Approaches in the Absence of a Differing Site Conditions Clause
April 10, 2019 —
Parker A. Lewton - Smith CurrieA contractor who has encountered unforeseen conditions will typically rely on the contract’s differing site conditions clause as a means to recovery. Most construction contracts address those issues directly. In ConsensusDocs Standard Agreement and General Conditions between Owner and Constructor, the starting point is § 3.16.2. But what if the contract does not contain a differing site conditions clause? Or, what if the contract does contain such a clause, but the contractor failed to provide adequate notice or satisfy other conditions or requirements of the contract? When reliance on a differing site conditions clause is impractical, a contractor still may seek recovery in certain instances under one or more of the following legal theories: misrepresentation; fraud; duty to disclose; breach of implied warranty; and mutual mistake.
Misrepresentation
Misrepresentation occurs when an owner “misleads a contractor by a negligently untrue representation of fact[.]” John Massman Contracting Co. v. United States, 23 Cl. Ct. 24, 31 (1991) (citing Morrison–Knudsen Co. v. United States, 170 Ct. Cl. 712, 718–19, 345 F.2d 535, 539 (1965)). A contractor may be able to recover extra costs incurred, under a theory of misrepresentation, if it can show that (1) the owner made an erroneous representation, (2) the erroneous representation went to a material fact, (3) the contractor honestly and reasonably relied on that representation, and (4) the contractor’s reliance on the erroneous representation was to the contractor’s detriment. See T. Brown Constructors, Inc. v. Pena, 132 F.3d 724, 728–29 (Fed. Cir. 1997). These four requirements can be satisfied, for example, through the use of deposition testimony detailing the owner’s representations and the contractor’s reliance thereon. See, e.g., C & H Commercial Contractors, Inc. v. United States, 35 Fed. Cl. 246, 256–57 (1996).
Read the court decisionRead the full story...Reprinted courtesy of
Parker A. Lewton, Smith CurrieMr. Parker may be contacted at
palewton@smithcurrie.com
Thoughts on New Pay if Paid Legislation
March 28, 2022 —
Christopher G. Hill - Construction Law MusingsRecently, the Virginia General Assembly closed its session having passed legislation essentially banning “pay if paid” clauses in construction contracts, both public and private. Assuming that Governor Youngkin signs the bill into law on or before his deadline of April 11, 2022, the following new requirement will be grafted into any Virginia construction contract:
Such contract shall require such higher-tier contractor to pay such lower-tier subcontractor within the earlier of (i) 45 days of the satisfactory completion of the portion of the work for which the subcontractor has invoiced or (ii) seven days after receipt of amounts paid by the owner to the general contractor or by the higher-tier contractor to the lower-tier contractor for work performed by a subcontractor pursuant to the terms of the contract.
This is the main operative language (the 45-day payment requirement is also applied to project owners), but the legislation also imposes certain other notice duties upon both the owner and any higher-tier contractor on a construction project. Interestingly, the legislation does not include a provision making it only effective for those contracts entered into after its effective date. More on that later.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Unlocking the Potential of AI and Chat GBT in Construction Management
September 11, 2023 —
Matthew DeVries - Best Practices Construction LawThe construction industry is one of the most complex and challenging sectors. Projects can be highly demanding and require a significant amount of planning and coordination to complete successfully. However, with advancements in technology, specifically the use of artificial intelligence (AI) and chat GBT, the construction industry can experience a transformation in how it operates.
One of the significant challenges in construction projects is the management of data. Information is collected from various sources and needs to be organized and analyzed to make informed decisions. AI can play a significant role in data analysis by providing real-time insights into the project’s progress. This can help in predicting potential delays, identifying areas where cost savings can be made, and even improve safety measures.
Chat GBT, a natural language processing tool, can assist in project management by acting as a virtual assistant to construction managers. The software can be programmed to answer questions about the project, provide updates on the progress, and even suggest solutions to potential problems. This can help in reducing the workload of the project manager and allow them to focus on other critical tasks.
Read the court decisionRead the full story...Reprinted courtesy of
Matthew DeVries, Burr & Forman LLPMr. DeVries may be contacted at
mdevries@burr.com
Workers at Two NFL Stadiums Test Positive for COVID-19, But Construction Continues
April 13, 2020 —
Tim Newcomb - Engineering News-RecordConstruction at SoFi Stadium in Inglewood, Calif., and Allegiant Stadium outside Las Vegas—two new NFL stadiums scheduled to open in 2020—continue forward despite a worker at each location testing positive for COVID-19.
Tim Newcomb, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Corrective Action Protest Grounds for GSA Schedule Federal Construction Contractors
September 09, 2024 —
Marissa L. Downs - The Dispute ResolverA contract awarded, protested, terminated, appealed, then reinstated. It’s no secret that federal construction procurements are plagued with uncertainty. From delays, constructive suspensions, compromised supply chains, the litigation-laden critical path method, and the mandate for all construction materials used in federally funded projects for infrastructure to be produced in the United States under the Build America, Buy America Act (BABAA) (to name just a few traditional and emerging favorites), just one of these issues could fill the rest of anyone’s month with substantive research. To add one more, which is entirely unique to bid protests, federal contractors–including construction contractors–listed in a General Service Administration (GSA) Schedule may have new grounds to have a contract award reinstated that was terminated by a federal agency pending a GAO decision.
GAO Protest
An initial GAO protest filed by Deloitte & Touche LLP (Deloitte) argued that the National Geo-Spatial Intelligence Agency (Agency) wrongfully made an award to Kearney & Company, P.C. (Kearney) when the Agency: (1) improperly evaluated quotes; and (2) failed to conduct a proper best-value tradeoff analysis. At issue was a competed task order with Kearney under a GSA FSS multiple-award contract. Before the GAO issued an opinion, however, it held an unrecorded predictive-outcome conference with Deloitte and Kearney where the only mutual consensus was the likely ineligibility of all offerors for the relevant award. The Agency subsequently elected to take corrective action, terminating Kearney’s contract award for convenience, amending the solicitation to avoid issues (including undisputed issues) addressed in the GAO protest. After the Agency adopted their corrective action, the GAO protest was dismissed as academic and moot.
Read the court decisionRead the full story...Reprinted courtesy of
Marissa L. Downs, Laurie & Brennan, LLPMs. Downs may be contacted at
mdowns@lauriebrennan.com
HP Unveils Cheaper, 3-D Printing System to Spur Sales
November 05, 2014 —
Jack Clark - BloombergHewlett-Packard Co. (HPQ) unveiled a new 3-D-capable computer and speedier 3-D printer technology as it prepares to spin off its personal-computer and printer businesses into a stand-alone company.
The company today introduced Sprout, an $1,899 computer that lets people scan and manipulate 2-D and 3-D objects. It will be available early next month online and in some U.S. stores. Hewlett-Packard also said new 3-D printer technology will make the process cheaper and faster than competitors.
The Palo Alto, California-based company is betting that 3-D technology will help revitalize sales and spur growth in the printer industry. More than 2.3 million 3-D printers will ship in 2018, up from about 108000 this year, according to researcher Gartner Inc. Earlier this month, Hewlett-Packard said it would split into two companies by late 2015, with one focused on corporate hardware services and the other -- dubbed HP Inc. -- on PCs and printers.
Read the court decisionRead the full story...Reprinted courtesy of
Jack Clark, BloombergMr. Clark may be contacted at
jclark185@bloomberg.net
Real Estate & Construction News Round-Up (11/03/21)
December 06, 2021 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogAmenity-rich buildings become a key focus in enticing employees back into the office, supply chain links are strained by a lack of storage capacity in warehouses and port areas, green lease signings are on the uptick, and more.
- In an effort to draw employees back into the office and retain talent in a tight labor market, businesses are spending more than ever on upscale workspaces, paying high rents for modern, amenity-rich buildings. (Peter Grant, The Wall Street Journal)
- As sustainability and ESG factors become increasingly important, net-zero carbon commitments are emerging as the next big “must-have” for commercial real estate owners, as more than 100 businesses and organizations have signed on to the World Green Building Council’s Net Zero Carbon Buildings Commitment, which seeks to decarbonize the buildings sector by 2050 and get halfway there by 2030. (Elsa Wenzel, GreenBiz)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Termination for Convenience Clauses: Maybe More Than Just Convenience
June 06, 2022 —
Robert C. Shaia - ConsensusDocsA contractor begins work on a project and everything is going well, until one day the owner informs the contractor that it is being terminated for convenience. Possibly, there is no discussion about alleged defects, reasons for the termination, or any damages the owner might seek against the contractor. In that moment, the contractor may be unaware of any perceived wrongdoing or problems with its work.
The industry has typically accepted that, in this scenario, the owner implicitly waives the right to any remedies against the contractor, except those expressly set forth in the contract. Reasonable minds might assume that, if the owner believed it needed to seek further remedies, it would terminate the contractor for cause instead of convenience. And often overlooked during contract negotiations are the benefits of including an express “waiver of remedies” in the termination for convenience section.
Read the court decisionRead the full story...Reprinted courtesy of
Robert C. Shaia, Watt, Tieder, Hoffar, & Fitzgerald, LLP (ConsensusDocs)Mr. Shaia may be contacted at