Beware of Statutory Limits on Change Orders
February 18, 2015 —
Craig Martin – Construction Contractor AdvisorWhile change orders are always part of construction projects, it’s important to know whether a public agency is limited on how much it can increase the scope of the work through change orders. A contractor in Virginia found out the hard way that the state agency did not have the authority to increase the scope of the project and thus the contractor could not collect for the extra work.
In Carnell Construction Corp. v. Danville Redevelopment & Housing Authority, the contractor was hired by the housing authority to prepare a site for construction. The project did not go well and both sides blamed the other for delays and increased costs. After being removed from the project, the contractor sued the housing authority for, among other things, breach of contract. The jury awarded the contractor a total of $915,000 for the housing authority’s failure to pay for extra work and improper removal.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Discussing Parametric Design with Shajay Bhooshan of Zaha Hadid Architects
May 10, 2017 —
Aarni Heiskanen - AEC Businessobotics, 3D printing, and digital fabrication—these evolving technologies are changing how we design and construct. Looking into the future can surprisingly cause us to rediscover history, as I learned when discussing parametric design with Shajay Bhooshan.
During the AEC Hackathon Munich in April 2017, I became acquainted with Shajay Bhooshan, associate at Zaha Hadid Architects. Shajay showed me designs that were intriguingly reminiscent of natural forms but completely modern in expression. He explained how these lightweight structures had been digitally designed and constructed with minimal use of material. One of the examples he shared was a large shell structure that consisted of aluminium elements that could be assembled and dismantled easily.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
info@aepartners.fi
Reinsurer Must Reimburse Health Care Organization for Settlement Costs
June 17, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe Indiana Supreme Court reversed summary judgment issued to reinsurer Continental Casualty Company (CNA) and determined it must reimburse the insured for settlement costs under the E & O policy. Wellpoint, Inc., et al. v. National Union Fire Ins. Co. of Pittsburgh, PA, et al., 2015 Ind. LEXIS 316 (Ind. April 22, 2015).
Anthem, Inc. was a large managed health care organization. Anthem was its own primary and excess insurer for E&O liability. It had numerous excess reinsurers. Beginning in 1998, anthem was confronted by various lawsuits alleging it and other managed care organizations failed to pay claims in a full and timely manner, thereby breaching state and federal statutes. The various lawsuits alleged substantially the same wrongful conduct, namely that after promising to pay doctors in a timely manner for their services, Anthem sought to improperly deny, delay and diminish payments due.
The cases were consolidated into a federal multi-district litigation proceeding in the Southern District of Florida. Claims for breach of contract, unjust enrichment, and violations of state prompt pay statutes were dismissed or dropped. Anthem then settled the underlying litigation in July 2005 without admitting and instead denying any wrongdoing or liability. The settlement called for both cash payments and implementation of specific business practices consistent with requested injunctive relief.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Court Provides Guidance on ‘Pay-When-Paid’ Provisions in Construction Subcontracts
July 13, 2020 —
Ted R. Gropman & Cindy J. Lee - ConsensusDocsOn April 17, the California Court of Appeal decided Crosno Construction, Inc. v. Travelers Casualty & Surety Company of America,1 effectively narrowing the scope of enforceable “pay-when-paid” provisions in construction subcontracts to the extent the subcontractor seeks recovery against a general contractor’s payment bond surety. Although the Crosno case involved a public works project, the rationale and holding should apply with equal force to private works projects. Basing the bulk of its decision on the Wm. R. Clarke Corp. v. Safeco Insurance Co.2 case, the court found that an open-ended “pay-when-paid” provision in a subcontract is not enforceable against a subcontractor that seeks to recover on a public works payment bond claim. This article discusses the Crosno decision and the implications for contractors on both sides of the contract moving forward.
Brief Case Summary
In Crosno, general contractor Clark Bros., Inc. contracted with the North Edwards Water District (the District) to build an arsenic removal water treatment plant. Clark hired steel storage tank subcontractor Crosno Construction, Inc. to build and coat two steel reservoir tanks. Clark and Crosno’s subcontract included a “pay-when-paid” provision, which stated that Clark would pay Crosno within a “reasonable time” of receiving payments from the owner, but “in no event less than the time Contractor and Subcontractor require to pursue to conclusion their legal remedies against Owner or other responsible party to obtain payment.” After Crosno completed its work, a dispute arose between Clark and the District, and the District withheld payment from Clark (including the monies earmarked for Clark’s subcontractors). Clark sued the District for payment, and Crosno filed its own action against Travelers Casualty and Surety Company of America, the surety on Clark’s statutory public works payment bond, for recovery of the unpaid subcontract balance. Travelers rejected Crosno’s bond claim as premature, invoking the “pay-when-paid” subcontract language and pointing to Clark’s pending payment action against the District. The issue on appeal was whether the “pay-when-paid” provision in the subcontract blocked Crosno from recovering under the payment bond from Travelers while Clark’s lawsuit against the District was still pending.
Reprinted courtesy of
Ted R. Gropman, Pepper Hamilton LLP and
Cindy J. Lee, Pepper Hamilton LLP
Mr. Gropman may be contacted at ted.gropman@troutman.com
Ms. Lee may be contacted at cindy.lee@troutman.com
Read the court decisionRead the full story...Reprinted courtesy of
Pennsylvania Supreme Court Will Not Address Trigger for DEP Environmental Cleanup Action at This Time
August 14, 2018 —
Gregory Capps - White and Williams LLPOn July 18, 2018, in Pennsylvania Manufacturers’ Association Insurance Company v. Johnson Matthey, Inc., et al., No. 24 MAP 2017 (Pa. July 18, 2018), the Pennsylvania Supreme Court quashed the Pennsylvania Manufacturers’ Association’s (PMA) appeal seeking review of a ruling denying its motion for summary judgment for an order that coverage for the cleanup of a toxic waste site is limited to the policy in effect when property damage was first discovered. In short, the court found the lower court’s ruling only narrowed the dispute between the parties and is, therefore, interlocutory and not appealable at this time.
Read the court decisionRead the full story...Reprinted courtesy of
Gregory Capps, White & Williams LLPMr. Capps may be contacted at
cappsg@whiteandwilliams.com
Presenting a “Total Time” Delay Claim Is Not Sufficient
September 12, 2022 —
David Adelstein - Florida Construction Legal UpdatesWhen presenting a delay-type of claim on a construction project, a claimant MUST be in a position to properly PROVE the claim. Trying to present a delay claim loosey-goosey is not a recipe for success. In fact, it can be a recipe for an easy loss. This is not what you want. To combat this, make sure you engage a delay expert that understands delay methodologies and how to calculate delay and do NOT present a total time claim. Presenting a delay claim using a total time approach, discussed below, makes it too easy to attack the flaws and credibility of the approach. Per the discussion of the case below, a total time claim with a contractor that used its project manager, versus a delay expert, to support its claim turned the contractor’s claim into a loss.
In French Construction, LLC v. Department of Veteran Affairs, 2022 WL 3134507, CBCA 6490 (CBCA 2022), a contractor submitted a delay claim to the government for almost $400,000. The contractor was hired to construct a two-story corridor to connect hospital buildings. The contractor was required to be complete within 365 days. It was not. The contractor was seeking 419 days of delay from the government. The contractor’s “delay expert” was its project manager who compared the contractor’s as-planned schedule to an as-built schedule he prepared for the claim.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
There is No Presumptive Resumption!
January 21, 2025 —
Daniel Lund III - LexologyA Louisiana school board filed suit in court in 2018 on a construction project but was rebuffed based upon arguments by the general contractor and surety defendants. Those defendants asserted that the court filings were premature, based upon an arbitration clause in the general contract. The trial court agreed and stayed the litigation, “pending completion of arbitration.”
Arbitration was never filed. Interestingly, within the arbitration clause, the following language existed: “For statute of limitations purposes, receipt of written demand for arbitration shall constitute the institution of legal or equitable proceedings based upon the Claim.”
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
The ABCs of PFAS: What You Need to Know About Liabilities for the “Forever Chemical”
February 22, 2021 —
Robert F. Walsh, Gregory S. Capps & R. Victoria Fuller - Complex Insurance Coverage ReporterThis article is based on a presentation the authors made at White and Williams LLP’s Virtual Coverage College® on October 22, 2020. Every year, hundreds of insurance professionals come to Philadelphia—this year via our online platform—to participate in a full day of lectures and interactive presentations by White and Williams lawyers and guest panelists about the latest issues and challenges involved in claim handling and insurance litigation. Visit coveragecollege.com for more information and stay tuned for Coverage College® 2021.
Perfluoroalkyl and polyfluoroalkyl substances, commonly referred to as PFAS or PFOS, have been a key ingredient in numerous industrial and consumer products for decades. These man-made chemicals are prevalent and are also known for their longevity in the environment. More recently, PFAS have been the focus of thousands of lawsuits alleging personal injury and property damage. Some insurers have already questioned whether PFAS could rival asbestos in scope and bottom-line impacts. It is a legacy that confronts manufacturers and other defendants and insurers today.
This article provides a primer on PFAS, including the current regulatory framework and litigation landscape. We also identify some key emerging coverage issues insurers should be aware of when dealing with PFAS claims under liability and first-party property policies.
Reprinted courtesy of
Robert F. Walsh, White and Williams LLP and
Gregory S. Capps, White and Williams LLP
Mr. Walsh may be contacted at walshr@whiteandwilliams.com
Mr. Capps may be contacted at cappsg@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of