Miller Act and “Public Work of the Federal Government”
March 01, 2017 —
David Adelstein – Florida Construction Legal UpdatesThe Miller Act applies to the “construction, alteration, or repair of any public building or public work of the Federal Government.” 40 U.S.C. s. 3131.
A recent opinion out of the Northern District of Oklahoma sheds light on what the Miller Act means regarding its application to any public work of the Federal Government. See U.S. v. Bronze Oak, LLC, 2017 WL 190099 (N.D.Ok. 2017). If the project is not a public works project of the Federal Government, the Miller Act does not apply.
In this case, the Department of Transportation entered into an agreement with the Cherokee Nation where the Department would provide lump sum funding and the Nation would use the money to fund transportation projects. Based on the federal funding, the Nation issued a bid for a transportation project in Mayes County, Oklahoma and the project was awarded to a prime contractor. The prime contractor provided a payment bond that identified the United States as the obligee (as a Miller Act payment is required to do) and stated that it was issued per the Miller Act. Thereafter, the Nation and Mayes County, Oklahoma entered into a Memorandum of Understanding where the County would assume responsibility for the construction and maintenance of the project and the Nation would pay the County an agreed amount upon the completion of the project.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Certified Question Asks Washington Supreme Court Whether Insurer is Bound by Contradictory Certificate of Insurance
January 21, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe Ninth Circuit certified a question to the Washington Supreme Court as follows:
Under Washington law, is an insurer bound by representations made by its authorized agent in a certificate of insurance with respect to a party's status as an additional insured under a policy issued by the insurer, when the certificate includes language disclaiming its authority and ability to expand coverage?
T-Mobile USA Inc. v. Selective Ins. Co lf Am., 2018 U.S. App. LEXIS 31863 (9th Cir. Nov. 9, 2018).
In 2010, T-Mobile entered into a Field Services Agreement (FSA) with Innovative Engineering, Inc. under which Innovative would provide services in connection with the construction of rooftop cellular antennae towers in New York City. The FSA required Innovative to maintain general liability insurance naming T-Mobile as an additional insured, and required that Innovative provide T-Mobile with certificates of insurance documenting the coverage. Innovative obtained coverage from Selective Insurance Company of America.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Former UN General Assembly President Charged in Bribe Scheme
October 21, 2015 —
Patricia Hurtado & Greg Farrell – BloombergA former president of the United Nations General Assembly and a billionaire Macau developer were accused of taking part in a four-year corruption scheme that included bribes to help fund a campaign for the post at the organization in exchange for the promotion of Chinese businesses.
John Ashe, president of the UN General Assembly from September 2013 to September 2014, accepted more than $1 million in payoffs from developer Ng Lap Seng and an associate to help persuade the international body to build a multibillion-dollar conference center in Macau and promote Chinese businesses, including a bank, in Antigua, according to the U.S.
The new charges, announced Tuesday, relate to an earlier case against Ng, 68, who has a personal net worth of about $1.8 billion. He’s been held in a federal jail in Manhattan since he was arrested Sept. 19, accused of bringing $4.5 million into the country and lying about its purpose to U.S. authorities.
Reprinted courtesy of
Patricia Hurtado, Bloomberg and
Greg Farrell, Bloomberg
Read the court decisionRead the full story...Reprinted courtesy of
California Case Adds Difficulties for Contractors & Material Suppliers
August 20, 2014 —
Beverley BevenFlorez-CDJ STAFFGarret Murai in his California Law Blog declared that “things just got a lot tougher for contractors and material suppliers in the Golden State.” In his blog, Murai analyzed the recent case Golden State Boring & Pipe Jacking, Inc. v. Eastern Municipal Water District, Case No. E054618 (July 23, 2014), in which “the California Court of Appeals for the Fourth Appellate District found that a subcontractor’s public works payment bond claim was time barred because its stop payment notice was served ‘before’ a notice of completion was recorded.”
Murai explained the importance of the ruling and how it changed the status quo: “Whereas before, it was commonly understood that you could serve a stop payment notice ‘during’ construction (after all, that was the point wasn’t it, to stop construction funds before they are paid out), now you may have only have a 30 day window (probably less) to serve a stop notice within 30 days after a notice of completion or notice of cessation is recorded.”
Read the court decisionRead the full story...Reprinted courtesy of
Coronavirus, Force Majeure, and Delay and Time-Impact Claims
March 30, 2020 —
Garret Murai - California Construction Law BlogIt’s scary, uncertain times as the world grasps with how to deal with the coronavirus pandemic that has now spread to every continent on the globe with the exception of Antarctica. Although this is a global crisis, it has, and for the immediately future will continue to have, a direct impact on us individually as well our industry.
While the impact of the coronavirus on the construction industry is uncertain, what is certain, is that it will have an impact, whether on the construction labor market, on construction supply chains, on the ability of contractors to deliver projects on time and within budget, and on decisions by owners whether to move forward with projects altogether.
According to Ken Simonson, chief economist with the Associated General Contractors of America, during an interview at the ConExpo conference this past week in Las Vegas, while the coronavirus crises “is a story evolving by the hour . . . the impacts on construction are going to happen, but it’s hard to say how extensive, how long they’ll last, [and] how soon they’ll show up.”
From a legal perspective, the coronavirus, and really any natural disaster, from the “Campfire Fire” in Northern California in 2018 to the “Big One” which can happen anytime, has the potential to adversely impact a construction project or shut it down completely. This in turn raises two different, but interrelated legal concepts: (1) force majeure; and (2) delay and time-impact claims.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Massive Wildfire Near Boulder, Colo., Destroys Nearly 1,000 Homes and Businesses
January 03, 2022 —
Mark Shaw - Engineering News-RecordA wildfire, driven by wind gusts up to 105 mph, swept through 6,000 acres in suburban neighborhoods east of Boulder, Colo., destroying 991 homes and damaging 127 others in the towns of Superior and Louisville, according to estimates from the Boulder County sheriff’s office.
Reprinted courtesy of
Mark Shaw, Engineering News-Record
Mr. Shaw may be contacted at shawm@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Lost Productivity or Inefficiency Claim Can Be Challenging to Prove
May 02, 2022 —
David Adelstein - Florida Construction Legal UpdatesOne of the most challenging claims to prove is a lost productivity or inefficiency claim. There is an alluring appeal to these claims because there are oftentimes intriguing facts and high damages. But the allure of the presentation of the claim does not compensate for the actual burden of proof in proving the lost productivity or inefficiency claim, which will require an expert. And they really are challenging to prove.
Don’t take it from me. A recent Federal Claims Court opinion, Nova Group/Tutor-Saliba v. U.S., 2022 WL 815826, (Fed.Cl. 2022), that I also discussed in the preceding
article, exemplifies this point.
To determine lost productivity or inefficiency, the claimant’s expert tried three different methodologies.
First, the expert looked at industry standard lost productivity factors such as those promulgated by the Mechanical Contractor’s Association. However, the claimant was not a mechanical contractor and there is a bunch of subjectivity involved when using these factors. The expert decided not to use such industry standard factors correctly noting they provide value when you are looking at a potential impact prospectively, but once you incur actual damages and have real data, it is not an accurate measure.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Prevailing Payment Bond Surety Entitled to Statutory Attorneys’ Fees Even if Defended by Principal
January 09, 2023 —
Garret Murai - California Construction Law BlogFor contractors involved in California public works projects the scenario is not uncommon: The general contractor awarded the public works project is required to obtain a payment bond for the benefit of subcontractors and suppliers and the payment bond surety issuing the payment bond requires the general contractor to defend and indemnify the surety from and against any claims against the payment bond.
In Cell-Crete Corporation v. Federal Insurance Company, 82 Cal.App.5th 1090 (2022), the 4th District Court of Appeal examined whether a payment bond surety, who prevails in a claim against the payment bond, is entitled to statutory attorneys’ fees when the party actually incurring the attorneys’ fees was the general contractor, pursuant to its defense and indemnity obligations, as opposed to the surety itself.
The Cell-Crete Case
General contractor Granite Construction Company was awarded a public works contract issued by the City of Thermal known as the Airport Boulevard at Grapefruit Boulevard and Union Pacific Railroad Grade Separation Project. We’ll just call it the “Project.” Subcontractor Cell-Crete Corporation entered into a subcontract with Granite for lightweight concrete and related work.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com