Enforceability Of Subcontract “Pay-When-Paid” Provisions – An Important Update
June 15, 2020 —
Patrick McNamara - Porter Law GroupA California Court of Appeals opinion published earlier this month brings a change to payment bond claims brought by unpaid subcontractors and suppliers. The decision (Crosno Construction, Inc. v. Travelers Casualty and Surety Company of America) places limitations on a payment bond surety’s ability to rely on subcontract “pay-when-paid” language, stating that a payment provision typically found in subcontracts is contrary to the “reasonable time” statutory requirement and will not be enforced. This represents a major shift in California construction payment bond claim rights.
Plaintiff Crosno Construction, Inc. (“Crosno) was a subcontractor to general contractor Clark Brothers (“Clark”), who was principal on a public works payment bond issued by Travelers. The owner was a public agency district (“District.”) Crosno had completed most of its subcontract work when a dispute between District and Clark arose, causing the project to stop. Crosno then sought payment through a payment bond claim against Travelers. Travelers denied the claim, relying on the subcontract’s payment provisions and asserting the defense that it had no obligation to pay on the bond claim because the litigation between Clark and the District had not yet reached its conclusion.
Subcontract. The subcontract between Clark and Crosno contained a “pay-when-paid” provision stating that Clark would pay Crosno within a reasonable time after receiving payment from the District. In defining “a reasonable time,” the subcontract language provided that the time for payment “in no event shall be less than the time [Clark] and [Crosno] require to pursue to conclusion their legal remedies against [District] or other responsible party to obtain payment.”
Read the court decisionRead the full story...Reprinted courtesy of
Patrick McNamara, Porter Law GroupMr. McNamara may be contacted at
pmcnamara@porterlaw.com
Designer of World’s Tallest Building Wants to Turn Skyscrapers Into Batteries
July 31, 2024 —
Will Wade - BloombergThe architecture firm that designed the world’s tallest building is considering ways to build skyscrapers that can store energy using gravity.
Skidmore, Owings & Merrill LLP has developed a series of prototype designs that use electric motors to elevate massive blocks, creating potential energy that can be converted into electricity when the blocks are lowered. The designs are based on technology developed by partner Energy Vault Holdings Inc. as an alternative to lithium-ion batteries and other types of chemical cells. They are seeking developer partners interested in offsetting greenhouse gas pollution from buildings, which the United Nations estimates are responsible for almost 40% of global emissions.
The concept is similar to widely used pumped hydroelectric plants. Energy Vault completed its first major project this month near Shanghai, a stand-alone storage system that can supply as much as 25 megawatts of power for four hours. Other companies are testing new types of gravity storage systems, including ones using abandoned oil wells and mines.
Read the court decisionRead the full story...Reprinted courtesy of
Will Wade, Bloomberg
California Fire Lawyers File Suit Against PG&E on Behalf of More Than 50 Wildfire Victims
November 15, 2017 —
David Suggs – Bert L. Howe & Associates, Inc.Digital Journal reports that the California fire lawyers are comprised of four law firms, Baron & Budd, Singleton Law Firm, Dixon Diab & Chambers LLP, and Thornes Bartolotta McGuire. These firms filed suit against PG&E (Pacific Gas and Electric Company) on October 27th alleging that the brutal wildfires that swept through Northern California started when electrical infrastructure encountered vegetation.
According to Digital Journal, more than 50 plaintiffs are being represented in this case who endured damages including “wrongful death, personal injuries, damage to or destruction of property, loss of cherished possessions, medical bills, evacuation expenses and lost wages.”
John Fiske, an attorney at Baron & Budd stated, “through our team’s investigation to date, we believe that PG&E may have played a role in causing these fires.” Holding PG&E accountable for the 40 people killed, 8,400 structures destroyed, and 210,000 acres burned is their goal.
Read the court decisionRead the full story...Reprinted courtesy of
Georgia Local Government Drainage Liability: Nuisance and Trespass
November 29, 2021 —
David R. Cook Jr. - Autry, Hall & Cook, LLPA long-running dispute between a landowner and a municipality has escalated to the Georgia Court of Appeals and in the federal court for the Northern District of Georgia.[1] The municipality maintained a stormwater system that discharged on property uphill from the landowner’s property. The uphill property was used as an illegal dump, and debris washed downhill from the dump to the landowner’s property. The debris clogged the landowner’s surface water drainage system, which caused flooding of the property and a building.
State Case
The landowner sued for trespass, nuisance, takings, and inverse condemnation. While the other claims were barred by the four-year statute of limitations, the court addressed the plaintiff-landowner’s claim for continuing nuisance.
Municipalities may be liable when they negligently construct or maintain a sewer or drainage system that causes repeated flooding of property, such that it results in a continuing, abatable nuisance.[2] For a municipality to be liable for maintenance of a nuisance:
the municipality must be chargeable with performing a continuous or regularly repetitious act, or creating a continuous or regularly repetitious condition, which causes the hurt, inconvenience or injury; the municipality must have knowledge or be chargeable with notice of the dangerous condition; and, if the municipality did not perform an act creating the dangerous condition, . . . the failure of the municipality to rectify the dangerous condition must be in violation of a duty to act.[3]
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook Jr., Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
White House Seeks $310M To Fix Critical San Diego Wastewater Plant
December 04, 2023 —
James Leggate - Engineering News-RecordThe Biden administration’s $55.9-billion
supplemental funding request to Congress for disaster response and other issues includes $310 million for a project to repair and expand the ailing South Bay International Wastewater Treatment Plant in San Diego, Calif. The plant is part of a
repeatedly overwhelmed wastewater treatment system on the U.S.-Mexico border that has allowed untreated sewage flows to foul area beaches.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
LAX Construction Defect Suit May Run into Statute of Limitations
December 30, 2013 —
CDJ STAFFCurrent arguments over the claims made by LAX that Runway 25L was built in a defective manner by Tutor-Saliba/O&G Industries are hinging over whether the airport knew the runway was defective less than four years after the construction was completed. The runway was built almost five years ago, and Tutor-Saliba is claiming that Los Angeles World Airports has delayed too long in making a construction defect complaint. Tutor-Saliba is not conceding that the runway is defective, only that if it were, the airport would have known it earlier.
Los Angeles World Airports, which operates LAX, is not commenting on the matter, but Robert Span, an aviation attorney at Steinbrecher & Span, told the Daily Breeze that while “there is a four year statute of limitations for dealing with construction defects, but that’s for what they called patent defects,” and that “there’s a 10-year statute of limitations for construction projects where the defect that is alleged is called latent — something that would not be readily apparent.”
Tim Pierce, a construction attorney at K&L Gates LLP described it as “a common defense,” though he said it is “raised in most cases and only works in some.”
Read the court decisionRead the full story...Reprinted courtesy of
The ARC and The Covenants
May 30, 2018 —
Christopher G. Hill - Construction Law MusingsFor this week’s Guest Post Friday here at Musings, we welcome back Mike Collignon. Mike is a co-founder of the Green Builder Coalition. The Green Builder® Coalition amplifies the voice of green builders and professionals to drive advocacy and education for more sustainable building practices.
As we start to see signs of a housing recovery, slow as it may be, I feel the industry is in a great position. All the effort put in by so many to improve our energy codes, green building programs & rating systems will finally be able to bear fruit. We can start to build homes that are much more environmentally responsible. Sure, we can have a lengthy debate about implementation and adoption rates, but you’ve got to walk before you can run. Unfortunately, I can see that progress getting shackled by an unexpected impediment: the architectural review committee (ARC; sometimes called “architectural committee” or “architectural control authority”) and the covenants of a homeowners’ association.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
How To Lock Disputes Out Of Your Project In Construction
July 22, 2019 —
Anastasios Koutsogiannis – LetsBuildDisputes are seen as one of the main threats for the successful completion of a project in construction. There is a plethora of factors which could lead to a construction dispute (e.g. contracts, behavior, environment) but, strangely enough, the industry seems to invest more attention on the resolution of a conflict instead of its prevention.
Thanks to the progress that digital technologies have witnessed during the last few years, there is a good chance that things in construction will change for the better soon. The ability to exchange crucial updates in real time, while keeping a detailed record of everything that happens on the field adds an extra level of protection to your project and ensures that all agents are on the same page.
In an effort to shed some light on the issue of construction disputes, we present below four tips that could help your team to lock conflicts out of your project:
1. Standardize your processes
Before you kickstart your project, it is of paramount importance that you standardize all your systems and processes. In that way, you will be able to add extra clarity to your workflow and eliminate misunderstandings.
Once you have achieved that, you can replicate the same process to your future projects. The more you manage to repeat the same project structure the better your team will become in completing their tasks without ending up in any kind of conflict.
In that sense, standardization could be a long-term investment for your organization.
2. Go digital
As soon as your processes are defined, it is time for the digital journey to begin. Finding the right tool for your project will result in a streamlined construction process where all the members of the team are on the same page without any room for costly mistakes or disagreements.
Furthermore, with the help of digital solutions it becomes easier for project managers to measure the performance on site and monitor the completion of the set benchmarks. Like that, all payments will be on time and the program of the project will reflect reality.
3. Be extra careful with the contracts
A poorly-written contract can have a big impact on the effort to lock disputes out of your construction project. While putting together a new contract, you should always make sure that you have taken into account all the different scenarios for your project.
Either that is a delay due to weather conditions or an accident on site everything should be described in detail in the contracts and be well understood by those in charge.
In any other case, things can get a bit risky and a costly dispute might wait to happen.
4. Hold regular meetings with all stakeholders
Last but certainly not least, meet regularly with all project stakeholders. The frequent contact with the different members of your team will allow you to discuss and resolve any problematic situations before they grow out of proportion.
What is more, regular meetings will help both your field teams and the people in the office to remain aligned and will eliminate the possibility of having people working on outdated versions of the program.
Of course, these meetings don’t need to be time-consuming or even in person. With the help of technology, you can keep these meetings short and to the point. In that manner, everybody involved will be able to get the most out of them.
Final word
All in all, it becomes clear that locking disputes out of your project in construction requires continuous work and a carefully-elaborated plan. Thankfully, the emergence and progress of digital solutions have made this process much easier contributing significantly to the development of the industry far from disputes and project misunderstandings.
About the author: Anastasios Koutsogiannis is Content Marketing Manager at LetsBuild.
Read the court decisionRead the full story...Reprinted courtesy of
Anastasios Koutsogiannis, LetsBuild