Hawaii Federal District Court Grants Preliminary Approval of Settlement on Volcano Damage
September 13, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court granted preliminary approval of the class action settlement reached on behalf of insureds who suffered property damage due to the 2018 Kilauea eruption on the Big Island. Aquilina v. Certain Underwriters at Lloyd's London, 2021 U.S. Dist. LEXIS 152614 (D. Haw. Aug. 13, 2021).
After destruction of their homes due to lava flow, plaintiffs sued various insurers and agents as a putative class action. Plaintiffs claimed they purchased surplus lines policies brokered and underwritten by various defendants. The policies each contained an exclusion for the peril of lava flow, which plaintiffs claimed rendered them worthless or unsuitable given that their properties were located in a high-risk lava zone.
Plaintiffs alleged that defendants breached obligations under the Hawaii Surplus Lines Act, which required that surplus lines insurers conduct a diligent search for other available coverage before placing a homeowner with surplus lines coverage. Plaintiffs alleged defendants should have advised them of the availability of lava-damage coverage through the Hawaii Property Insurance Association (HPIA), a statutorily created association of admitted insurers established in part in response to Kilauea's eruption patterns, which made the private insurance market less likely to Insure certain high-risk areas.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Toolbox Talk Series Recap – Best Practices for Productive Rule 26(f) Conferences on Discovery Plans
May 13, 2024 —
Douglas J. Mackin - The Dispute ResolverIn the April 4, 2024 edition of Division 1’s Toolbox Talk Series,
Julian Ackert and
Steve Swart presented on how to prepare for and structure Rule 26(f) conferences to be more effective. While Swart and Ackert focused on the requirements of Federal Rule of Civil Procedure 26(f) regarding the requisite conference of the parties prior to a scheduling conference or scheduling order, it is worth noting that many states have substantially similar requirements.
Rule 26(f) requires the parties to (i) discuss the nature and basis of their claims or defense; (ii) make or arrange for mandatory disclosures pursuant to Rule 26(a)(1); (iii) discuss issues about preserving discoverable information (including Electronically Stored Information – “ESI”); and (iv) develop a proposed discovery plan. Swart and Ackert’s presentation focused on the preservation of ESI and the proposed discovery plan.
Read the court decisionRead the full story...Reprinted courtesy of
Douglas J. Mackin, Cozen O’ConnorMr. Mackin may be contacted at
dmackin@cozen.com
Missouri Asbestos Litigation Reform: New Bill Seeks to Establish Robust Disclosure Obligations
March 15, 2021 —
Jennifer B. Pigeon - Lewis BrisboisMissouri State Senator Eric Burlison is reviving attempts to reform asbestos litigation in the State of Missouri through the introduction of SB 331. This bill was pre-filed on December 29, 2020 and first read on January 6, 2021. The bill establishes disclosure procedures for claimants in asbestos-related lawsuits. Specifically, the bill, if passed, would require claimants in civil asbestos-related lawsuits to file a sworn information form within 30 days of filing an asbestos-related lawsuit.
The required disclosures under SB 331 include, but are not limited to (1) each asbestos-containing product to which the exposed person was exposed and each physical location at which the exposure occurred; (2) the identity of the manufacturer or distributor of specific asbestos-containing products for each named exposure; (3) the specific location and manner of each exposure; (4) the beginning and end dates of each exposure, the frequency and length of each exposure, and the proximity of the asbestos-containing product or its use to the exposed person; and (5) a certification that any claim that can be made with a bankruptcy trust concerning any asbestos injury to the exposed person has been filed.
Read the court decisionRead the full story...Reprinted courtesy of
Jennifer B. Pigeon, Lewis BrisboisMs. Pigeon may be contacted at
Jenna.Pigeon@lewisbrisbois.com
Measure Of Damages for Breach of Construction Contract
October 18, 2021 —
David Adelstein - Florida Construction Legal UpdatesHow do you determine damages for a breach of a construction contract? If you are interested in pursing a breach of a construction contract action, this is something you NEED TO KNOW!
The recent Fourth District Court of Appeal’s decision in Cano, Inc. v. Judet, 46 Fla. L. Weekly D2083b (Fla. 4th DCA 201) explains:
Where a contractor breaches a construction contract, and the owner sues for breach of contract and the cost to complete, the measure of damages is the difference between the contract price and the reasonable cost to perform the contract. See Grossman Holdings Ltd. v. Hourihan, 414 So. 2d 1037, 1039-40 (Fla. 1982). In Grossman, the supreme court adopted subsection 346(1)(a) of the Restatement (First) of Contracts (1932), which it concluded was “designed to restore the injured party to the condition he would have been in if the contract had been performed.” Id. at 1039. In other words, the owner will obtain the benefit of his bargain [and this is known as benefit of the bargain damages]. But where there is a total breach of the contract as opposed to a partial breach, an injured party may elect to treat the contract as void and seek damages that will restore him to the position that he was in prior to entering into the contract or the party may seek the benefit of his bargain. See McCray v. Murray, 423 So. 2d 559, 561 (Fla. 1st DCA 1982).
In Judet, an owner entered into a fixed price contract with a contractor to repair damage from a lightning strike. The contract amount was $300,000 payable in $30,000 installments. A few months after the contractor commenced performance, the owner terminated the contractor because the owner learned the contractor had not obtained required electrical and plumbing permits. At this time, the owner had paid the contractor $90,000. The contractor recorded a $40,000 lien for an amount it claimed it was owed and filed a lawsuit to foreclose its construction lien. The owner counter-sued the contractor to recover a claimed over-payment and a disgorgement of monies for unpermitted work. The owner was NOT claiming benefit of the bargain damages, but rather, damages for the contractor’s total breach “to restore him to the position that he was in prior to entering into the contract.”
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Amazon HQ2 Puts Concrete on an Embodied Carbon Diet
January 17, 2022 —
Nadine M. Post - Engineering News-RecordBefore the ground-breaking for Amazon’s 2.1-million-sq-ft Metropolitan Park office development across the Potomac River from the nation’s capital, Clark Construction Group’s John Swagart and Jeff King walked door to door, introducing themselves to shopkeepers near the MetPark site. The good-will ambassadors were pounding the pavement to inform MetPark’s neighbors of the plan to dig a 50-ft-deep hole—710 ft x 310 ft—and create two 22-story buildings.
Reprinted courtesy of
Nadine M. Post, Engineering News-Record
Ms. Post may be contacted at postn@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Factual Issues Prevent Summary Judgment Determination on Coverage for Additional Insured
May 01, 2014 —
Tred R. Eyerly – Insurance Law HawaiiNumerous factual issues prevented the court from deciding at the summary judgment stage whether the additional insured was covered for a personal injury claim that happened on a construction site. Paynes Cranes v. Am States Ins. Co., 2014 U.S. Dist. LEXIS 40485 (E.D. N.Y. March 26, 2014).
Intermetal Fabricators, Inc. hired Paynes to provide a crane and driver for the construction of a store. A construction worker was injured while working with the crane. The injured worker sued several defendants, including Paynes.
Intermetal had coverage for the project that included additional insureds. The policy provided, “Any person or organization . . . for whom you [Intermetal] are required by written contract, agreement or permit to provide insurance is an insured, subject to the following additional provisions: a. The contract, agreement or permit must be in effect during the policy period . . . and must have been executed prior to the ‘bodily injury,’ ‘property damage,’ 'person and advertising injury.’”
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Wearable Ways to Work in Extreme Heat
July 15, 2024 —
Clare Epstein - Construction ExecutiveEarth experienced its hottest months yet in summer 2023, and
NASA scientists are expecting 2024 to be even hotter. Rising temperatures and high humidity aren’t just uncomfortable for those outside during the summer months: They can cause serious health consequences, including death. While employers are working to find ways to combat the heat, the extreme variability in weather conditions continues to pose threats to employees.
Recently, company leaders have turned to new methods and technologies to help their teams stay safe while working both indoors and outdoors. A balance of methods and technology is necessary to keep everyone safe while they work. As summer approaches, is important to remember that the time to review and update current heat-stress safety plans is in the spring—or better yet, year-round—in order to prioritize employee safety and determine both proactive and reactive measures needed to withstand the hottest months of the year.
TRIED AND TRUE
While we are all navigating new ways of working safely in extreme temperatures, the tried-and-true measures are still extremely useful in preventing heat stress among employees. Employers can support their employees working outdoors by ensuring there are proper amenities available at all times, including shady areas, a water source and electrolyte drinks.
Reprinted courtesy of
Clare Epstein, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
SAFETY Act Part II: Levels of Protection
June 21, 2024 —
Lorelie S. Masters, Kevin W. Jones & Charlotte Leszinske - Hunton Insurance Recovery BlogPart I of this series,
SAFETY Act is Powerful Protection Against Emerging Liabilities, addressed the benefits of obtaining SAFETY Act coverage, including:
- From a reputational perspective, SAFETY Act protection provides benefits even absent a security incident: it demonstrates that a knowledgeable federal agency has examined the relevant technology and determined that it is both safe and effective.
- SAFETY Act protection can benefit companies taking steps to enhance the security of their physical premises and operations, or their cybersecurity defenses, to reduce their potential liability and enhance their reputation.
- Other benefits include—depending on the level of protection—powerful liability protections including exclusive federal jurisdiction and choice of law for the venue where the incident occurred, caps on liability, prohibitions on punitive damages, and government contractor immunity.
This post will explain the levels of protection that a company can seek under the SAFETY Act.
Reprinted courtesy of
Lorelie S. Masters, Hunton Andrews Kurth,
Kevin W. Jones, Hunton Andrews Kurth and
Charlotte Leszinske, Hunton Andrews Kurth
Ms. Masters may be contacted at lmasters@HuntonAK.com
Mr. Jones may be contacted at kjones@HuntonAK.com
Ms. Leszinske may be contacted at cleszinske@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of