Construction Defects Not Occurrences under Ohio Law
November 07, 2012 —
CDJ STAFFConcluding the “claims of defective construction or workmanship brought by a property owners are not claims for ‘property damage’ caused by an ‘occurrence’ under a commercial general liability policy,” the Supreme Court of Ohio has ruled in Westfield Insurance Co. v. Custom Agri Systems, Inc. In the underlying case, Custom Agri Systems, Inc. built a grain bin as a subcontractor to Younglove Construction, LLC. Younglove had been contracted by PSD Development, which withheld payment, claiming it had suffered damages due to defects in Custom Agri System’s work. Younglove filed a complaint against Custom Agri, which filed complaints against its subcontractors. Custom Agri also requested that its insurer, Westfield Insurance Company, defend and indemnify it. Westfield claimed that it had no such duty. The Ohio Supreme Court concurred.
The decision notes that “Custom was being sued under two general theories: defective construction and consequential damages resulting from the defective construction.” Westfield argued that none of the claims were “for ‘property damage’ caused by an ‘occurrence” and therefore none of the claims were covered under the CGL policy.” Further, Westfield argued that “even if the claims were for property damage caused by an occurrence, they were removed from coverage by an exclusion in the policy.”
The case was filed in the US District Court which issued a summary judgment for Westfield. The plaintiff appealed and Sixth Circuit Court of Appeals certified the questions to the Supreme Court of Ohio.
The court noted that “all of the claims against which Westfield is being asked to defect and indemnify Custom relate to Custom’s work itself.” And so, the court concluded that they “must decide whether Custom’s alleged defective construction of and workmanship on the steel grain bin constitute property damage caused by an ‘occurrence.’” However, the court noted that under the terms of the insurance contract, an occurrence is defined as “an accident, including continuous or repeated exposure to substantially the same general harmful conditions,” and the court noted that the “natural and commonly accepted meaning” of “accident” is something “unexpected, as well as unintended.”
The Ohio Supreme Court also looked at court decisions in other places, and found that in many similar cases, courts have concluded that construction defects are not occurrences.
In a dissenting opinion, Justice Pfeifer argues that “if the defective construction is accidental, it constitutes an ‘occurrence’ under a CGL policy.” Justice Pfeifer characterized the majority’s definition of “accidental” as “broad, covering unexpected, unintentional happenings.”
Read the court decisionRead the full story...Reprinted courtesy of
Slip and Fall Claim from Standing Water in Parking Garage
January 22, 2014 —
Beverley BevenFlorez-CDJ STAFFIn Metairie, Louisiana, Paul Unkauf filed a lawsuit after he allegedly “slipped and fell on standing water in the parking garage,” located at Heritage Plaza, according to the Louisiana Record. The defendants, Stewart Development LLC, Stirling Properties LLC, Platinum Parking LLC and First Financial Company, are “accused of permitting standing water to dampen the pathway leading to the elevator bank, failing to dry the pathway, failing to warn of the hazard, failing to properly inspect the area in question, failing to provide a safe means of exit and entrance, being careless and negligent under the circumstances, failing to properly identify and correct defects in design and failing to properly supervise and train employees,” reports the Louisiana Record.
Unkauf is seeking an “unspecified amount in damages” for “medical expenses, physical pain, loss of function, mental anguish, emotional distress, loss of enjoyment of life and permanent partial disability.”
Read the court decisionRead the full story...Reprinted courtesy of
Continuity and Disaster Recovery Plans for Contractors: Lessons From the Past
November 28, 2022 —
Rich Sghiatti - Construction ExecutiveThere is no shortage of natural disasters to illustrate the importance of being prepared. Wildfires, hurricanes, winter storms and floods can hit a construction job site hard. Appropriate property-casualty insurance and surety bonds are necessary protections for a contractor and project owner. But the addition of well-thought-out continuity and disaster recovery plans will better position the contractor to deal with whatever Mother Nature brings.
Consider Hurricane Katrina, the costliest hurricane to hit the United States. Pummeling Florida, Louisiana and Mississippi in August 2005, the storm led to 1,833 fatalities and an estimated $108 billion in damages. Levees meant to protect New Orleans from Lake Pontchartrain did not hold, flooding 80% of the city.
Utilities including power, water and sanitary sewers were severely damaged. Homes were destroyed. Roadways were closed. Communications systems were down.
Contractors who had good business continuity and disaster recovery plans fared better than those who did not.
Reprinted courtesy of
Rich Sghiatti, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
The Biggest Trials Coming to Courts Around the World in 2021
January 04, 2021 —
Anthony Lin - BloombergSeveral former world leaders, a Hong Kong media tycoon, the CEO of Theranos and Jeffrey Epstein’s confidante — all are scheduled to have their day in court next year.
With vaccinations heralding a return to normalcy, the next year should see courtrooms around the world coming back to life. Ghislaine Maxwell, China critic Jimmy Lai and Samsung heir Jay Y. Lee are among those facing high-profile criminal cases in 2021. Some proceedings, including the fraud trial of Theranos founder Elizabeth Holmes, are resuming after being postponed by the pandemic. Another delayed case, UBS’s appeal of its $4.9 billion French government tax penalty, is among the many that will be heard by higher-level and supreme courts.
There are also a number of cases against former world leaders, including France’s Nicolas Sarkozy, Malaysia’s Najib Razak and South Africa’s Jacob Zuma. One of the most tantalizing questions will be whether a certain former U.S. president could find himself facing trial as well.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony Lin, Bloomberg
U.S. Codes for Deck Attachment
July 16, 2014 —
Beverley BevenFlorez-CDJ STAFFTed Cushman in Big Builder explained how “decks often collapse when the ledger attachment to the main house fails.” Now, codes require “positive attachment…a solid connection with closely spaced lag screws (or better yet, bolts)." Cushman demonstrated this pictorially in a detail. He also stated to make sure to fasten securely, remove siding, and install flashing.
Read the court decisionRead the full story...Reprinted courtesy of
California Contractor Tests the Bounds of Job Order Contracting
March 01, 2021 —
Garret Murai - California Construction Law BlogMost contractors have heard of design-bid-build, design-build, construction manager at risk, and even public private partnerships, various project delivery methods, which, at their heart, focus on balancing the interests of the various parties involved in a construction project, from owners, to design professionals, to contractors. There’s one project delivery method you may not be as familiar with though: Job Order Contracting, also known by its acronym JOC.
JOC contracting is a project delivery method used on public works projects and has been authorized to be used by California K-12 school districts, community colleges, CalState universities, and the Judicial Council of California, which, among other things, is responsible for the construction of California state courts. It is intended to be used on smaller, independent, long-horizon project typically involving maintenance, repair and refurbishment. Think periodic maintenance of facilities.
JOC contracts are administered by public entities issuing a request for proposals. The public entity then awards a JOC contract to the lowest responsible bidder. The lowest responsible bidder then enters into a JOC contract with the public entity. JOC contracts typically have a duration of one (1) year and are limited to a total construction value of $4.9 million increased annually based on the Consumer Price Index. When entering into a JOC contract, a JOC contractor agrees to perform work at prices set forth in a Construction Task Catalog also known as a unit price book which includes current local labor, material and equipment costs. Unit prices are then adjusted by a “bid adjustment factor” based on the JOC contractor’s bid. When work is needed, the public entity will then issue a job order to the JOC contractor.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Sanibel Causeway Repair: Contractors Flooded Site With Crews, Resources
November 15, 2022 —
Derek Lacey - Engineering News-RecordAfter Hurricane Ian slammed into southwest Florida, washing out the Sanibel Causeway and cutting off thousands of Sanibel Island residents, another flood hit the area: construction crews and resources that swarmed the area to rebuild two roadway sections and five washed-out approaches to restore access.
Reprinted courtesy of
Derek Lacey, Engineering News-Record
Mr. Lacey may be contacted at laceyd@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Insurer’s Consent Not Needed for Settlement
October 14, 2013 —
CDJ STAFFThe Texas Supreme Court has concluded in Lennar Corp. v. Markel Am. Ins. Co. that “the costs incurred by a builder to locate and repair damage caused by the builder’s defective product are covered under its general liability insurance policy.” Hunton & Williams have issued a Client Alert discussing the case.
For the background of the case, Lennar built about 800 homes using EIFS. The EIFS trapped water and the homes suffered from rot, structural damage, mold, mildew, and termites. Lennar fixed all the homes so built, avoiding litigation. Lennar “notifed its insurers of the defects and invited its insurers to participate in the proactive remediation program.”
A lower court had agreed with Markel, one of Lennar’s insurers, that the losses were not “caused by property damage,” and that Lennar should not have made “voluntary payments without Markel’s consent.” The Texas Supreme Court granted review, rejecting Markel’s argument and affirming the jury’s finding.
According to Hunton & Williams, the implications of the Texas Lennar decision is that it “confirms that all insurers with policy in effect at the time of property damage are responsible for all sums for which the policyholder is liable.”
Read the court decisionRead the full story...Reprinted courtesy of