Christopher G. Hill - Construction Law MusingsI have often discussed the limited circumstances under which a construction contract claim and a fraud claim can coexist. A recent case from the Western District of Virginia federal court demonstrates that care is necessary even in those limited circumstances.
In Fluor Fed. Sols., LLC v. Bae Sys. Ordinance Sys., the Court examined the question of a fraud statute of limitations under Virginia law. The basic facts found in the Complaint are these:
In 2011, the United States Army awarded BAE Systems Ordinance Systems Inc. a basic ordering agreement under which BAE was responsible for modernization projects at the Radford Army Ammunition Plant. This action stems from a subcontract between Fluor Federal Solutions LLC and BAE, under which Fluor agreed to design and construct a new natural gas boiler at the plant. Fluor has completed work on the project, and BAE has accepted that work. Nonetheless, Fluor claims that BAE has refused or failed to pay for the balance of the project costs. Fluor alleges that BAE received several changes to its prime contract from the Army but did not pass those changes along to Fluor until after BAE solicited a bid from Fluor and entered a contract with Fluor to build a temporary facility. Instead, BAE continued to misrepresent the scope of the project. Fluor alleges that the change in plans increased costs substantially, but that BAE withheld information about those changes so that it could solicit lower bids. Fluor alleges that it requested a copy of BAE’s prime contract on numerous occasions, but BAE failed to provide a copy of it. Instead, Fluor submitted a request under the Freedom of Information Act. It received a copy of BAE’s prime contract on Oct. 3, 2018.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Be Careful with Good Faith Payments
February 24, 2020 —
Christopher G. Hill - Construction Law MusingsSometimes doing the expedient thing and what looks good at the time can come back to bite you. Just ask 3M Company.
In Faneuil, Inc. v. 3M Co., the Virginia Supreme Court considered a customer services subcontract between Faneuil and 3M relating to a toll collection contract 3M entered into with ERC. The subcontract had a “pay if paid” clause in it requiring payment to 3M from ERC before ERC was required to pay Faneuil, a written change order provision and a base monthly payment to Faneuil for the services that could be reduced in the event of less than expected toll collections. Further, the subcontract stated that if either party settled 3rd party claims, that settlement would not bind the other party to the subcontract absent consent or Court order.
Faneuil was then alleged to have been required to provide “Special Services” relating to manual identification of license plates and other information necessary for toll billing due to 3M’s alleged failure to provide adequate imaging services. Faneuil requested (without written change order) and 3M promised to pay extra for these services. When 3M was slow to pay for the special services, Faneuil did what you would expect and threatened to stop providing them. Instead of contesting the right to the work, 3m made sporadic “good faith” payments to induce continued Special Services from Faneuil. Eventually 3M’s issues caused ERC to stop payments and thus 3M stopped paying Faneuil. 3M then settled the payment claims with ERC and still failed to pay Faneuil.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Veolia Agrees to $25M Settlement in Flint Water Crisis Case
February 19, 2024 —
James Leggate - Engineering News-RecordEngineering firm Veolia North America agreed to a $25-million settlement to resolve a federal class action case related to its work for the city of Flint, Mich., during the city’s lead-in-water crisis, the company and attorneys for the plaintiffs announced Feb. 1. Veolia is the second engineering firm that worked for the city to settle with city residents, and the deal came ahead of a class-action trial scheduled to start later this month.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
DoD Testing New Roofing System that Saves Energy and Water
October 08, 2014 —
Beverley BevenFlorez-CDJ STAFFBuilder reported that the Department of Defense (DoD) is hosting a new “dynamic roofing system, installed at the Security Forces Building at Goodfellow Air Force Base in San Angelo, Texas,” which “uses a combination of technologies that heat and cool air and water, produce electricity, and collect rainwater.” If the project is successful, it “could be replicated at thousands of DoD buildings throughout the country in the near future.”
Builder described the process: “A retrofitted metal roof is installed over the existing roof, which creates a cavity between the existing and new roofs. Within that cavity insulation, solar thermal heating systems and cooling of air and water for the building can be installed. The roofing, insulation, hydronic solar thermal systems, engineered air pathways, and photovoltaic cells are designed to work symbiotically.”
Read the court decisionRead the full story...Reprinted courtesy of
Hollywood Legend Betty Grable’s Former Home for Sale
June 30, 2014 —
Catherine Sherman – BloombergWhen it comes to Old Hollywood stars, Betty Grable was “the girl with the million-dollar legs.” She also lived in a million-dollar home just four blocks from the Hotel Bel-Air.
Located at 1280 Stone Canyon Rd, the house is currently on the market for $13.295 million.
“It’s a classic, Hollywood estate,” said listing agent Bjorn Farrugia of Hilton & Hyland. “It’s very picturesque — set back on one of the best streets in Bel-Air.”
Grable moved in after the home was built in 1937, the same year she married actor Jackie Coogan (aka “Uncle Fester” in the 1960s sitcom The Addams Family). Soon after, in 1939, the couple appeared in “Million Dollar Legs,” a movie giving rise to the actress’ nickname.
Read the court decisionRead the full story...Reprinted courtesy of
Catherine Sherman – Bloomberg
Georgia Amends Anti-Indemnity Statute
June 02, 2016 —
David R. Cook Jr. – AHHC Construction Law BlogIn its most recent session, the Georgia General Assembly passed HB 943, which amends Georgia’s Anti-Indemnity Statute. The amendment expands the Anti-Indemnity Statute beyond construction contracts to include contracts for engineering, architectural, and land surveying services (“A/E Contracts”).
In a
prior post, we discussed
Georgia’s Anti-Indemnity Statute, which generally prohibits indemnity clauses in construction contracts that require one party (the “Indemnitor”) to indemnify another party (the “Indemnitee”) if property damage or bodily injury results from the Indemnitee’s sole negligence. The
prior post, discussed the Supreme Court of Georgia’s broad interpretation of the Anti-Indemnity Statute.
HB 943 adds subpart (c), which states:
A covenant, promise, agreement, or understanding in or in connection with or collateral to a contract or agreement for engineering, architectural, or land surveying services purporting to require that one party to such contract or agreement shall indemnify, hold harmless, insure, or defend the other party to the contract or other named indemnitee, including its, his, or her officers, agents, or employees, against liability or claims for damages, losses, or expenses, including attorney fees, is against public policy and void and unenforceable, except for indemnification for damages, losses, or expenses to the extent caused by or resulting from the negligence, recklessness, or intentionally wrongful conduct of the indemnitor or other persons employed or utilized by the indemnitor in the performance of the contract. This subsection shall not affect any obligation under workers’ compensation or coverage or insurance specifically relating to workers’ compensation, nor shall this subsection apply to any requirement that one party to the contract purchase a project specific insurance policy or project specific policy endorsement.
(Emphasis added.)
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook Jr., Autry, Hanrahan, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
The “Climate 21 Project” Prepared for the New Administration
December 21, 2020 —
Anthony B. Cavender - Gravel2GavelThis is a brief review of the recently released “Climate 21 Project” policy memo. It is the work of many former members of the Obama Administration who are deeply concerned about climate change and what steps the new administration can take in the first 100 days to confront a problem. Offering “actionable advice” rather than a policy agenda, the group recognizes that Congress must do its part by providing new statutory authorities within the early days of the new administration, and the President must be prepared to aggressively exercise the powers of his office. As the members of the Group see it, there are four interlocking crises facing the President: (a) the COVID-19 pandemic; (b) the economic devastation visited upon many people by the pandemic; (c) racial injustice; and (d) accelerating threats posed by climate change.
Accordingly:
1. The Executive Office of the President must take stronger steps to reduce greenhouse gas emissions through domestic investment, rulemakings, policy changes, and international diplomacy. A new Special Assistant for Climate Change must be created to take charge of these climate change initiatives. There should also be established in the Executive Office of the President a National Climate Change Council. All agencies must be advised of the urgency of this problem. The paper seems to envision a substantial growth in the White Hose staff.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Affordable Housing, Military Contracts and Mars: 3D Printing Construction Potential Builds
September 05, 2022 —
Adam J. Weaver & Lindsey Mitchell - Gravel2Gavel Construction & Real Estate Law BlogThe 3D printing construction market is likely on the cusp of a boom.
This unique construction method boasts many advantages in comparison to traditional forms of construction. Projects can be completed more quickly and at a fraction of the cost, given fewer laborers are required and the materials used are much cheaper. Though market growth stalled during the COVID-19 pandemic, industry leaders expect 3D printing construction to experience exponential growth in the coming years.
While 3D printing technology has risen in popularity and prominence in the past couple of decades, it is only recently that 3D printing companies have begun making strides in the construction industry. Critical to the construction process is the software that is used to create and model the planned structure. A software program turns a building’s blueprint into code that then dictates the movement of a 3D printer on the construction site. After a concrete-like mix is loaded into the printer, the printer begins to build the walls by laying one cylindrical layer of concrete at a time, in accordance with the blueprint. There is no one-size-fits-all approach in 3D printing construction: some companies print the core structure as well as the roof and floor of the structure, while others print only the core and shell and install those portions separately using traditional methods and materials.
Reprinted courtesy of
Adam J. Weaver, Pillsbury and
Lindsey Mitchell, Pillsbury
Mr. Weaver may be contacted at adam.weaver@pillsburylaw.com