Safe Harbors- not just for Sailors anymore (or, why advance planning can prevent claims of defective plans & specs) (law note)
August 17, 2011 —
Melissa Brumback, Construction Law in North CarolinaHave you ever considered a “Safe Harbor Provision” for your Owner-Architect or Owner-Engineer contract? Maybe it is time that you do.
As you are (probably too well) aware, on every construction project there are changes. Some of these are due to the owner’s change of heart, value engineering concerns, contractor failures, and material substitutions. Some may be because of a design error, omission, or drawing conflict. It happens.
A “Safe Harbor Provision” is a provision that establishes an acceptable percentage of increased construction costs (that is, a percentage of the project’s contingency). The idea is that if the construction changes attributable to the designer is within this percentage, no claim will be made by the Owner for design defects.
Read the full story…
Reprinted courtesy of Melissa Brumback of Ragsdale Liggett PLLC. Ms. Brumback can be contacted at mbrumback@rl-law.com.
Read the court decisionRead the full story...Reprinted courtesy of
California Mediation Confidentiality May Apply to Third Party “Participants” Retained to Provide Analysis
November 02, 2017 —
Tony Carucci - Snell & Wilmer Real Estate Litigation BlogCalifornia Evidence Code section 1119 governs the general admissibility of oral and written communications generated during the mediation process. Section 1119(a) provides that “[n]o evidence of anything said or any admission made
for the purpose of, in the course of, or pursuant to, a mediation . . . is admissible or subject to discovery, and disclosure of the evidence shall not be compelled, in any . . . civil action . . . .” Cal. Evid. Code § 1119(a) (emphasis added). Similarly, section 1119(b) bars discovery or admission in evidence of any “writing . . . prepared
for the purpose of, in the course of, or pursuant to, a mediation . . . .” Cal. Evid. Code § 1119(b) (emphasis added). Finally, section 1119(c) provides that “[a]ll communications, negotiations, or settlement discussions by and between
participants in the course of a mediation . . . shall remain confidential.” Cal. Evid. Code § 1119(c) (emphasis added).
Read the court decisionRead the full story...Reprinted courtesy of
Tony Carucci, Snell & WilmerMr. Carucci may be contacted at
acarucci@swlaw.com
Disaster Remediation Contracts: Understanding the Law to Avoid a Second Disaster
August 30, 2017 —
Todd Colvard – Peckar & Abramson, P.C.In the aftermath of Hurricane Harvey, consumers and contractors should be aware of protections prescribed by the Texas Legislature for Disaster Remediation Contracts. Chapter 58 of the Texas Business and Commerce Code includes several important consumer protections. Consumers should be aware of these protections, and contractors should take care to avoid inadvertent violations.
This statute applies to a contractor engaged in “disaster remediation,” in a county subject to a disaster declaration. Those contracts are subject to certain notice provisions and limitations. A violation of Chapter 58 is considered a Deceptive Trade Practice and could subject a violator to both public and private remedies. The full text of Chapter 58 is found here: http://www.statutes.legis.state.tx.us/Docs/BC/htm/BC.58.htm.
Read the court decisionRead the full story...Reprinted courtesy of
Todd Colvard, Peckar & Abramson, P.C.Mr. Colvard may be contacted at
tcolvard@pecklaw.com
Apartment Construction Increasing in Colorado while Condo Construction Remains Slow
March 12, 2014 —
Beverley BevenFlorez-CDJ STAFFDennis Huspeni writing for the Denver Business Journal reported that Colorado is having a surge of new apartment construction, but very little condominium building. According to Huspeni, “some business leaders and government officials worry that Colorado’s construction defect laws” are the reason for the lack of condominium construction.
Huspeni in the Denver Business Journal alleged that there is a large “liability risk for builders, developers and subcontractors” because current state laws “make it easier for homeowners’ associations to file large, class-action lawsuits against builders for construction problems associated with new condominiums.”
Huspeni spoke with John Batug, senior vice president and regional manager of Wells Fargo’s community banking real estate group, who stated that condo development usually occurs at the same rate as apartment development. Batug alleged that construction defect litigation “seems to have pushed that component of the market out.”
A bill that is supposed to “jump-start” the “condominium construction sector will be introduced this session, but its sponsor said he remains unsure what types of legal reform will be a part of it,” reported Ed Sealover in the Denver Business Journal.
Lakewood Mayor Bob Murphy told Sealover that “city and business leaders would like to see two particular changes in the law: 1.They want to require a super-majority of condo owners to have to agree to legal action before any lawsuit is filed — instead of just needing two of them to move forward. 2.They want a requirement to attempt some sort of alternative dispute resolution before a suit can be filed.”
However, not everyone is in favor of the proposed suggestions. Jonathan Harris, vice president of The Point Homeowners Association, told Sealover that the “bill that the Metro Mayors Caucus wants ignores the fact that arbitration can be an expensive process for property owners.”
Read the full story, Huspeni Article...
Read the full story, Sealover Article... Read the court decisionRead the full story...Reprinted courtesy of
Professor Senet’s List of 25 Decisions Every California Construction Lawyer Should Know:
January 17, 2022 —
Ted Senet - Gibbs Giden- Aas v. Superior Court (2000) 24 Cal. 4th 627 – economic loss rule
- Amelco Electric v. City of Thousand Oaks ( (2002) 27 Cal. 4th 228 – abandonment does not apply to public works – total cost theory is allowed
- Beacon Residential Community Association v. Skidmore, Owings & Merrill (2014) 59 Cal. 4th 568 – architect liable in absence of privity
- Cates Const., Inc. v. Talbot Partners (1999) 21 Cal.4th 28 – no tort recovery on bonds – performance bonds can cover contract warranties
- Condon-Johnson & Associates, Inc. v. Sacramento Municipal Utility Dist., 149 Cal. App. 4th 1384 – liability for concealed conditions
- Connolly Development, Inc. v. Superior Court of Merced County (1976) 17 Cal. 3d 803 – mechanic lien remedy is constitutional
- Crawford v. Weather Shield Mfg. (2008) 44 Cal. 4th 541 – indemnity implies obligation to defend [now limited to commercial contracts under CCP 2782 (c)–(h)]
Read the court decisionRead the full story...Reprinted courtesy of
Ted Senet, Gibbs GiddenMr. Senet may be contacted at
tsenet@gibbsgiden.com
The Importance of the Recent Amendment to Rule 702 of the Federal Rules of Evidence
January 22, 2024 —
Andrew G. Vicknair - The Dispute ResolverEvery litigator understands that expert witnesses play a key role in litigation, especially when dealing with construction issues. Expert testimony at trial can be a deciding factor in persuading a judge or jury in your client’s favor. It is so important that, as parties get closer to trial, litigators often spend considerable time filing motions to limit or disqualify certain aspects of expert testimony in an effort to gain an advantage at trial. Because experts are a key aspect of the trial process, it is important to understand the various rules governing use of expert testimony, primarily Rule 702 of the Federal Rules of Evidence.
On December 1, 2023, amendments to Rule 702 of the Federal Rules of Evidence went into effect which added the language in underline below and removed the language which is crossed out:
Rule 702. Testimony by Expert Witness
A witness who is qualified as an expert by knowledge, skill, experience, training, or education may testify in the form of an opinion or otherwise if the proponent demonstrates to the court that it is more likely than not that:
(a) the expert’s scientific, technical, or other specialized knowledge will help the trier of fact to understand the evidence or to determine a fact in issue;
(b) the testimony is based on sufficient facts or data;
(c) the testimony is the product of reliable principles and methods; and
(d) the expert has reliably applied expert’s opinion reflects a reliable application of the principles and methods to the facts of the case.
Read the court decisionRead the full story...Reprinted courtesy of
Andrew G. Vicknair, D'Arcy Vicknair, LLCMr. Vicknair may be contacted at
agv@darcyvicknair.com
Want to Make Your Jobsite Safer? Look to the Skies.
October 10, 2022 —
Rory San Miguel - Construction ExecutiveNew York Gov. Kathy Hochul is set to sign Carlos’ Law for worker protection. The law would set a national precedent for construction site safety, substantially raising the minimum fines for construction companies found liable for onsite injuries.
Worksites are very complex, and many factors go into creating a safe space. Following suit, innovative operators are looking at advanced technologies to boost onsite safety, including drone data visualization, which involves flying a drone over a site to capture a highly accurate 3D model of current conditions in close to real time. Using drones can't solve every problem, but it can help not only protect workers but also encourage new ones to join your team.
How drone surveying improves jobsite safety
3D mapping a worksite with a drone keeps workers out of harm’s way, helping surveyors avoid potentially dangerous areas filled with constantly moving heavy equipment and machinery. Drone mapping also means surveyors can stay out of the heat, avoiding the risk of excess sun exposure by sending the drone out in their stead to traverse the terrains and slopes of the site.
Reprinted courtesy of
Rory San Miguel, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Construction Termination Part 3: When the Contractor Is Firing the Owner
August 07, 2023 —
Melissa Dewey Brumback - Construction Law in North CarolinaLast week we discussed an Owner terminating a Contractor “for cause.” Today, it’s time for a 180: what is your role as the architect when the Contractor is quitting?
First, be aware that there are valid reasons for a contractor to quit within the contract itself. Most of these have to do with either (a) time delays/stand stills or (b) failure of the Owner to make payments as required.
The Contractor can suspend or terminate a contract with the Owner for cause, provided a 7 day written notice is given to Owner and Architect. See A201§14.1.3. (This can be an
email notice as all AIA notice clauses now allow).
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale LiggettMs. Brumback may be contacted at
mbrumback@rl-law.com