LAX Construction Defect Suit May Run into Statute of Limitations
December 30, 2013 —
CDJ STAFFCurrent arguments over the claims made by LAX that Runway 25L was built in a defective manner by Tutor-Saliba/O&G Industries are hinging over whether the airport knew the runway was defective less than four years after the construction was completed. The runway was built almost five years ago, and Tutor-Saliba is claiming that Los Angeles World Airports has delayed too long in making a construction defect complaint. Tutor-Saliba is not conceding that the runway is defective, only that if it were, the airport would have known it earlier.
Los Angeles World Airports, which operates LAX, is not commenting on the matter, but Robert Span, an aviation attorney at Steinbrecher & Span, told the Daily Breeze that while “there is a four year statute of limitations for dealing with construction defects, but that’s for what they called patent defects,” and that “there’s a 10-year statute of limitations for construction projects where the defect that is alleged is called latent — something that would not be readily apparent.”
Tim Pierce, a construction attorney at K&L Gates LLP described it as “a common defense,” though he said it is “raised in most cases and only works in some.”
Read the court decisionRead the full story...Reprinted courtesy of
Draft Federal Legislation Reinforces Advice to Promptly Notify Insurers of COVID-19 Losses
April 20, 2020 —
James Hultz - Newmeyer DillionInsurers across the country are nearly universally denying claims for business interruption stemming from the COVID-19 pandemic. Those denials have in turn been met with swift litigation and potential legislative action. The first business interruption coverage lawsuit related to COVID-19 was filed in New Orleans on March 16. There are now no less than 13 such cases nationwide and many more are likely to follow. Further, legislatures in at least seven states are considering legislation that would, to varying degrees, mandate business interruption coverage for COVID-19 losses, notwithstanding any seemingly contrary policy provisions.
From the early stages of the pandemic, we have consistently advised our clients to promptly notify their insurers of all COVID-19 related losses, even where coverage appeared uncertain. The deluge of coverage litigation and contemplated legislation could drastically alter how insurers handle COVID-19 claims. But policyholders who have failed to satisfy policy notice requirements could miss out on the benefits of those changes. Therefore, policyholders would be ill-advised to sit on the sidelines and wait it out.
Now, draft Federal legislation appears to add further impetus to instructions to “tender early.” The contemplated “Pandemic Risk Insurance Act of 2020” would reportedly devote billions of dollars of federal funds through a Department of Treasury administered reinsurance program designed to offset losses sustained by insurers who actually pay business interruption losses. The legislation is still taking shape but would reportedly create “a Federal program that provides for a transparent system of shared public and private compensation for business interruption losses resulting from a pandemic or outbreak of communicable disease.” President Trump is also reportedly pressuring insurers to provide business interruption coverage. The massive influx of federal funds and pressure from the White House could encourage insurers to reconsider denials of COVID-19 business interruption claims.
Read the court decisionRead the full story...Reprinted courtesy of
James Hultz, Newmeyer DillionMr. Hultz may be contacted at
james.hultz@ndlf.com
6 Ways to Reduce Fire Safety Hazards in BESS
January 02, 2024 —
The Hartford Staff - The Hartford InsightsRenewable energy sources, such as solar and wind, are projected to generate 44% of all power in the U.S. by 2050, which is increasing the need for battery energy storage systems (BESS).1
BESS are electrochemical devices that collect energy from a power grid, power plant or renewable source, hold it, and then discharge that energy later to provide electricity on demand.
“A BESS does not itself create or produce energy, it is a storage system. The energy is produced by other means, including different types of renewable sources. Think of a cellphone – you charge it overnight and then it runs throughout the day off that battery power,” says Stacie Prescott, head of energy for middle and large commercial at The Hartford.
Read the court decisionRead the full story...Reprinted courtesy of
The Hartford Staff, The Hartford Insights
Helsinki is Building a Digital Twin of the City
May 20, 2019 —
Aarni Heiskanen - AEC BusinessThe capital of Finland first tested city modeling as long back as 1987. But the most recent model of the Kalasatama district demonstrates the new state-of-the-art possibilities of this technology: creation of a highly accurate digital twin of the city.
My hosts, Helsinki’s city modeling specialists Jarmo Suomisto and Enni Airaksinen, showed me their latest projects. One of them offered a glimpse of history through a lens of the future.
With 3D glasses on, I was able to experience the unrealized city plan made by Eliel Saarinen, the father of the world-renowned architect Eero Saarinen. The virtual model in question was a digitized version of a huge physical model from 1915. Being able to stroll the streets and fly over the roofs of the imagined city really made me understand how awesome the original design was. I had seen a scale model of this same plan while it was laid in the foyer of the Museum of Finnish Architecture many years ago, but this experience was quite different.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Suing a Local Government in Land Use Cases – Part 1 – Substantive Due Process
February 16, 2017 —
Wally Zimolong – Supplemental ConditionsBecause of my personal political persuasions (pro-freedom) and success in litigating cases against the government and other media about those cases businesses frequently approach me about bringing claims against local governments and agencies for interfering with their Constitutional rights. Actions by local government agencies that could give rise to a Constitutional violation include: treating a developer’s project differently than a similar project, revoking a previously issued zoning or building permit, disqualifying a contractor from bidding on a government contract, retaliating against a business owner for speaking out against the local agency or one of its members, or unnecessarily delaying the issuance of a permit. The Constitutional rights most typically implicated in these cases are those guaranteed by the 5th and 14th Amendments to the United States Constitution. However, the 1st Amendment is also frequently implicated.
Suing a local government agency for violating your Constitutional rights is not easy. However, the federal statute under which the cases are brought, 42 U.S.C. Section 1983, provides for the award of a successful plaintiff’s attorneys fees. This is true even if the Judge or jury awards a mere $1 is damages. Moreover, sometimes there can be a strategic value in the litigation.
This is the first in a series of blog posts exploring claims available to businesses harassed by local government agencies and officials and the challenges inherent in successfully bringing those claims. We will start with a claim for a substantive due process violation.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
2017 Colorado Construction Defect Recap: Colorado Legislature and Judiciary Make Favorable Advances for Development Community
January 24, 2018 —
Kaitlin Marsh-Blake – Gordon & Rees Construction Law Blog Last March, the Colorado General Assembly introduced House Bill 17-1279 concerning the requirement that a unit owners’ association obtain approval through a vote of unit owners before filing a construction defect action. The bill, passed in May, requires a home owners’ association to first notify all unit owners and the developer or builder of a potential construction defect action, call a meeting where both the HOA and developer or builder have an opportunity to present arguments and potentially remedy the defect, and obtain a majority vote of approval from the unit owners to pursue a lawsuit before bringing a construction defect action against a developer or builder. The bill amends C.R.S. § 38-33.3-303.5, which previously only required substantial compliance with the above-mentioned actions. Moreover, the previous version of C.R.S. § 38-33.3-303.5 did not require the HOA to perform these actions prior to a suit being filed. HB 17-1279 also removed the provision of C.R.S. § 38-33.3-303.5 that made it only applicable to buildings of five or more units.
Read the court decisionRead the full story...Reprinted courtesy of
Kaitlin Marsh-Blake, Gordon & ReesMs. Marsh-Blake may be contacted at
kmarsh-blake@grsm.com
Force Majeure Under the Coronavirus (COVID-19) Pandemic
March 29, 2021 —
Lindsay T. Watkins - Ahlers Cressman & Sleight PLLCAs COVID-19 disrupts work and life as we know it, the question many contractors have is what protections are available against the inevitable project impacts and delays? Generally, construction contracts require a contractor to timely perform work until project completion or potentially face damages (liquidated or actual) and possible termination. When events occur, however, that are beyond our control (such as a national pandemic), it is important to review and understand what contract provisions or avenues are available for potential relief.
- Review Your Contract For A Force Majeure Provision.
A “force majeure” contract provision is commonly included in construction contracts, service agreements, purchase orders, etc. It typically covers events or conditions that can be neither anticipated nor controlled. These provisions, however, will vary greatly from contract to contract and may not include the language “force majeure” but rather may be included in general delay or impact clauses. For example, some common provisions include:
- Washington State Department of Transportation Clause (2018 Standard Specifications for Road, Bridge and Municipal Construction): The Contractor shall rebuild, repair, restore, and make good all damages to any portion of the permanent or temporary Work occurring before the Physical Completion Date and shall bear all the expense to do so, except damage to the permanent Work caused by: (a) acts of God, such as earthquake, floods, or other cataclysmic phenomenon of nature, or (b) acts of the public enemy or of governmental authorities; or (c) slides in cases where Section 2-03.3(11) is applicable; Provided, however, that these exceptions shall not apply should damages result from the Contractor’s failure to take reasonable precautions or to exercise sound engineering and construction practices in conducting the Work.
Read the court decisionRead the full story...Reprinted courtesy of
Lindsay T. Watkins, Ahlers Cressman & Sleight PLLCMs. Watkins may be contacted at
Lindsay.Watkins@acslawyers.com
Hawaii Federal Court Grants Insured's Motion for Remand
January 12, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe federal district court, district of Hawaii, recently granted the insured's motion for remand. Catholic Foreign Mission Society of Am., Inc. v. Arrowood Indem. Co., Civ. No. 14-00420, Order Granting Plaintiff's Motion for Remand and Denying Defendants' Motion to Dismiss or Transfer (D. Haw. Dec. 30, 2014) [Order here]. [Full disclosure - our office represents the insured, Maryknoll].
Maryknoll was sued in several lawsuits filed in Hawaii state court by victims of alleged sexual abuse occurring as far back as the 1950s by members of the clergy. Maryknoll was insured during these periods under liability policies issued by various carriers. The successor of Royal Globe Insurance Company, Arrowood Indemnity Company, agreed to defend some of the underlying lawsuits, but declined to defend others. The Travelers Companies, Inc. refused to defend.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com