Stacy R. Goldscher & Tracy M. Lewis - Wood Smith Henning & BermanHow do you define the term "contractor?" In the case of California Specialty Insulation Inc. v. Allied World Surplus Lines Insurance Company, No. B324805 (2024), the court ultimately honored the reasonable expectations of the insured and ordered that the insurer defend and indemnify in an underlying suit stemming from the policy. This case involves a commercial general liability insurance policy issued by Allied World Surplus Lines Insurance Company (Allied) to California Specialty Insulation, Inc. (CSI). The central issue is whether Allied World is obligated to defend and indemnify CSI against a negligence claim stemming from a construction site accident. The dispute hinges on the interpretation of a policy exclusion for bodily injury to employees of any "contractor," a term not defined in the policy.
Factual Background
In 2017 Air Control Systems. Inc. (Air Control) was contracted to perform improvement work at a Los Angeles building and subsequently hired CSI to install duct insulation. In 2019, Jason Standiford, and Air Control employee, filed a negligence lawsuit against CSI, alleging injuries from a 2017 incident where a CSI employee allegedly drove a scissor lift into a ladder Standiford was on, causing him to fall. CSI requested Allied World to defend it in the Standiford lawsuit. Initially, Allied World accepted the defense, but later withdrew, citing the Contractor Exclusion in the policy. CSI filed for declaratory relief, leading to cross-motions for summary judgment. The trial court ruled in favor of CSI, finding the term contractor ambiguous and construing it in CSI's favor. Allied World appealed the decision.
Reprinted courtesy of
Stacy R. Goldscher, Wood Smith Henning & Berman and
Tracy M. Lewis, Wood Smith Henning & Berman
Ms. Goldscher may be contacted at sgoldscher@wshblaw.com
Ms. Lewis may be contacted at tlewis@wshblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
To Bee or Not to Bee - CA Court Finds Denial of Coverage Based on Exclusion was Premature Where Facts had not been Judicially Determined
November 28, 2018 —
Philip B. Wilusz - Saxe Doernberger & Vita, P.C.While I typically discuss cases concerning pollution, today I will change a few letters around and discuss pollination. The case, Unigard Insurance Co. et al. v. George Perry and Sons Inc. et al., asks whether there is coverage for a lawsuit brought against a commercial farm that is alleged to have killed off bee colonies used for pollination. The farm, owned by George Perry & Sons Inc. (“Perry”), allegedly used a pesticide that killed off the bee colonies that Perry had hired from Gary Mattes (“Mattes”) pursuant to an oral agreement. The bees, operating well outside of their weight class, were hired to pollinate Perry’s crops of watermelons and pumpkins. Interestingly, the bees would be brought to the farm in either large hives or “nukes,” which are smaller versions of hives.
Read the court decisionRead the full story...Reprinted courtesy of
Philip B. Wilusz, Saxe Doernberger & Vita, P.C.Mr. Wilusz may be contacted at
pbw@sdvlaw.com
Negligent Misrepresentation in Sale of Building Altered without Permits
September 30, 2011 —
CDJ STAFFThe Supreme Court of New Hampshire has ruled in the case Wyle v. Lees. The Leeses owned a two-unit apartment building in North Conway, New Hampshire. They hired a contractor to add a third, larger apartment, including a two-car garage. The Leeses and their contractor submitted a building permit application. They were informed that site plan review was required. After receiving approval on the site plan, construction started. At no point did they obtain a building permit and the construction was never inspected. The Leeses subsequently added more space to the unit, reducing parking spaces below the minimum required. Again, they did not obtain a building permit.
In 2007, three years after all these changes were complete, the Leeses sold their building to Mr. Wyle. To the question “are you aware of any modifications or repairs made without the necessary permits?” they answered “no.” About six weeks after closing, Wyle “received a letter from the town code enforcement officer regarding the legality of the removal of a garage door from the new unit.” A subsequent inspection revealed “numerous building and life safety code violations.”
Mr. Wyle brought a claim against the Leeses for negligent misrepresentation. The defendants filed a motion “seeking to preclude economic loss damages.” At a two-day bench trial, Mr. Wyle won. The Leeses appealed.
The appeals court found that “the defendants negligently misrepresented that the premises were licensed for immediate occupancy and that the defendants had obtained all necessary permits,” and thus upheld the lower court’s finding of negligent misrepresentation. The appeals court also rejected the Leeses’ argument that damages must be apportioned on all parties, including “the plaintiff himself, the plaintiff’s building inspector, and the defendant’s contractor,” finding a lack of “adequate evidence.”
The Leeses further argued that they were unaware that modifications and repairs were accomplished without the required permits. The appeals court noted that “the trial court found that both the conditional approval and final approval for the site plan stated that a building permit and a certificate of occupancy were required prior to any use.” The court concluded that the Leeses “knew or should have known of the falsity of their representation.”
The appeals affirmed the findings of the trial court.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Nailing Social Media: The Key to Generating Leads for Construction Companies
March 13, 2023 —
Matthew DeVries - Best Practices Construction LawSocial media has become a powerful tool for small to medium-sized construction companies to generate leads for both residential and commercial projects. With over 3 billion people using social media worldwide, there is a huge opportunity for construction companies to reach potential customers and promote their services.
Following are some tips for contractors to use social media to generate leads and improve their revenue targets in 2023.
Firstly, it is important to choose the right social media platforms. Different social media platforms have different user demographics and can be more effective for certain types of projects. For example, Facebook and Instagram are popular platforms for residential projects, while LinkedIn is more effective for commercial projects. By understanding the target audience and selecting the right social media platforms, small construction companies can improve the effectiveness of their social media marketing efforts.
Read the court decisionRead the full story...Reprinted courtesy of
Matthew DeVries, Burr & Forman LLPMr. DeVries may be contacted at
mdevries@burr.com
Toolbox Talk Series Recap – Arbitration Motion Practice
August 07, 2023 —
Michael Zehner - The Dispute ResolverIn the June 22, 2023 edition of the Toolbox Talk Series,
Adrian Bastianelli, Peckar & Abramson, P.C., and
Brian Cashmere, Williams Mullen, moderated by Jennifer Millender of the American Arbitration Association (“AAA”), discussed motion practice in arbitration. Specifically, they offered advice on how to choose the right issue for a motion, how to get approval for a motion, how to write the motion, and how to get the arbitrator to grant it. They also discussed the pros and cons of motion writing in arbitration settings.
1. How to choose the “right issue” for a motion in arbitration
The panel discussed what type of issues can, or should, be brought up in a motion in arbitration. Cashmere stated that a clear and concise issue is best for this type of review. For example, statute of limitations, notice, or contract interpretation issues may make great summary judgment or partial summary judgment motions. Essentially, an issue that the arbitrator may resolve via primarily a question of law is more likely to succeed. Bastianelli warned against submitting just any “available” motion, as the practice may turn the arbitrator against you. Both panelists mentioned the need to consider strategy before filing a motion—ask, “how will filing this motion help or hurt reachingArbi final resolution.” Cashmere noted that sometimes the threat of bringing the issue to a hearing can put pressure on the adverse party in a way that is favorable to your client’s goals; possibly even more so than actually submitting the issue.
Read the court decisionRead the full story...Reprinted courtesy of
Michael Zehner, BBG Construction LawMr. Zehner may be contacted at
mzehner@bbglaw.com
Additional Dismissals of COVID Business Interruption, Civil Authority Claims
December 29, 2020 —
Tred R. Eyerly - Insurance Law HawaiiAmong the recent decisions dismissing complaints for business interruption and civil authority coverage due to closures caused by COVID-19 are Pappy's Barber Shops, Inc. v. Farmers Group, Inc., 2020 U.S. Dist. LEXIS 166808 (S.D. Calif. Sept. 11, 2020) and Sandy Point Dental v. Cincinnati Insurance Co., 2020 U.S. Dist. LEXIS 171979 (E.D. Ill. Sept. 21, 2020). The difficulty in proving "direct physical loss" was the downfall of both cases.
In Pappy's, claims were made for business income losses insured as a result of local and state closure orders. The policy required "direct physical loss of or damage to property at the described premises." Plaintiffs argued that "direct physical loss of" did not require a tangible damage or alteration to property and that the loss of the ability to continue operating their businesses as a result of the government orders met this requirement.
The court relied upon a prior decision, 10E, LLC v. Travelers Indem. Co. of Connecticut, 2020 U.S. Dist. LEXIS 165252 (C.D. Calif. Sept. 2, 2020) [post here], where the court noted that under California law, losses from inability to use property did not amount to "direct physical loss" within the meaning of the policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Accounting for Payments on Projects Became Even More Crucial This Year
September 21, 2020 —
Christopher G. Hill - Construction Law MusingsI discussed
several of the statutory changes affecting the construction industry here at Construction Law Musings in the run-up to July 1, 2020. One of those changes, an amendment to
Virginia Code Section 43-13, may add another arrow to the collection quiver of subcontractors and suppliers. As part of the previously-linked rundown, I highlighted one of the big additions in 2020, namely the amendment making those pesky clauses that let those up the payment chain from you hold money on “this or any other project” void as against public policy.
The other big addition to 43-13 is the change that adds a possible civil cause of action for downstream and unpaid subcontractors and suppliers in the event that funds paid to a general contractor or subcontractor are not first used to pay their downstream contractors and suppliers. Prior to July 1, 2020, this statute provided criminal penalties for such behavior but did not contain the possibility of a civil penalty. The operative language for the change is as follows:
The use by any such contractor or subcontractor or any officer, director, or employee of such contractor or subcontractor of any moneys paid under the contract before paying all amounts due or to become due for labor performed or material furnished for such building or structure for any other purpose than paying such amounts due on the project shall be prima facie evidence of intent to defraud. Any breach or violation of this section may give rise to a civil cause of action for a party in contract with the general contractor or subcontractor, as appropriate; however, this right does not affect a contractor’s or subcontractor’s right to withhold payment for failure to properly perform labor or furnish materials on the project.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Seattle Independent Contractor Ordinance – Pitfalls for Unwary Construction Professionals
October 09, 2023 —
Travis Colburn - Ahlers Cressman & SleightChapter 14.34 of the Seattle Municipal Code is a relatively new ordinance that can affect the parties to a construction contract for work performed within the City of Seattle’s city limits. The Independent Contractor Protection Ordinance (“ICPO”) was enacted to provide self-employed persons, or entities composed of not more than one person, regardless of corporate form, recourse for timely payment for work performed. The ICPO applies to contracts of $600[i] or more between an independent contractor and a hiring entity where the work, in whole or in part, is known to be performed within the City of Seattle’s city limits.[ii] The ICPO cannot be waived by parties to a contract.[iii]
Historically, the primary legal recourse for non-payment or late payment for work performed under a contract involves an expensive breach of contract action, and one reason the ICPO was enacted was to give greater protection to a growing number of Washington independent contractors who report problems with timely and accurate payment.
The ICPO affects “hiring entities” or any individual, partnership, association, corporation, business trust, or any entity, person or group of persons, or a successor thereof, that hires independent contractors to provide services within the scope of a hiring entity’s business or commercial activities. In the construction context, most general contractors, subcontractors, design professionals, and design consultants should be aware of this ordinance, as well as certain owners[iv] and development-side entities.
Read the court decisionRead the full story...Reprinted courtesy of
Travis Colburn, Ahlers Cressman & SleightMr. Colburn may be contacted at