Graham & Who May Trigger The Need To Protest
December 23, 2023 —
Hugo Fraga - Ahlers Cressman & Sleight PLLCOn May 30, 2023, the Washington Court of Appeals, Division I, issued a decision that appears to expand a contractor’s obligation with respect to WSDOT notice and claim procedures. In
Graham Contracting, Ltd. v. City of Federal Way, No. 83494-1-I, 2023 WL 3721171 (Wash. Ct. App. May 30, 2023) (Unpublished), the Court held that under the 2016 WSDOT Standard Specifications for Road, Bridge, and Municipal Construction (“Standard Specifications”), a Contractor must protest the actions of not only the “Engineer” but also the actions of any person or organization acting on behalf of the Owner.
This case arises out of a public construction contract in which Graham Contracting Ltd (“Graham”) built a multi-million dollar roadway improvement for the City of Federal Way along a stretch of Pacific Highway. The appeal was from the trial court’s granting of the City’s motion for summary judgment to dismiss claims by Graham for extra time and money due to delays and impacts to Graham’s construction of the Project.
Read the court decisionRead the full story...Reprinted courtesy of
Hugo Fraga, Ahlers Cressman & Sleight PLLCMr. Fraga may be contacted at
hugo.fraga@acslawyers.com
Architect, Engineer, and Design Professional Liens in California: A Different Animal than the Mechanics’ Lien
August 15, 2022 —
William L. Porter - Porter Law GroupMost in the construction industry are familiar with the rules governing California mechanics’ liens. They know that the Preliminary Notice of Civil Code Section 8034 and 8200-8216 is an important foundational prerequisite document and that the deadline to record a mechanics’ lien is generally triggered by events occurring at the end of construction, including completion of the work of improvement and/or the recording of the notice of completion or notice of cessation. Most of these rules are found in California Civil Code sections 8160-8494.
While architects, engineers and other design professionals are certainly entitled to pursue a mechanics’ lien at the end of a construction project when they are unpaid for their work, unless they also consider the remedy available to them under the California “design professional lien,” they are missing a powerful opportunity to preserve the right to payment only available to architects, engineers, and design professionals.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
No Interlocutory Appeals of "Garden-Variety" Contract Disputes
March 12, 2015 —
Jesse Howard Witt – Acerbic WittColorado’s new procedure for interlocutory appeals has its limits. In the recent decision of Rich v. Ball Ranch Partnership, ___ P.3d ___, 2014 COA 6 (2015), the Colorado Court of Appeals held that Appellate Rule 4.2 does not permit interlocutory review of questions of law in “garden-variety” or “run-of-the-mill” contract disputes. This resolves a subtle question that has been lingering since Colorado first created the interlocutory appeal process four years ago.
Prior to 2011, Colorado did not permit civil litigants to seek appellate review prior to final judgment, except in a small handful of situations. As I discussed in an article at the time, this changed with the passage of C.R.S. § 13-4-102.1 and the adoption of Rule 4.2, which granted the court of appeals discretion to permit the immediate appeal of certain district court orders. These provisions allowed parties to seek interlocutory review of orders before the conclusion of a case if a district court could certify that (1) immediate review might promote a more orderly disposition or establish a final disposition of the litigation, and (2) the order involved a controlling and unresolved question of law. The rule was patterned after 28 U.S.C. § 1292(b), which provides similar relief in the federal courts.
Read the court decisionRead the full story...Reprinted courtesy of
Jesse Howard Witt, The Witt Law FirmMr. Witt welcomes comments at www.acerbicwitt.com
Florida SB 2022-736: Construction Defect Claims
February 07, 2022 —
Kelly A. Johnson - Saxe Doernberger & Vita, P.C.*Special thank you to SDV Law Clerk Iliriana Fteja for contributing to this article.
A new bill (SB 2022-736) was recently introduced to the Florida Senate. The proposed amendments to the statutes of limitations and repose could significantly impact construction defect claims by effectively creating additional exposure to contractors and insurance carriers.
The proposed bill requires all actions founded on the design, planning, or construction of an improvement to real property to be commenced within four years after the time to commence an action begins. Under the proposed amendment, the time to commence an action runs from the date of actual possession by the owner, the date of the issuance of a certificate of occupancy, the date of abandonment of construction if not completed, or the date of completion of the contract or termination of the contract between the professional engineer, registered architect, or licensed contractor and their employer. This provision would effectively alter the time to commence an action to whichever triggering event is earliest instead of the latest triggering event per the previous statute.
Read the court decisionRead the full story...Reprinted courtesy of
Kelly A. Johnson, Saxe Doernberger & Vita, P.C.Ms. Johnson may be contacted at
KJohnson@sdvlaw.com
Endorsements Do Not Exclude Coverage for Wrongful Death Claim
August 30, 2017 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer's motion for summary judgment, attempting to bar coverage under two endorsements for a wrongful death suit, was denied. Essex Ins. Co. v. FD Event Co., LLC, 2017 U.S. Dist. LEXIS 124400 (C.D. Calif. July 25, 2017).
FD Event owned an amusement attraction known as Free Drop, which was operated at county fairs and festivals. Participants paid an admission fee to FD Event in order to jump from a scaffold structure onto an inflatable airbag below.
FD Event had a policy with Essex. When securing the policy, FD Event understood that there was no coverage for amusement devices, inflatables, rides or animals. 28th Event, who ran the San Bernardino County Fair, was an additional insured on the policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly - Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Corrective Action Protest Grounds for GSA Schedule Federal Construction Contractors
September 09, 2024 —
Marissa L. Downs - The Dispute ResolverA contract awarded, protested, terminated, appealed, then reinstated. It’s no secret that federal construction procurements are plagued with uncertainty. From delays, constructive suspensions, compromised supply chains, the litigation-laden critical path method, and the mandate for all construction materials used in federally funded projects for infrastructure to be produced in the United States under the Build America, Buy America Act (BABAA) (to name just a few traditional and emerging favorites), just one of these issues could fill the rest of anyone’s month with substantive research. To add one more, which is entirely unique to bid protests, federal contractors–including construction contractors–listed in a General Service Administration (GSA) Schedule may have new grounds to have a contract award reinstated that was terminated by a federal agency pending a GAO decision.
GAO Protest
An initial GAO protest filed by Deloitte & Touche LLP (Deloitte) argued that the National Geo-Spatial Intelligence Agency (Agency) wrongfully made an award to Kearney & Company, P.C. (Kearney) when the Agency: (1) improperly evaluated quotes; and (2) failed to conduct a proper best-value tradeoff analysis. At issue was a competed task order with Kearney under a GSA FSS multiple-award contract. Before the GAO issued an opinion, however, it held an unrecorded predictive-outcome conference with Deloitte and Kearney where the only mutual consensus was the likely ineligibility of all offerors for the relevant award. The Agency subsequently elected to take corrective action, terminating Kearney’s contract award for convenience, amending the solicitation to avoid issues (including undisputed issues) addressed in the GAO protest. After the Agency adopted their corrective action, the GAO protest was dismissed as academic and moot.
Read the court decisionRead the full story...Reprinted courtesy of
Marissa L. Downs, Laurie & Brennan, LLPMs. Downs may be contacted at
mdowns@lauriebrennan.com
Construction Spending Had Strongest Increase in Four Years
January 13, 2014 —
CDJ STAFFThe Commerce Department announced a 1% gain in construction spending, from October to November, which is the biggest gain that construction has seen since March 2009, according to The Spokesman-Review. The gain brought construction spending to an adjusted annual rate of $934.4 billion.
The Spokesman-Review further reports that residential construction rose 1.9% in November, while commercial construction rose 2.7%. Government construction, on the other hand, fell 1.8%.
Read the court decisionRead the full story...Reprinted courtesy of
No Coverage for Additional Insured for Construction Defect Claim
July 02, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe Seventh Circuit affirmed the district court's grant of summary judgment to the insurers, finding there was no coverage for the additional insured on a construction defect claim. St. Paul Guardian Ins. Co. v. Walsh Construction. Co., 2024 U.S. App. LEXIS 10285 (7th Cir. April 29, 2024).
The City of Chicago hired Walsh Construction Company as general contractor for the Facade and Circulation Enhancement (FACE) project at O'Hare International Airport. The FACE project involved building and installing a new canopy for Terminals 1, 2 and 3. The project also called for the construction of a steel and glass curtain wall that would be integrated with the curtain wall at Terminals 2 and 3. Walsh contracted with Carlo Steel Corporation to manufacture the steel and curtain wall. Carlo, in turn, subcontracted with LB Steel, LLC to manufacture and install the steel elements of the wall, which included steel columns, hammer heads and box girders. The subcontract between Carlo and LB Steel included an indemnity provision that required LB Steel to indemnify Carlo and Walsh for any property damage resulting from LB Steel's negligent performance.
Read the court decisionRead the full story...Reprinted courtesy of