Builder Must Respond To Homeowner’s Notice Of Claim Within 14 Days Even If Construction Defect Claim Is Not Alleged With The “Reasonable Detail”
June 05, 2017 —
Richard H. Glucksman & David A. Napper - CGDRB News & PublicationsOn February 10, 2017, California’s Fourth District Court of Appeal held that if a builder fails to acknowledge receipt of a homeowner’s Notice of Claim within 14 days, as required by the Right to Repair Act (“SB800”), specifically California Civil Code §913, the homeowner is released from the requirements of SB800 and may proceed with the filing of a lawsuit.
In Blanchette v. Superior Court, Blanchette owned 1 of 28 homes constructed by GHA Enterprises, Inc. (“GHA”). On February 2, 2016, Blanchette served GHA with notice of a claim, setting forth the alleged defects in all 28 homes. On February 23, 2016, GHA responded that the construction defects were not alleged with sufficient “reasonable detail” as required by Civil Code §910. In response, Blanchette asserted that GHA’s response was untimely and thus excused him and the other homeowners from any obligations under SB800. The trial court found for the builder, GHA, holding that Blanchette’s Notice of Claim lacked detail sufficient to trigger GHA’s obligations under SB800. Blanchette appealed the ruling.
Reprinted courtesy of
Richard H. Glucksman, Chapman Glucksman Dean Roeb & Barger and
David A. Napper, Chapman Glucksman Dean Roeb & Barger
Mr. Glucksman may be contacted at rglucksman@cgdrblaw.com
Mr. Napper may be contacted at dnapper@cgdrblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Florida’s Statute of Limitations / Repose for Actions Founded on Construction Improvement Modified
April 25, 2023 —
David Adelstein - Florida Construction Legal UpdatesOn April 13, 2023, Florida’s all-important four-year statute of limitations–Florida Statute s. 95.11(3)(c)–relating to actions founded on construction of an improvement of real property was modified. This is a key statute of limitations for ALL construction practitioners because it also includes the statute of repose for latent construction defects.
At the bottom of this posting is the current version fo s. 95.11(3)(c) with the underlined section being recent additions. (They hyperlink above will identify the deletions and additions.) Important things to note:
- Statute of Repose. The statute of repose has been reduced from 10 years to 7 years. There is now an objective date for when the repose period commences: “within 7 years after the date the authority having jurisdiction issues a temporary certificate of occupancy, a certificate of occupancy, or a certificate of completion, or the date of abandonment of construction if not completed, whichever date is earliest.”
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Gillotti v. Stewart (2017) 2017 WL 1488711 Rejects Liberty Mutual, Holding Once Again that the Right to Repair Act is the Exclusive Remedy for Construction Defect Claims
November 21, 2017 —
Richard H. Glucksman, Esq. & Chelsea L. Zwart, Esq. - Chapman Glucksman Dean Roeb & Barger BulletinOriginally published by CDJ on June 5, 2017
Background
In Gillotti v. Stewart (April 26, 2017) 2017 WL 1488711, which was ordered to be published on May 18, 2017, the defendant grading subcontractor added soil over tree roots to level the driveway on the plaintiff homeowner’s sloped lot. The homeowner sued the grading subcontractor under the California Right to Repair Act (Civil Code §§ 895, et seq.) claiming that the subcontractor’s work damaged the trees.
After the jury found the subcontractor was not negligent, the trial court entered judgment in favor of the subcontractor. The homeowner appealed, arguing that the trial court improperly construed the Right to Repair Act as barring a common law negligence theory against the subcontractor and erred in failing to follow Liberty Mutual Insurance Co. v. Brookfield Crystal Cove LLC (2013) 219 Cal.App.4th 98. The Third District Court of Appeal disagreed and affirmed the trial court’s judgment in favor of the subcontractor.
Impact
This is the second time the Third District Court of Appeal has held that Liberty Mutual (discussed below) was wrongly decided and held that the Right to Repair Act is the exclusive remedy for construction defect claims. The decision follows its holding in Elliott Homes, Inc. v. Superior Court (Hicks) (2016) 6 Cal.App.5th 333, in which the Court of Appeal held that the Right to Repair Act’s pre-litigation procedures apply when homeowners plead construction defect claims based on common law causes of action, as opposed to violations of the building standards set forth in the Right to Repair Act. Elliott is currently on hold at the California Supreme Court, pending the decision in McMillin Albany, LLC v. Superior Court (2015) 239 Cal.App.4th 1132, wherein Liberty Mutual was rejected for the first time by the Fifth District. CGDRB continues to follow developments regarding the much anticipated McMillin decision closely, as well as all related matters.
Reprinted courtesy of
Richard H. Glucksman, Chapman Glucksman Dean Roeb & Barger and
Chelsea L. Zwart, Chapman Glucksman Dean Roeb & Barger
Mr. Glucksman may be contacted at rglucksman@cgdrblaw.com
Ms. Zwart may be contacted at czwart@cgdrblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Colorado Court of Appeals Decides the Triple Crown Case
January 17, 2014 —
Berkeley W. Mann, Jr. – Higgins, Hopkins, McLain & Roswell, LLCIn an earlier blog post, I discussed the case of Triple Crown Observatory Village Assn., Inc. v. Village Homes of Colorado, Inc., et al (2013 WL 5761028) because it presented the rare case where the Colorado Court of Appeals accepted an interlocutory appeal. Notably, the interlocutory appeal resulted from dismissal of the HOA case in which the trial judge directed the parties to arbitrate in lieu of a jury trial, under the declaration of covenants, conditions, and restrictions that governed the community. The Court of Appeals decided the case on its merits on November 7, 2013, and its decision can be found at 2013 WL 6502659. (Note: this presently unpublished opinion may be subject to further appeal to the Colorado Supreme Court.)
The case resulted from an attempt by the HOA’s counsel to amend the mandatory arbitration provisions of the declarations before it filed suit. This amendment process took the form of soliciting signature votes of homeowners on a revocation resolution to repeal the specific provisions of the declarations that provided mandatory, binding arbitration as the sole remedy for disputes between the HOA and the developer and/or general contractor. The declarations required that 67% of homeowners vote in favor of amendment in order to modify the declarations.
Read the court decisionRead the full story...Reprinted courtesy of
Berkeley W. Mann, Jr., Higgins, Hopkins, McLain & Roswell, LLCMr. Mann may be reached at
mann@hhmrlaw.com
Quick Note: Aim to Avoid a Stay to your Miller Act Payment Bond Claim
February 23, 2017 —
David Adelstein – Florida Construction Legal UpdatesStrategy is important. This is especially true if you are trying to avoid arbitration. In a recent federal district court case, a subcontractor sued the prime contractor and the Miller Act payment bond surety. The subcontractor, however, had an arbitration provision in its subcontract with the prime contractor. The prime contractor moved to compel arbitration pursuant to the subcontract and moved to stay the subcontractor’s Miller Act payment bond claim. The last thing, and I mean the last thing, the subcontractor wanted to do was to stay its claim against the Miller Act payment bond. However, the district court compelled the subcontractor’s claim against the prime contractor to arbitration and stayed the subcontractor’s Miller Act payment bond claim pending the outcome of the arbitration. See U.S. v. International Fidelity Ins. Co., 2017 WL 495614 (S.D.Al. 2017). This is not what the subcontractor wanted.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Construction Law Client Alert: California Is One Step Closer to Prohibiting Type I Indemnity Agreements In Private Commercial Projects
June 15, 2011 —
Haight Brown & Bonesteel, LLPOn June 1, 2011 by majority vote, the California Senate passed Senate Bill 474, which would amend Civil Code section 2782, and add Civil Code section 2782.05. The passage of this new law is a critical development for real estate developers, general contractors and subcontractors because it will affect how these projects are insured and how disputes are resolved.
Civil Code section 2782 was amended in 2007 to prohibit Type I indemnity agreements for residential projects only. Since 2007, various trade associations and labor unions have lobbied to expand those very same restrictions to other projects. These new provisions apply to contracts, entered into after January 1, 2013, that are not for residential projects, and that are not executed by a public entity. The revisions provide that any provision in a contract purporting to indemnify, hold harmless, and defend another for their negligence or other fault is against public policy and void. These provisions cannot be waived.
A provision in a contract requiring additional insured coverage is also void and unenforceable to the extent it would be prohibited under the new law. Moreover, the new law does not apply to wrap-up insurance policies or programs, or a cause of action for breach of contract or warranty that exists independently of the indemnity obligation.
The practical impact of this new law is that greater participation in wrap-up insurance programs will likely result. While many wrap-up programs suffer from problems such as insufficient limits, and disputes about funding the self-insured retention, the incentive for the developer or general contractor to utilize wrap-up insurance will be greater than ever before because they will no longer be able to spread the risk of the litigation to the trades and the trade carriers.
Read the full story…
Reprinted courtesy of Steve Cvitanovic of Haight Brown & Bonesteel, LLP.
Read the court decisionRead the full story...Reprinted courtesy of
Wall Enclosing Georgia Neighborhood Built for Walking Dead TV Show
July 16, 2014 —
Beverley BevenFlorez-CDJ STAFFThe studio for AMC’s Walking Dead television show “is constructing a 15-foot-high wall around a neighborhood in the small town of Senoia,” located outside of Atlanta, Georgia to create a set for new episodes, the Sacramento Bee reported.
The town’s mayor, Larry Owens, stated that the city council approved plans for the wall, which will enclose “about four brownstone town homes plus about a half-dozen additional residences.” About 30 people currently live in the area affected. The show will use the area “as a safe haven from zombies,” which the show refers to as “walkers.”
Read the court decisionRead the full story...Reprinted courtesy of
Court Finds That SIR Requirements are Not Incorporated into High Level Excess Policies and That Excess Insurers’ Payment of Defense Costs is Not Conditioned on Actual Liability
April 22, 2019 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Deere & Co. v. Allstate Ins. Co. (No. A145170, filed 2/25/19), a California appeals court held that the insured was not required to pay additional self-insured retentions (SIRs) in order to trigger higher level excess coverage because the retained limits applicable to the first layer of coverage did not also apply to the higher-layer excess policies.
In Deere, the insured was sued for injuries from alleged exposure to asbestos-containing assemblies used in Deere machines. In a declaratory relief action against its umbrella and excess insurers, the case was tried on: (1) whether the higher-layer excess policies were triggered once the first-layer excess policy limits, which were subject to an SIR paid by Deere, had been exhausted; and (2) whether the insurers’ indemnity obligation extended to Deere’s defense costs incurred in asbestos claims that had been dismissed. The trial court found in favor of the insurers, concluding that the retained limits in the first layer of coverage also applied to the higher-layer excess, which was not triggered until Deere paid additional SIRs. The court also concluded that the insurers were not obligated to pay defense costs when underlying cases were dismissed without payment to a claimant either by judgment or settlement.
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP Read the court decisionRead the full story...Reprinted courtesy of