CSLB Joint Venture Licenses – Providing Contractors With The Means To Expand Their Businesses
April 28, 2016 —
David A. Harris – Haight Brown & Bonesteel LLPCalifornia’s Business and Professions Code requires contractors to be licensed by the Contractors State License Board (“CSLB”). The CSLB issues licenses in 44 different classifications which are separated into three categories: “A” licenses are for general engineering contractors, “B” licenses are for general building contractors, and “C” licenses are specialty licenses that cover everything from installing boilers to installing ornamental metal.
Performing construction work without a license or without the requisite license is a misdemeanor and can lead to the imposition of fines and in certain instances, jail time. (California’s Business and Professions Code Section 7028(a).) While potential imprisonment is unlikely, contractors are frequently fined, or prohibited from filing suit to collect money for their work. Perhaps most onerous, a contractor who is unlicensed, or working with a suspended license or the wrong license, can be forced to return all of the money it was paid for its work. (See our alert:Performing Work with a Suspended CSLB License Costs Big: Subcontractor Faces $18,000,000 Disgorgement.)
Read the court decisionRead the full story...Reprinted courtesy of
David A. Harris, Haight Brown & Bonesteel LLPMr. Harris may be contacted at
dharris@hbblaw.com
Eighth Circuit Affirms Finding of Bad Faith, Award of Costs and Prejudgment Interest
October 25, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe Eighth Circuit affirmed the district court's finding of bad faith and award to the insured of taxable costs and prejudgment interest. Selective Ins. Co. v. Sela, 2021 U.S. App. LEXIS 26062 (8th Cir. Aug. 30, 2021).
The insured suffered two hail storms that damaged his home. In 2010, the first storm caused over half a million dollars in loss. Before submitting a claim to his original insurer or beginning any repairs, the insured secured a new policy with Selective. The policy did not exclude pre-existing damage, it did preclude coverage if the insured "willfully and with intent to defraud, concealed or misrepresented any material fact or circumstance relating to the insurance."
Before issuing the policy, Selective appraised the property and assigned a $1.6 million value to the home. The insured then filed a claim with his original insurer and received $510,787.23 for actual cash value of his loss. Neither the terms of this settlement nor this new policy with Selective required the insured to repair all of the 2010 damage.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Court of Appeals Finds Additional Insured Coverage Despite “Care, Custody or Control” Exclusion
September 30, 2019 —
Garret Murai - California Construction Law BlogWhen things go wrong on a construction project it’s often a scramble of finger pointing. In McMillin Homes Construction, Inc. v. National Fire & Marine Insurance Company, Case No. D074219 (June 5, 2019), the California Court of Appeals for the 4th District considered whether an additional insured exclusion, excluding “property in the care, custody or control of the additional insured,” precluded a duty to defend by an insurer.
McMillin Homes Construction, Inc. v. National Fire & Marine Insurance Company
McMillin Homes Construction, Inc. was the developer and general contractor on a residential project known as Auburn Lane in Chula Vista, California. McMillin subcontracted with Martin Roofing Company, Inc. to perform roofing work. Under the subcontract, Martin was required to obtain commercial general liability insurance naming McMillin as an additional insured.
The commercial general liability insurance policy secured by Martin was issued by National Fire and Marine Insurance Company. As is typical, the policy covered “property damage” and “personal injury” arising out of an “occurrence” during the policy period. McMillin was covered as additional insured under ISO endorsement form CG 20 09 03 97.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel, Rosen, Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
“You Can’t Climb a Tile Wall”
February 03, 2025 —
Daniel Lund III - Lexology… or, in certain circumstances, walk on a tile floor.
A Louisiana appellate court reversed a trial court’s summary judgment in favor of a project architect in a case involving liability for a slip-and-fall incident at a pool area and a casino in Lake Charles, Louisiana. The plaintiff alleged that travertine tile on which she slipped was unsuitable for wet areas, thus failing to meet the necessary safety standards.
The architect – the professional of record for the original design of the casino – attempted to deflect responsibility by arguing that a landscape architect which specified the travertine was an independent contractor and thus solely liable for any issues related to the tile. Ultimately, however, the court held that the absence of a contract between the architect and landscape architect left unresolved questions about the nature of their relationship and the degree of control the former exercised over the work of the latter.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Georgia Court of Appeals Holds That Insurer Must Defend Oil Company Against Entire Lawsuit
October 07, 2019 —
Lawrence J. Bracken II, Michael S. Levine & Alexander D. Russo - Hunton Andrews KurthThe Georgia Court of Appeals recently affirmed a grant of summary judgment in favor of Mountain Express Oil Company on its breach of contract claim against liability insurer, Southern Trust Insurance Company. Empire Petroleum brought claims against Mountain Express for breach of contract, injunctive relief, and libel or slander, among others. Mountain Express sought a defense to that lawsuit under its insurance policy with Southern Trust. Southern Trust contended that the insurance policy did not cover Empire’s non-libel/slander claims, and therefore reimbursed Mountain Express for only a portion of its attorneys’ fees. After the Empire lawsuit settled, Mountain Express sued Southern Trust for breach of contract and bad faith for failing to pay the remaining defense costs, contending that Southern Trust had a duty to defend the entire lawsuit.
The Georgia Court of Appeals affirmed the trial court’s grant of summary judgment to Mountain Express on its breach of contract claim. Citing policy language stating that “[the insurer] will have the right and duty to defend the insured against any ‘suit’ seeking those damages,” the court held that Southern Trust was obligated to defend the entire lawsuit. Specifically, in reaching that conclusion, the court noted that by agreeing to defend any “suit,” not any “claim,” Southern Trust obligated itself to defend the entire lawsuit if any claim could be covered under the policy. Accordingly, Southern Trust breached the policy when it only agreed to defend some of the claims against its insured.
Reprinted courtesy of
Lawrence J. Bracken II, Hunton Andrews Kurth,
Michael S. Levine, Hunton Andrews Kurth and Alexander D. Russo, Hunton Andrews Kurth
Mr. Bracken may be contacted at lbracken@HuntonAK.com
Mr. Levine may be contacted at mlevine@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Court Sharpens The “Sword” And Strengthens The “Shield” Of Contractors’ License Law
July 24, 2023 —
Kyle S. Case - ConsensusDocsPerforming construction work without the necessary license can have significant repercussions on a contractor’s business. California in particular has become known for its imposition of “strict and harsh” penalties for a contractor’s failure to maintain proper licensure. In the realm of public works projects, any contract with an unlicensed contractor is deemed void. See Business & Professions Code Section 7028.15(e). On private projects, California’s Contractors’ License Law prohibits contractors from maintaining any action to recover payment for their work, and more severe, may require a contractor to disgorge all funds paid to it for performing unlicensed work. See Business & Professions Code Section 7031). These methods of deterrence are referred to as the “shield” and “sword” of the Contractors’ State License Law. Loranger v. Jones, 184 Cal. App. 4th 847, 854 (2010).
In any discussion surrounding licensure, it is important to review the language of the Business and Professions Code (“Bus. & Prof.”). Section 7031(a) states:
Except as provided in subdivision (e), no person engaged in the business or acting in the capacity of a contractor, may bring or maintain any action, or recover in law or equity in any action, in any court of this state for compensation for the performance of any act or contract where a license is required by this chapter without alleging that they were a duly licensed contractor at all times during the performance of that act or contract regardless of the merits of the cause of action brought by the person…
Read the court decisionRead the full story...Reprinted courtesy of
Kyle S. Case, Watt, Tieder, Hoffar & Fitzgerald LLPMr. Case may be contacted at
kcase@watttieder.com
Enforcement Of Contractual Terms (E.G., Flow-Down, Field Verification, Shop Drawing Approval, And No-Damage-For-Delay Provisions)
May 04, 2020 —
David Adelstein - Florida Construction Legal UpdatesWhat you contractually agree to matters, particularly when you are deemed a sophisticated entity. This means you can figuratively live or die by the terms and conditions agreed to. Don’t take it from me, but it take it from the Fourth Circuit’s decision in U.S. f/u/b/o Modern Mosaic, Ltd. v. Turner Construction Co., 2019 WL 7174550 (4th Cir. 2019), where the Court started off by stressing, “One of our country’s bedrock principles is the freedom of individuals and entities to enter into contracts and rely that their terms will be enforced.” Id. at *1.
This case involved a dispute between a prime contractor and its precast concrete subcontractor on a federal project. The subcontractor filed a Miller Act payment bond lawsuit. The trial court ruled against the subcontractor based on…the subcontract’s terms! So, yes, what you contractually agree to matters.
Example #1 – The subcontractor fabricated and installed precast concrete panels per engineering drawings. However, the parking garage was not built per dimensions meaning the panels it fabricated would not fit. The subcontractor had to perform remedial work on the panels to get them to fit. The subcontractor pursued the prime contractor for these costs arguing the prime contractor should have field verified the dimensions. The problem for the subcontractor, however, was that the subcontract required the subcontractor, not the prime contractor, to field verify the dimensions. Based on this language that required the subcontractor to field verify existing conditions and take field measurements, the subcontractor was not entitled to its remedial costs (and they were close to $1 Million). Furthermore, and of importance, the Court noted that the subcontract contained a flow down provision requiring the subcontractor to be bound by all of the terms and conditions of the prime contract and assume those duties and obligations that the prime contractor was to assume towards the owner. While this flow-down provision may often be overlooked, here it was not, as it meant the subcontractor was assuming the field verification duties that the prime contractor was responsible to perform for the owner.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
California Clarifies Its Inverse Condemnation Standard
December 30, 2019 —
Gus Sara - The Subrogation StrategistIn City of Oroville v. Superior Court, 446 P.3d 304 (Cal. 2019), the Supreme Court of California considered whether the City of Oroville (City) was liable to a dental practice for inverse condemnation damages associated with a sewer backup. The court held that in order to establish inverse condemnation against a public entity, a property owner must show that an inherent risk in the public improvement was a substantial cause of the damage. Since the dental practice did not have a code-required backwater valve — which would have prevented or minimized this loss — the court found that the city was not liable because the sewage system was not a substantial cause of the loss. This case establishes that a claim for inverse condemnation requires a showing of a substantial causal connection between the public improvement and the property damage. It also suggests that comparative negligence can be a defense to inverse condemnation claims.
In December 2009, a dental practice, WGS Dental Complex (WGS), located in the City, incurred significant water damage as a result of untreated sewage from the City’s sewer main backing up into WGS’ building. WGS submitted a claim to its insurance carrier, The Dentists Insurance Company (TDIC) and, in addition, sued the City for its uninsured losses, alleging inverse condemnation and nuisance. TDIC joined the litigation, alleging negligence, nuisance, trespass and inverse condemnation. Under California law, when a government entity fails to recognize that an action or circumstance essentially amounts to a taking for public use, a property owner can pursue an inverse condemnation action for compensation. The City filed a cross-complaint against WGS for failing to install a code-required backwater valve on their lateral sewer line, which would have prevented or minimized the backup.
The City filed a motion for summary judgment, which the trial court denied. WGS then sought a judicial determination on the issue of inverse condemnation. The City presented evidence that the sewage system was designed in accordance with industry standards, and that WGS failed to comply with the City’s plumbing code by failing to install a backwater valve on its private sewer lateral. The trial court found the City liable for inverse condemnation because the blockage that caused the backup originated in the City’s sewer line. The court held that the blockage was an inherent risk of sewer operation. The Court of Appeals affirmed the decision, holding that the City would have had to prove that the WGS’s lack of a backwater valve was the sole cause of the loss in order to absolve itself of liability.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com