Liquidated Damages: A Dangerous Afterthought
January 15, 2019 —
Trevor B. Potter - Construction ExecutiveOwners and contractors frequently treat liquidated damages provisions as an afterthought, but they deserve to be treated as a key deal term. If a contractor breaches a contract by failing to complete the work in a timely manner, the remedy is typically an agreed upon amount or rate of liquidated damages.
Liquidated damages provisions seldom get more than a cursory, “back of the napkin” analysis, or worse, parties will simply plug in a number. This practice is dangerous because liquidated damages typically represent the owner’s sole remedy for delay and, more importantly, they are subject to attack and possible invalidation if certain legal standards are not met. The parties to a construction contract should never agree to an amount of liquidated damages without first attempting to forecast and calculate actual, potential damages.
Reprinted courtesy of
Trevor B. Potter, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Colorado Nearly Triples Damages Caps for Cases Filed in 2025, Allows Siblings to File Wrongful Death Claims
July 22, 2024 —
Amy Johnson - Lewis BrisboisDenver, Colo. (June 13, 2024) - On June 3, 2024, Colorado Governor Jared Polis signed HB24-1472 to increase the damages caps for personal injury and wrongful death claims. The law nearly triples the amounts available to plaintiffs, which will continue to increase for inflationary adjustments beginning in 2028 and every two years thereafter. These new damages caps affect not only claims that accrue in 2025 and beyond, but they also change the caps for any civil cases filed on or after January 1, 2025. This law was enacted as a compromise to a ballot measure that would have removed any cap on damages. The new caps are as follows:
- The cap on noneconomic damages for personal injuries will be $1.5 million.
- The cap on noneconomic damages for wrongful death will be $2.125 million.
Plaintiffs are likely to delay filing new actions through the rest of 2024 as long as they are not up against a statute of limitations deadline.
Read the court decisionRead the full story...Reprinted courtesy of
Amy Johnson, Lewis BrisboisMs. Johnson may be contacted at
Amy.Johnson@lewisbrisbois.com
Traub Lieberman Partner Bradley T. Guldalian Wins Summary Judgment
November 19, 2021 —
Bradley T. Guldalian - Traub LiebermanOn September 14, 2021, Traub Lieberman Partner Bradley T. Guldalian secured summary judgment on behalf of a City which operated a park containing a natural bathing spring in Sarasota County, Florida. The underlying loss occurred when the Plaintiff went to the park, entered the spring without incident, swam for more than an hour, then exited the spring and was returning to the area where she had stored her belongings when she slipped and fell on mud and grass, sustaining an open angulated fracture of her right tibia and fibula. The Plaintiff was rushed to the hospital where she underwent open reduction, internal fixation surgery on her right leg which consisted of implantation of a metal rod into the medullary cavity of her tibia that was secured by two proximal and two distal interlocking screws. She was in the hospital for four days. Upon discharge, the Plaintiff was placed in a walking boot and confined to a wheelchair for several months. The Plaintiff incurred nearly $100,000 in medical expenses. The Plaintiff filed a premises liability action against the City claiming it failed to maintain its premises in a reasonably safe condition. The Plaintiff also alleged that the City failed to warn her that the area where she had stored her belongings had become saturated and slippery proximately causing her fall and resulting injuries.
After the close of discovery, Mr. Guldalian filed a Motion for Summary Judgment on behalf of the City arguing the wet grass and mud upon which the Plaintiff fell and injured herself was a byproduct of patrons going in and out of the water and walking to and from the area where they stored their belongings, was open and obvious, and did not constitute a dangerous condition as a matter of law. Citing to case law from the Florida Supreme Court which held that it is common knowledge that walks adjacent to, leading to, or surrounding a bathing area generally have water constantly thrown upon them and are in a slippery condition, as well as deposition testimony from the Plaintiff confirming she had been swimming at the spring for the past eighteen plus years and was “very familiar” with the park, the spring, and the area where she normally stored her belongings, Mr. Guldalian argued that some injury-causing conditions, like wet grass and mud surrounding a swimming area, are simply so open and so obvious that they cannot be held, as a matter of law, to give rise to liability as dangerous conditions.
Read the court decisionRead the full story...Reprinted courtesy of
Bradley T. Guldalian, Traub LiebermanMr. Guldalian may be contacted at
bguldalian@tlsslaw.com
Alleged Defective Water Pump Leads to 900K in Damages
January 13, 2014 —
CDJ STAFFA lawsuit filed by Liberty Mutual on behalf of their client, Turner Construction, alleges that defects in the installation of a water pump lead to $900,000 in costs for a building in New Jersey. They are seeking compensation from Triangle Plumbing. Law360 quotes the complaint, which states “as a result of Triangle’s failure to provide a complete, functional plumbing system at the property as required by the subcontract agreement, Triangle has breached the specific scope of work provision of the subcontract agreement.”
Read the court decisionRead the full story...Reprinted courtesy of
New Jersey Supreme Court Holding Impacts Allocation of Damages in Cases Involving Successive Tortfeasors
March 28, 2022 —
Thomas Regan & Karley Kamaris - Lewis BrisboisNewark, N.J. (March 21, 2022) - Late in 2021, the Supreme Court of New Jersey addressed the issue of allocating damages in personal injury cases in which the plaintiff asserts claims against successive tortfeasors, such as medical malpractice in the treatment of a slip and fall injury caused by negligence. The decision in Glassman v. Friedel, 249 N.J. 199 (2021) overruled and replaced the long-held principles established in Ciluffo v. Middlesex General Hospital, 146 N.J. Super. 478 (App. Div. 1977) regarding successive liability. Ciluffo held that, when an initial tortfeasor settles before trial, the non-settling defendants in a successive tort were entitled to a pro tanto credit for the settlement amount against any damages assessed against them. The Superior Court of New Jersey Appellate Division in 2020, and the Supreme Court of New Jersey last year, abandoned that framework for one more consistent with statutory contribution law in the Garden State.
In Glassman v. Friedel, 465 N.J. Super. 436 (App. Div. 2020), the Appellate Division held that the application of the principles in Ciluffo in a negligence case has no support in modern jurisprudence, thus limiting its application. It rejected the holding in Ciluffo in light of the state legislature’s enactment of the Comparative Negligence Act, which requires juries to apportion damages between successive events and apportion fault among the parties responsible for each event. The appellate division went on to hold that a non-settling, successive tortfeasor may present proofs at trial as to the negligence of the settling tortfeasor, and that the burden of proof as to the initial tortfeasor’s negligence being the proximate cause of the second causative event indeed lies on the non-settling defendant. In sum, the appellate division in Glassman established steps the jury can use to determine successive tortfeasor liability, but largely treated it as one, attenuated incident.
Reprinted courtesy of
Thomas Regan, Lewis Brisbois and
Karley Kamaris, Lewis Brisbois
Mr. Regan may be contacted at Thomas.Regan@lewisbrisbois.com
Ms. Kamaris may be contacted at Karley.Kamaris@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Avoid Delay or Get Ready to Pay: The Risks of “Time-Is-of-The-Essence” Clauses
August 29, 2018 —
Stephen Orlando - Gordon & Rees Construction Law BlogLike death and taxes, construction delays are inevitable. Even the most cautious, diligent contractor may face subcontractor disputes, supply shortages, or inclement weather which slows down a project. Even if the contractor avoids unexpected problems, the sheer complexity of a job may cause a contractor to exceed the deadlines proposed in a contract.
Fortunately, courts recognize the practical reality of construction projects and the unavoidable delays which may arise. Therefore, as a general rule, a contractor is only liable for delayed completion of a project if the delay resulted from the contractor’s unreasonable performance of his or her work. Reasonable performance will typically serve as a defense to a claim of delayed completion. This defense is a vital asset when a contractor surpasses the project’s expected timeframe.
Read the court decisionRead the full story...Reprinted courtesy of
Stephen Orlando, Gordon & Rees Scully Mansukhani
Traub Lieberman Attorneys Lisa M. Rolle and Justyn Verzillo Win Motion for Summary Judgment
December 23, 2024 —
Lisa M. Rolle & Justyn Verzillo - Traub LiebermanIn this subrogation action brought in the Supreme Court of the State of New York, Dutchess County, Traub Lieberman attorneys Lisa M. Rolle and Justyn Verzillo successfully obtained dismissal of a third-party complaint against their client, a fire-system protection company. In the underlying case, a fire sprinkler system within a commercial building leaked water into multiple tenant spaces, causing damage. The tenants’ insurers alleged that they each paid several hundred thousand dollars to cover their insureds’ claims. The insurers then filed complaints against the company which originally installed the sprinkler (the “Installer”), asserting that the company breached its duty of care. The Installer commenced a third-party action against the property owner and two fire-system protection companies—including Traub Lieberman’s client—who had separately conducted annual inspections of the sprinkler system over the years. The property owner and the two fire-system protection companies each asserted cross-claims against each other.
Reprinted courtesy of
Lisa M. Rolle, Traub Lieberman and
Justyn Verzillo, Traub Lieberman
Ms. Rolle may be contacted at lrolle@tlsslaw.com
Mr. Verzillo may be contacted at jverzillo@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Client Alert: California’s Unfair Competition Law (B&P §17200) Preempted by Federal Workplace Safety Law
September 24, 2014 —
R. Bryan Martin, Yvette Davis, & Kristian Moriarty - Haight Brown & Bonesteel LLPIn Solus Industrial Innovations LLC v. Superior Court (No. G047661, filed 9/22/2014) (“Solus”) the California Court of Appeal, Fourth Appellate District, held California’s Unfair Competition Law (Business & Professions Code §17200) is preempted by the federal Occupational Safety and Health Act of 1970 (“Fed/OSHA”) because the Unfair Competition law, as approved by the United States Secretary of Labor, does not include any provision for civil enforcement of workplace safety standards by a state prosecutor through a complaint for penalties.
Solus Industrial Innovations, LLC (“Solus”) is a plastics manufacturer. In 2007, Solus installed a residential water heater at its commercial facility in Orange County. The water heater exploded in March 2009, killing two workers. California’s Division of Occupational Safety and Health (“Cal/OSHA”) investigated and determined the explosion was caused by a failed safety valve and lack of any proper safety feature on the water heater. Cal/OSHA charged Solus with five violations of Title 8 of the California Code of Regulations. Because deaths were involved, Cal/OSHA forwarded the results of its investigation to the Orange County District Attorney.
In March 2012, the Orange County District Attorney filed criminal charges against Solus’ plant manager and maintenance supervisor. The District Attorney also filed a civil action against Solus, including two causes of action for violation of California Business & Professions Code §17200 – the Unfair Competition Law (“UCL”). The action sought civil penalties under the UCL in the amount of $2,500 per day, per employee, from November 29, 2007 through March 19, 2009.
Reprinted courtesy of Haight Brown & Bonesteel LLP attorneys
R. Bryan Martin,
Yvette Davis and
Kristian Moriarty
Mr. Martin may be contacted at bmartin@hbblaw.com
Ms. Davis may be contacted at ydavis@hbblaw.com
Mr. Moriarty may be contacted at kmoriarty@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of