Do Not File a Miller Act Payment Bond Lawsuit After the One-Year Statute of Limitations
November 01, 2022 —
David Adelstein - Florida Construction Legal UpdatesUnder the Miller Act, a claim against a Miller Act payment bond must be commenced “no later than one year after the date on which the last of the labor was performed or material was supplied by the person bringing the action.” 40 U.S.C. s. 3133(b)(4). Stated another way, a claimant must file its lawsuit against the Miller Act payment bond within one year from its final furnishing on the project.
Filing a lawsuit too late, i.e., outside of the one-year statute of limitations, will be fatal to a Miller Act payment bond claim. This was the outcome in Diamond Services Corp. v. Travelers Casualty & Surety Company of America, 2022 WL 4990416 (5th Cir. 2022) where a claimant filed a Miller Act payment bond lawsuit four days late. That four days proved to be fatal to its Miller Act payment bond claim and lawsuit. Do not let this happen to you!
In Diamond Services Corp., the claimant submitted a claim to the Miller Act payment bond surety. The surety issued a claim form to the claimant that requested additional information. The claimant returned the surety’s claim form. The surety denied the claim a year and a couple of days after the claimant’s final furnishing. The claimant immediately filed its payment bond lawsuit four days after the year expired. The claimant argued that the surety should be equitably estopped from asserting the statute of limitations in light of the surety’s letter requesting additional information. (The claimant was basically arguing that the statute of limitations should be equitably tolled.) The trial court dismissed the Miller Act payment bond claim finding it was barred by the one-year statute of limitations and that equitable estoppel did not apply.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Texas Federal Court Upholds Professional Services Exclusion to Preclude Duty to Defend
March 16, 2020 —
Jeremy S. Macklin - Traub Lieberman Insurance Law BlogIn Project Surveillance, Inc. v. The Travelers Indemnity Company, No. 4:19-CV-03324, 2020 WL 292247 (S.D. Tex. Jan. 21, 2020), a Texas federal court held that a professional services exclusion in a commercial general liability policy precluded Travelers’ duty to defend its insured.
The underlying lawsuit was a wrongful death action brought by the family of a worker killed on a construction site. Project Surveillance was present at the construction site “to provide safety supervision or other services.” The underlying lawsuit alleged that Project Surveillance negligently failed to inspect or adequately inspect the project and failed to warn or adequately warn the decedent of a dangerous condition. The underlying lawsuit also alleged that Project Surveillance was negligent in failing to stop work.
At the time of the incident, Project Surveillance had commercial general liability insurance through Travelers and professional liability insurance through RLI. RLI agreed to defend Project Surveillance in the underlying lawsuit. Travelers, however, denied owing a duty to defend or indemnify based on an exclusion for “bodily injury” arising out of the rendering or failure to render any “professional service.” The Traveler policy defined the term “professional services” to mean any service requiring specialized skill or training, including “failure to prepare [. . .] any warning,” “supervision,” “inspection,” “control,” “surveying activity or service,” “job site safety,” “construction administration,” and “monitoring [. . .] necessary to perform and of [those] services.”
Read the court decisionRead the full story...Reprinted courtesy of
Jeremy S. Macklin, Traub LiebermanMr. Macklin may be contacted at
jmacklin@tlsslaw.com
Drone Operation in a Construction Zone
August 17, 2020 —
Mark R. Berry & Freddy X. Muñoz - Peckar & AbramsonThe potential uses of unmanned aircraft systems (UAS) in the construction industry continue to expand as new technologies enter the market and construction companies realize UAS can perform unique tasks at tremendous cost savings. The full technological capabilities of UAS are, however, limited by law for public safety reasons. UAS share airspace with traditional passenger, military and cargo aircraft, and are potential hazards for humans below. The risk of potential catastrophic collisions has led to a careful approach to the adoption of this technology.
All U.S. airspace is exclusively regulated by the Federal Aviation Administration (FAA), and therefore, most drone regulation originates from this agency. Many states and localities have also enacted additional limits on UAS operations, and many of these nonfederal regulations are presently on unsure footing after a federal court ruling in Singer v. Newton invalidated a local regulation that conflicted with FAA regulations.
What is clear is that all commercial UAS operations must comply with FAA regulations. Any drone operation conducted by any private company, even through use of an employee’s personal drone, would constitute commercial operation subject to regulation.
Reprinted courtesy of
Mark R. Berry, Peckar & Abramson and
Freddy X. Muñoz, Peckar & Abramson
Mr. Berry may be contacted at mberry@pecklaw.com
Mr. Muñoz may be contacted at fmunoz@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
FEMA, Congress Eye Pre-Disaster Funding, Projects
November 08, 2017 —
Pam Radtke Russell - Engineering News-RecordFederal Emergency Management Agency Administrator Brock Long wants to revamp the way federal disaster funds are distributed, putting a greater emphasis on building more-resilient structures and communities before disasters strike, Long told a House panel reviewing federal response to the recent slate of disasters.
Read the court decisionRead the full story...Reprinted courtesy of
Pam Radtke Russell, ENRMs. Russell may be contacted at
Russellp@bnpmedia.com
Continuing Breach Doctrine
May 28, 2024 —
David Adelstein - Florida Construction Legal UpdatesHave you ever heard of the “continuing breach” doctrine? Probably not. It is not a doctrine commonly discussed. It’s a doctrine used to try to argue around the statute of limitations.
In an older Southern District Court of Florida case, Allapattah Services, Inc. v. Exxon Corp., 188 F.R.Ed. 667, 679 (S.D.Fla. 1999), the court explained: “Under this [continuing breach] doctrine, a cause of action for breach of a contract does not begin to accrue upon the initial breach; rather, on contracts providing serial performance by the parties, accrual of a breach of contract cause of action commences upon the occurrence of the last breach or upon termination of the contract.”
Recently, this doctrine came up in an opinion by Florida’s Fifth District Court of Appeal. In Hernando County, Florida v. Hernando County Fair Association, Inc., 49 Fla.L.Weekly D947b (Fla. 5th DCA 2024), a plaintiff appealed the trial court’s dismissal with prejudice of its breach of contract claim based on the statute of limitations. The plaintiff claimed the defendant breached the contract by its failure to substantially redevelop property. The trial court dismissed based on the statute of limitations. However, the complaint alleged the defendant’s failure to comply “with numerous other intertwined, ongoing, and continuing contractual duties and obligations.” Hernando County, supra. The Fifth District reversed based on the continuing breach doctrine: “Where the nature of the contract is continuous, statutes of limitations do not typically begin to run until termination of the entire contract.” Id. quoting and citing Allapattah Servs., Inc.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Clearly Determining in Contract Who Determines Arbitrability of Dispute
April 26, 2021 —
David Adelstein - Florida Construction Legal UpdatesAs you know from prior postings: “Arbitration provisions are creatures of contract and must be construed ‘as a matter of contract interpretation.’ ” Fallang Family Limited Partnership v. Privcap Companies, LLC, 46 Fla.L.Weekly D639e (Fla. 4th DCA 2021) (citation omitted). Thus, if you prefer to arbitrate potential disputes, instead of litigating potential disputes, you want to include an arbitration provision in your contract. While there are positives and negatives to arbitration, no different than litigation, these positives and negatives should be considered during the contract negotiation process when dealing with the dispute resolution process in the contract.
Generally, under the law, the arbitrability of a dispute is determined by the court. However, this can be deferred to the arbitrator with clear and unmistakable language in the contract.
By way of example, the American Arbitration Association includes a rule that allows an arbitrator to rule on the arbitrability of the dispute, i.e., the claims asserted are subject to the governing arbitration provision in the contract. Recent law has suggested that if the objective is to authorize an American Arbitration Association arbitrator to make this determination, the contract clearly and unmistakably needs to state this intent and generally referring to the American Arbitration Association rules is not good enough. For this reason, I have included in arbitration provisions language that specifically states, “In the event of any dispute as to the arbitrability of any claim or dispute, the parties agree that an appointed arbitrator within the American Arbitration Association shall make this determination.” I have also included in arbitration provisions the converse so that if there is a dispute as to the arbitrability of a claim or dispute, the court, and not the arbitrator, will make this determination.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Balancing Risk and Reward: The Complexities of Stadium Construction Projects
April 15, 2024 —
Gregory A. Eichorn - Peckar & Abramson, P.C.From grand designs to opening day, stadium construction projects present a captivating blend of high-profile opportunities and significant challenges and risks. Navigating this complex landscape is not easy, but when managed properly, the potential rewards, both in terms of reputation and finances, can make it a gamble worth taking. While each stadium project is different, some of the more common risks include:
- Securing adequate labor, materials and equipment based on the size of the project;
- Logistical concerns regarding the concurrent performance of multiple trade scopes on a single site;
- Protection of work in place from weather due to the large footprint of the stadium project;
- Cash flow issues caused by protracted change order processing, conflicting and/or onerous payment requirements from project financing entities, and reimbursement of considerable monthly general condition costs; and
- Meeting the schedule requirements for the project.
Read the court decisionRead the full story...Reprinted courtesy of
Gregory A. Eichorn, Peckar & Abramson, P.C.Mr. Eichorn may be contacted at
geichorn@pecklaw.com
California Court of Appeal Holds That the Right to Repair Act Prohibits Class Actions Against Manufacturers of Products Completely Manufactured Offsite
February 06, 2019 —
Gus Sara - The Subrogation StrategistIn Kohler Co. v. Superior Court, 29 Cal. App. 5th 55 (2018), the Second District of the Court of Appeal of California considered whether the lower court properly allowed homeowners to bring class action claims under the Right to Repair Act (the Act) against a manufacturer of a plumbing fixture for alleged defects in the product. After an extensive analysis of the language of the Act, the court found that class action claims under the Act are not allowed if the product was completely manufactured offsite. Since the subject fixture was completely manufactured offsite, the Court of Appeal reversed the lower court’s decision. The court’s holding establishes that rights and remedies set forth in the Right to Repair Act are not available for class action claims alleging defects in products completely manufactured offsite.
In Kohler Co., homeowners instituted a class action against Kohler, the manufacturer of water pressure and temperature regulating valves that were installed into their homes during original construction. The class action was filed on behalf of all owners of residential dwellings in California in which these Kohler valves were installed as part of original construction. The complaint asserted, among other claims, a cause of action under the Act. Kohler filed a motion for anti-class certification on the ground that causes of actions under the Act cannot be certified as a class action. The trial court denied the motion with respect to the Act but certified its ruling for appellate review. Kohler filed a petition with the Court of Appeals, arguing that certain sections of the Act explicitly exclude class action claims under the Act.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and Williams LLPMr. Sara may be contacted at
sarag@whiteandwilliams.com