasingly impatient.
Reprinted courtesy of
Katarina Hoije, Bloomberg and
Fred Ojambo, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
For Whom Additional Insured Coverage Applies in New York
November 11, 2024 —
Bill Wilson - Construction Law ZoneSimply including a requirement in a contract to add certain parties as additional insureds under a commercial general liability insurance (CGL) policy may not be enough to ensure such coverage is provided in New York. In New York City Hous. Auth. v. Harleysville Worcester Ins. Co., 226 A.D.3d 804 (2024), the New York Supreme Court Appellate Division – Second Department ruled that the language in an insurance endorsement required privity of contract with the insured party subcontractor to obtain additional insured status and denied coverage to others despite a provision in a subcontract requiring such additional insured coverage.
In this case, an owner entered into a contract with a general contractor for construction services. The general contractor entered into a subcontract with a subcontractor. The subcontractor agreed to procure and maintain a CGL policy naming the owner, the general contractor, and another related party as additional insureds thereunder. An employee of the subcontractor was injured on the project and sued the three additional insureds and several other parties. Subcontractor’s insurance company refused to defend and indemnify any party other than the general contractor. All the parties sued by the subcontractor’s employee brought an action against the subcontractor’s insurance company, seeking coverage for defense and indemnification as additional insureds under the subcontractor’s CGL policy.
Read the court decisionRead the full story...Reprinted courtesy of
Bill Wilson, Robinson & Cole LLPMr. Wilson may be contacted at
wwilson@rc.com
What California’s COVID-19 Reopening Means for the Construction Industry
July 05, 2021 —
Garret Murai - California Construction Law BlogThis past Wednesday, Governor Newsom announced that California would reopen after being in lockdown for over a year due to COVID-19. Gone is Governor’s Stay at Home Executive Order. Gone is California’s Blueprint for a Safer Economy. And gone is the state’s somewhat confusing four-tier, yellow (minimal), orange (moderate), red (substantial) and purple (widespread), risk-level mapping system.
So what does this mean for the construction industry?
Well it’s not quite business back to usual. CalOSHA’s Standards Board voted this past Thursday to pass revised COVID-19 Emergency Temporary Standards (“Revised Standards”). That same day, Governor Newsom signed Executive Order N-09-21 implementing the Revised Standards immediately while they are being reviewed by the Office of Administrative Law.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com